1. Why This Document Exists
On a commercial program, the people who can tell you what to do are mostly in your own organization. On a federal task order they are not. The customer holds contractual authority and sits entirely outside the contractor's chain of command, and the single most expensive mistake available on a program like this is taking direction from someone who cannot legally give it.
So this document is organized around a boundary rather than a hierarchy. It names what the contractor owns, what the Government owns, and — the part that costs money when it is misunderstood — which Government person can change the contract and which cannot.
2. The Shape of the Organization
Thirty-five people, all contractor-side, all onshore. Unlike the commercial programs in this portfolio, the Task Order PM has real reporting authority over most of the team — this is a delivery organization the firm staffed against a contract, not a matrixed borrow from functional departments. The constraint is not authority over people; it is that almost nothing about scope, schedule or price can be changed without a signature the program does not hold.
| Function | Who | Owns | Does not own |
|---|---|---|---|
| Task Order PM | C. Tyrrell | Delivery, schedule, cost, CDRL submission, and every commitment made to the Government | Scope. Price. Period of performance. All three require a modification. |
| Back-End Development | H. Ibrahim + 5 | Build against the PWS, technical design, unit test | Whether a requirement is in the PWS — that reading belongs to the PM and, in dispute, to the CO |
| Quality Assurance | N. Castellano + 5 | Test execution and the evidence package behind each CDRL | Government acceptance — QA proves conformance, the COR accepts |
| Data Migration | P. Ochieng, R. Talbot | Extract, transform, load and reconciliation from the legacy benefits system | Legacy data quality, which is Government-furnished and inherited as-is |
| 508 / Accessibility | P. Duvall, L. Anders | Conformance testing and the VPAT evidence | The standard itself — Section 508 is law, not a negotiable requirement |
| Compliance / Privacy | K. Ashworth | Privacy impact analysis, PII handling review, ATO evidence support | The ATO decision — see §5 |
| Technical Writing | E. Marchand | CDRL documents to the format the PWS specifies | Whether a CDRL is acceptable — the COR decides that |
3. Governance — Who Decides
Three authorities, and confusing any two of them is expensive.
| Authority | Who | Can | Cannot |
|---|---|---|---|
| Contracting Officer | A. Reyes | Modify scope, price or period of performance; execute an SF-30; determine an REA; terminate | — (this is the Government's full authority) |
| COR | M. Whitcombe | Administer technically, monitor performance, inspect and accept deliverables, raise concerns to the CO | Direct changed work. Waive a requirement. Authorize overtime. Approve anything that costs money. |
| Task Order PM | C. Tyrrell | Everything inside the awarded scope: sequencing, staffing, method, internal risk | Anything that alters what was awarded |
4. The Functions, One at a Time
The Task Order PM is accountable for delivery and is the single contractual voice to the Government. That singularity matters more here than in commercial work: when several contractor staff talk to several Government staff, direction arrives through side channels and nobody can later establish what was authorized. Every scope-adjacent conversation routes through the PM, and every one that matters is confirmed in writing.
Quality Assurance proves conformance; it does not grant acceptance. N. Castellano's team assembles evidence that a CDRL meets the PWS, and the COR accepts or rejects. ⚠ That separation protects the contractor as much as the Government — a documented acceptance is what closes the door on a later claim that a deliverable was never adequate.
Data Migration inherits Government-furnished data. The team can profile it, report defects, and reconcile what moved; it cannot make a legacy record correct that was wrong when it was written. Scope is stated as what will be reconciled, never as what will be correct — the same discipline the commercial suites use, but here the distinction has contractual consequences.
508 / Accessibility is the one function whose requirement nobody in either organization may relax. Section 508 is statute. The COR cannot waive it, the CO cannot negotiate it away, and a VPAT that overstates conformance is a misrepresentation rather than an optimistic estimate.
5. What the Program Cannot Be Directed To Do
The Authorizing Official and the ATO. The Authority to Operate is a Government risk decision. The contractor supplies evidence and remediates findings; it does not influence the outcome and cannot be instructed to shortcut it. When the ATO ran 34 days late, the correct response was to notify in writing on day three and claim the delay — see REA-002, which was granted in full.
Government QA and inspection. The Government may inspect at any time. The program does not schedule, filter or prepare that inspection beyond keeping evidence current.
Statutory requirements. Section 508, privacy law, and records retention are not requirements the parties agreed to and therefore cannot un-agree.
6. How This Differs From the Commercial Programs Here
| Question | Federal (this suite) | Commercial (PM, Agile) |
|---|---|---|
| Who approves a change? | The Contracting Officer, by signature on an SF-30 | An internal board that can be persuaded |
| What happens to a refused change? | It never becomes a modification and leaves no trace unless separately recorded | It sits in the change log as a declined CR |
| Who owns the requirement? | The PWS. It was competed and awarded; nobody may quietly reinterpret it | The sponsor, who may change their mind |
| Who can direct the team? | The Task Order PM. Not the customer. | Functional managers, and the program only by influence |