← Agile/Scrum Suite 14 · Metrics & Reporting

Sprint Burndown Chart — Sprint 5

Download Excel

Combined story points remaining across both teams, Sprint 5 (Mar 16–27) — the Release 1 (MVP) launch sprint. Shown as an actual burndown, not a smoothed one, so the flat stretches (no story closures that day) are visible on purpose.

Ideal burndown Actual burndown
0 24 48 D0D1D2 D3D4D5 D6D7D8 D9D10
Day 1–2: Flat — team finishing carryover triage from Sprint 4 UAT before new closures began.
Day 5–6: Flat — release hardening/regression testing day, no story closures logged even though work was active.
Day 10: Ends at 2 pts remaining, not 0 — MCM-181 (rollback runbook) was completed manually outside the board rather than tracked as a closed story; see Sprint Backlogs for detail.