<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <Name>CWP-700 Composite Wing Panel Production Program WBS.mpp</Name>
  <Title>CWP-700 Composite Wing Panel Production Program WBS</Title>
  <Company>Acme Aerostructures</Company>
  <Manager>C. Tyrrell</Manager>
  <CalendarUID>1</CalendarUID>
  <StartDate>2026-02-02T08:00:00</StartDate>
  <FYStartDate>1</FYStartDate>
  <CurrentDate>2026-02-02T08:00:00</CurrentDate>
  <MinutesPerDay>480</MinutesPerDay>
  <MinutesPerWeek>2400</MinutesPerWeek>
  <DaysPerMonth>20</DaysPerMonth>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>

  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <WeekDays>
        <WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay>
        <WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay>
      </WeekDays>
    </Calendar>
  </Calendars>

  <Tasks>
    <Task>
      <UID>0</UID>
      <ID>0</ID>
      <Name>Phase 1: Qualification &amp; First Article</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1</WBS>
      <OutlineLevel>1</OutlineLevel>
      <OutlineNumber>1</OutlineNumber>
      <Start>2026-02-02T08:00:00</Start>
      <Finish>2026-06-09T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>1</Summary>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Production tooling design</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.1</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.1</OutlineNumber>
      <Start>2026-02-02T08:00:00</Start>
      <Finish>2026-03-09T17:00:00</Finish>
      <Duration>PT208H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Production tooling fabrication</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.2</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.2</OutlineNumber>
      <Start>2026-03-10T08:00:00</Start>
      <Finish>2026-04-22T17:00:00</Finish>
      <Duration>PT256H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>1</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Raw material qualification (PPAP)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.3</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.3</OutlineNumber>
      <Start>2026-02-02T08:00:00</Start>
      <Finish>2026-02-25T17:00:00</Finish>
      <Duration>PT144H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Initial composite layup (tooling qualification run, S/N 0001)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.4</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.4</OutlineNumber>
      <Start>2026-04-23T08:00:00</Start>
      <Finish>2026-04-30T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>2</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>NDT ultrasonic scan (initial run)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.5</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.5</OutlineNumber>
      <Start>2026-05-01T08:00:00</Start>
      <Finish>2026-05-05T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Quality inspection (initial run, dimensional + visual)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.6</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.6</OutlineNumber>
      <Start>2026-05-06T08:00:00</Start>
      <Finish>2026-05-11T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>FAI full dimensional layout</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.7</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.7</OutlineNumber>
      <Start>2026-05-12T08:00:00</Start>
      <Finish>2026-05-18T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>FAI documentation (AS9102 Form 1/2/3 package)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.8</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.8</OutlineNumber>
      <Start>2026-05-19T08:00:00</Start>
      <Finish>2026-05-22T17:00:00</Finish>
      <Duration>PT32H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>MRB-001 disposition (edge-trim rework)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.9</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.9</OutlineNumber>
      <Start>2026-05-25T08:00:00</Start>
      <Finish>2026-05-29T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Rework and FAI re-inspection</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.10</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.10</OutlineNumber>
      <Start>2026-06-01T08:00:00</Start>
      <Finish>2026-06-08T17:00:00</Finish>
      <Duration>PT48H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>9</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Milestone Gate: FAI Accepted, Customer Source Inspection Witness</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>1.11</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>1.11</OutlineNumber>
      <Start>2026-06-09T08:00:00</Start>
      <Finish>2026-06-09T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>1</Milestone>
      <PredecessorLink>
        <PredecessorUID>10</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Phase 2: Production Ramp &amp; Steady-State</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2</WBS>
      <OutlineLevel>1</OutlineLevel>
      <OutlineNumber>2</OutlineNumber>
      <Start>2026-06-10T08:00:00</Start>
      <Finish>2027-06-14T17:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>1</Summary>
      <Milestone>0</Milestone>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Production release authorization</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.1</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.1</OutlineNumber>
      <Start>2026-06-10T08:00:00</Start>
      <Finish>2026-06-10T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>11</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Composite layup production ramp (3-technician rotation)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.2</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.2</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-06-07T17:00:00</Finish>
      <Duration>PT2064H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>NDT inspection (production rate)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.3</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.3</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-05-24T17:00:00</Finish>
      <Duration>PT1984H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Quality inspection (production rate, 2-inspector rotation)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.4</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.4</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-05-24T17:00:00</Finish>
      <Duration>PT1984H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>MRB case management (MRB-002 through MRB-005)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.5</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.5</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-03-17T17:00:00</Finish>
      <Duration>PT1600H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Supplier PPAP maintenance &amp; incoming lot verification</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.6</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.6</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-05-31T17:00:00</Finish>
      <Duration>PT2024H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Purchase order execution &amp; supplier scheduling</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.7</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.7</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-03-17T17:00:00</Finish>
      <Duration>PT1600H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Preventive maintenance program (layup fixture, post MRB-004)</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.8</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.8</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2026-06-24T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Program status reporting &amp; RAIDD log maintenance</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.9</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.9</OutlineNumber>
      <Start>2026-06-11T08:00:00</Start>
      <Finish>2027-05-31T17:00:00</Finish>
      <Duration>PT2024H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Milestone: Program Closeout</Name>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>2.10</WBS>
      <OutlineLevel>2</OutlineLevel>
      <OutlineNumber>2.10</OutlineNumber>
      <Start>2027-06-08T08:00:00</Start>
      <Finish>2027-06-14T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Summary>0</Summary>
      <Milestone>0</Milestone>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>17</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>18</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <CrossProject>0</CrossProject>
      </PredecessorLink>
    </Task>
  </Tasks>

  <Resources>
    <Resource>
      <UID>1</UID>
      <ID>1</ID>
      <Name>A. Whitfield</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>2</UID>
      <ID>2</ID>
      <Name>S. Pham</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>3</UID>
      <ID>3</ID>
      <Name>K. Rutherford</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>4</UID>
      <ID>4</ID>
      <Name>L. Vance</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>5</UID>
      <ID>5</ID>
      <Name>B. Solis</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>6</UID>
      <ID>6</ID>
      <Name>M. Osei</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>7</UID>
      <ID>7</ID>
      <Name>R. Kessler</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>8</UID>
      <ID>8</ID>
      <Name>C. Tyrrell</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>9</UID>
      <ID>9</ID>
      <Name>T. Alvarado</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>10</UID>
      <ID>10</ID>
      <Name>C. Okwuosa</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>11</UID>
      <ID>11</ID>
      <Name>N. Vasquez</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>12</UID>
      <ID>12</ID>
      <Name>J. Ferraro</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>13</UID>
      <ID>13</ID>
      <Name>R. Bianchi</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
    <Resource>
      <UID>14</UID>
      <ID>14</ID>
      <Name>D. Okafor</Name>
      <Type>1</Type>
      <MaxUnits>1</MaxUnits>
    </Resource>
  </Resources>

  <Assignments>
    <Assignment>
      <UID>1</UID>
      <TaskUID>1</TaskUID>
      <ResourceUID>1</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>2</UID>
      <TaskUID>2</TaskUID>
      <ResourceUID>1</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>3</UID>
      <TaskUID>3</TaskUID>
      <ResourceUID>2</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>4</UID>
      <TaskUID>4</TaskUID>
      <ResourceUID>3</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>5</UID>
      <TaskUID>5</TaskUID>
      <ResourceUID>4</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>6</UID>
      <TaskUID>6</TaskUID>
      <ResourceUID>5</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>7</UID>
      <TaskUID>7</TaskUID>
      <ResourceUID>6</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>8</UID>
      <TaskUID>8</TaskUID>
      <ResourceUID>7</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>9</UID>
      <TaskUID>9</TaskUID>
      <ResourceUID>7</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>10</UID>
      <TaskUID>10</TaskUID>
      <ResourceUID>3</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>11</UID>
      <TaskUID>10</TaskUID>
      <ResourceUID>5</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>12</UID>
      <TaskUID>11</TaskUID>
      <ResourceUID>8</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>13</UID>
      <TaskUID>13</TaskUID>
      <ResourceUID>8</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>14</UID>
      <TaskUID>14</TaskUID>
      <ResourceUID>3</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>15</UID>
      <TaskUID>14</TaskUID>
      <ResourceUID>9</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>16</UID>
      <TaskUID>14</TaskUID>
      <ResourceUID>10</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>17</UID>
      <TaskUID>15</TaskUID>
      <ResourceUID>4</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>18</UID>
      <TaskUID>16</TaskUID>
      <ResourceUID>5</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>19</UID>
      <TaskUID>16</TaskUID>
      <ResourceUID>11</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>20</UID>
      <TaskUID>17</TaskUID>
      <ResourceUID>12</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>21</UID>
      <TaskUID>18</TaskUID>
      <ResourceUID>2</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>22</UID>
      <TaskUID>19</TaskUID>
      <ResourceUID>13</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>23</UID>
      <TaskUID>20</TaskUID>
      <ResourceUID>6</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>24</UID>
      <TaskUID>21</TaskUID>
      <ResourceUID>14</ResourceUID>
      <Units>1</Units>
    </Assignment>
    <Assignment>
      <UID>25</UID>
      <TaskUID>22</TaskUID>
      <ResourceUID>8</ResourceUID>
      <Units>1</Units>
    </Assignment>
  </Assignments>
</Project>