← Agile/Scrum Suite 34 · Metrics & Reporting

Program Dashboard

StatusClosed — Complete
As OfMay 15, 2026
Prepared ByC. Tyrrell
Overview

Program Health at a Glance

Overall
Green
Closed on target
Schedule
Green
On time
Scope
Green
98.5% delivered
Budget
Green
-2.2% to baseline
Quality
Green
0 critical defects

Release Timeline Sprint 0 → Closeout

Kickoff
Jan 5
Release 1
(MVP)
Mar 27
Release 2
(Cutover)
May 8
Closeout
May 15

All milestones met on original target dates — no schedule slips across the 8-sprint program.

Budget Final

Spend to Date$1.81M of $1.85M
Contingency remaining$106K of $127K
Variance to baseline: -2.2% 2 approved CRs absorbed within contingency

Change Control 3 CRs, all Implemented

3
Implemented
Detail

Drill-Down: Sprint Progress, RAIDD & Readiness

Sprint-by-Sprint Delivery 8 sprints · 337/342 pts

Sprint 1
100%Closed
Sprint 2
100%Closed
Sprint 3
100%Closed
Sprint 4
100%Closed
Sprint 5
100%Release 1 shipped
Sprint 6
100%Closed
Sprint 7
100%Closed
Sprint 8
100%Release 2 / Cutover

RAIDD Summary Final

CategoryCountNote
Risks4All closed
Assumptions3All held true
Issues21 closed, 1 accepted
Dependencies3All resolved
Decisions5All approved

Vendor Readiness

VendorStatus
PulseConnect (video SDK)SLA met, renewal recommended
Vantix (legacy, offboarded)Decommissioned, deletion pending cert.

Resource Utilization Program average

C. TyrrellProduct Owner & Delivery Lead
100%
J. MarshScrum Master, Falcon
100%
R. OkaforScrum Master, Anchor
100%
D. WhitfieldEngineering Lead, Falcon
100%
A. SinghEngineering Lead, Anchor
100%
K. AlvareziOS Developer
95%
S. ParkAndroid Developer
95%
R. KimBackend/API Developer
100%
N. OseiQA Engineer, Falcon
90%
Dr. L. NguyenCMIO (advisory)
10%
T. BranniganCompliance Director (advisory)
10%
M. DelacroixExecutive Sponsor
5%