Lighthouse Financial Services Company — The conditions under which Beacon Index Advantage does not launch on 06 March 2028, who decides each one, and what happens when it fires. Adopted for verification at Gate 4 on 24 February 2028, 11 days before launch.
1. What This Document Is Actually For
This program makes that harder than usual, and it is better to say so here than to discover it in February 2028. The launch date has never moved. It survived the Gate 1 recycle, which was absorbed by compressing Stage 2 from 46 weeks to 40 rather than by moving 06 March 2028. That is a real achievement, and it is also a pattern.
So the criteria below are written as no-go conditions with named deciders and pre-committed responses. Not a checklist of things that should be true — a list of things that, if false, stop something.
2. The No-Go Criteria
| ID | Domain | Condition | Decider | Effect |
|---|---|---|---|---|
| NG-01 | Regulatory | Fewer than the agreed minimum number of states approved, or neither large non-Compact market approved. | Gate Review Board | Absolute no-go |
| NG-02 | Regulatory | Any approved state's filing conditions differ materially from the illustrated product. | General Counsel | Partial — hold back scope |
| NG-03 | Product / systems | Any open severity-1 defect in issue, servicing or illustration. | Platform Delivery Lead | Absolute no-go |
| NG-04 | Product / systems | A severity-2 defect whose workaround is not documented, staffed and accepted by Operations. | Head of Operations | Absolute no-go |
| NG-05 | Risk | Hedging program not live and reconciled against a shadow book for a full month. | CFO, with CRO consulted | Absolute no-go |
| NG-06 | Risk | Reinsurance treaty not executed, or executed on terms that change the capital treatment assumed in pricing. | Chief Actuary | Absolute no-go |
| NG-07 | Operations | End-to-end cycle not completed by trained operations staff without build-team intervention. | Head of Operations | Absolute no-go |
| NG-08 | Distribution | Advisor training completion below the agreed threshold in any channel intended for launch. | Head of Distribution | Partial — hold back scope |
| NG-09 | Distribution | Wholesaler coverage materially below plan at launch. | Head of Distribution | Not a no-go |
Absolute stops the launch entirely. Partial holds back a state or a channel and lets the rest proceed — which is only viable because the product launches into a footprint rather than a single market. The distinction is doing real work: without it, every regulatory or distribution imperfection becomes a full-launch argument.
3. Pre-Committed Responses
Each criterion carries its response now, so that the response is not being invented by the people under the most pressure to avoid it.
| ID | Pre-committed response |
|---|---|
| NG-01 | Launch is deferred to the next viable window. The threshold itself is still undecided — see §4. |
| NG-02 | That state is withheld from launch and activated after remediation. Launch proceeds elsewhere. |
| NG-03 | Absolute no-go. No workaround is acceptable for an S1 in these three paths. |
| NG-04 | Treated as S1 until the workaround is staffed. Staffing is the test, not documentation. |
| NG-05 | Absolute no-go. The guarantee cannot be sold before it can be hedged. |
| NG-06 | No-go if capital treatment changes; the business case returns to a gate. |
| NG-07 | Absolute no-go. A product only the build team can operate is not launched, it is demonstrated. |
| NG-08 | That channel is held back. Launch proceeds in channels that are ready. |
| NG-09 | Not a no-go. It is a volume risk, disclosed and monitored — see §5 for why this one is deliberately excluded. |
4. The Decision This Document Cannot Make
This is stated rather than papered over because the alternative is worse. A readiness document that quietly assumed a threshold would give the appearance of a decision without the substance of one, and the gap would surface at exactly the moment it could not be closed calmly — with a trained sales force, a marketing date and a Board that has been told the program is ready.
Action: the Chair is tabling the threshold for decision at Gate 3 on 28 October 2027. If Gate 3 declines to set it, this document should record that the program has chosen to enter its launch window without a footprint rule.
5. What Is Deliberately Not a No-Go
A criteria list that includes everything important stops discriminating. Three items were considered and excluded.
| Considered | Why it is not a no-go |
|---|---|
| Wholesaler coverage below plan (NG-09) | Six were planned and four are committed. This is a volume risk — disclosed, monitored, and material to the business case — but launching with four wholesalers is a worse commercial outcome, not an unsafe one. Treating it as a no-go would put a distribution staffing question on the same footing as an unhedged guarantee. |
| Year 1 written commitments below target | Already true and already disclosed ($168,000,000 against $185,000,000). A no-go criterion that is already failing at the time of writing is not a criterion; it is a decision the program has already taken and should own openly. |
| Competitor launching in the same quarter | Outside the carrier's control and not a safety or compliance matter. It changes what launch is worth, not whether launch is possible. |
6. Verification and Timing
| When | What happens |
|---|---|
| Gate 4 — 24 Feb 2028 | Each criterion is certified by its named decider on evidence, not on assertion. Gate 4 is where launch readiness is judged; this document is its scoring instrument. |
| Gate 4 + 30 days | Re-confirmation of NG-03, NG-04 and NG-07 only — the three that can regress after certification because they depend on live systems and live people. |
| Launch minus 10 business days | Final confirmation by the Chair to the sponsor. No new criteria may be introduced at this point; a criterion invented in the final fortnight is an opinion with a deadline attached. |
| Launch — 06 Mar 2028 | First policy issued. This document is closed and BEN measurement begins. |
7. Gaps
| ID | Gap |
|---|---|
| LR-01 | NG-01's threshold is undecided. See §4. The most consequential criterion in the document currently names a number nobody has agreed. |
| LR-02 | No criterion has an escalation path if its decider says go and another disagrees. Each condition names one decider. Where two domains disagree — a partial-approval state that Distribution wants and Legal does not — the document is silent and it would land with the Chair, who has no vote. |
| LR-03 | “Advisor training completion below the agreed threshold” (NG-08) has the same problem as NG-01 in miniature — the threshold is referenced, not set. It is lower stakes and it is the same defect. |
| LR-04 | Nothing here can stop a launch after it has begun. These are pre-launch criteria. Once policies are being issued, withdrawal is a market-conduct and regulatory matter far outside this document, and no artifact in the program addresses it. |
Owned by C. Tyrrell, NPD Program Manager and Chair of the Gate Review Board, with each criterion certified by its named decider. Related: Master Test & Validation Strategy · Regulatory Filing Plan §4 · Gate Decision Framework · Benefits Realization Plan.