Program Dashboard

Download Word
Program timeline · status 16 Oct 2026Read the full story →
Harborline
Aug 2025
Cancelled
Gate 0
Feb 2026
Go
Stage 1
Business case
Gate 1
Apr 2026
Recycled
Gate 1
Jun 2026
Go w/ conditions
Stage 2
Development
You are here
Gate 2
Apr 2027
Gate 3
Oct 2027
Gate 4
Feb 2028
Launch
Mar 2028
Gate 5
Sep 2028

Lighthouse Financial Services Company — Program status as at 16 October 2026, week 18 of 41 in Stage 2, 167 days before Gate 2 convenes on 01 April 2027.

167
Days to Gate 2
18/41
Stage 2 weeks elapsed
39%
Stage 2 tranche spent
$13,672,000
Unreleased funding
2
Conditions open
1
Condition at risk

1. What this dashboard does not show, and why

Most program dashboards lead with percent complete and a cost/schedule performance index. This one shows neither, and the omission is the most important thing on the page.

There is no program-level baseline to measure against. Stage 3 and Stage 4 — $11,780,000 combined — are not authorized. A program-level CPI, SPI or percent-complete would be comparing real spend to a budget the Board has not approved, which is not a variance but a forecast wearing a variance's clothing. This is Decision D-10, and the Program Budget, the Weekly Status Report and this dashboard are all required to state it consistently.

So this dashboard reports on a decision, not on a delivery. “Are we on track?” presumes a track running to the end of the program; there is no such track, only track as far as the next gate. The question it answers instead is: will Gate 2 be able to decide, and on what evidence? Sections 3 and 4 are that answer; Section 2 is the one variance that can legitimately be computed.

2. The one legitimate variance — inside the released tranche

Performance within a released tranche is measurable, because the tranche is a real authorization with a real amount and a real window. Stage 2 released $11,640,000 at Gate 1 for a 41-week stage.

Stage 2 spend$4,538,000 of $11,640,000 — 39%
red mark = 44% of stage time elapsed-5% spend vs time

Spend is running 5% behind elapsed time. On a conventional program that would read as favorable. Here it is reported without a verdict attached, because two very different things produce the same number: work genuinely costing less than planned, and work not yet done. The Gate 2 must-meet trajectory at §3 is what distinguishes them — and it shows contract forms and hedging readiness both behind, which points at the second explanation.

Three stories, one number

Decomposed, the under-burn admits exactly three explanations, and this dashboard's design follows from the fact that the spend figure cannot rank them. Cheaper: the work is being done for less than planned — favorable, and the only reading a conventional RAG report would offer. Later: the work is behind, and the money will arrive with it — which on a stage already compressed to 41 weeks is the unfavorable reading. Lagged: the work is on pace and the invoices are not — noise, common early in a vendor-heavy stage where the Cordelane and Brightpath billing cycles trail delivery. The milestone evidence in §3 currently supports later for two workstreams, which is why this section will not print the word “favorable.”

Why the tranche is the wall

Notice what this section does not do: extend the bar past the Stage 2 tranche to show position against total authorization. That extension is the single most common way stage-funded programs mislead themselves — it converts money the Board has explicitly withheld into a denominator, and every ratio computed on it inherits the fiction. The Stage Budget Console exists to make the four funding states visually undeniable; this dashboard borrows its discipline and reports variance only where a real authorization creates a real denominator.

FundingAmountState
Stage 1 tranche$2,180,000Released and closed at $2,412,000
Stage 2 tranche$11,640,000Released, 39% spent
Stage 3 tranche$7,450,000Not released — requires Gate 2
Stage 4 tranche$4,330,000Not released — requires Gate 3
Contingency reserve$1,892,000Remaining of $2,304,000; Board-held (D-09)

3. Gate 2 must-meet trajectory

Five must-meet criteria were fixed at Gate 1. Any one unmet removes GO and GO WITH CONDITIONS from the table regardless of the weighted score, so this is the section that actually predicts the gate.

Must-meet criterionTrajectoryCurrent position
Contract forms cleared by outside counselWatchThird GLWB redraft with counsel (I-05)
Pricing signed, supported by GC-03 external reviewOn trackArdmore engaged; reporting ahead of due date
Illustration output validated vs filed methodologyOn trackConfig complete for the 3-strategy set
Hedging readiness plan accepted under GC-05At riskSecond ISDA counterparty not started (DEP-06)
All Gate 1 conditions closed or re-issuedWatch3 of 5 closed
One criterion is at risk and it is the same one every other document flags. The hedging readiness plan under GC-05 depends on two derivatives counterparties; one is at executed term sheet and the second has not begun negotiation (DEP-06). With 167 days to the gate and Stage 2 already compressed from 46 weeks to 41 by the Gate 1 recycle, there is no float left to absorb it.

The two open conditions are not equally dangerous, and the difference is structural

GC-03 (external actuarial peer review, due 26 Feb 2027) is on-track and — more importantly — is self-contained: its critical path runs through one engagement the program itself purchased and controls, and its evidence is a report that either exists at the gate or does not. GC-05 (hedging readiness, due 12 Mar 2027) is at-risk for the opposite structural reason: its critical path runs through a counterparty's legal department. ISDA onboarding is a negotiation the program can schedule but not compel, which is why DEP-06 exists as a tracked dependency rather than a task. A condition whose closure depends on an external party's calendar deserves a different watch-level than one whose closure depends on the program's own diligence — the register scores them identically as “open,” and that is precisely the flattening this dashboard exists to undo.

What the trajectory column is actually predicting

A must-meet criterion is a knockout: any single miss removes GO and GO WITH CONDITIONS from the Board's option set before the weighted scoring even convenes. So the trajectory column is not progress reporting — it is a forecast of which decisions will be available on 01 Apr 2027. Read that way, the current picture says: on today's evidence the Board would not have a clean GO available, and the program's remaining 167 days are about restoring options, not polishing a score.

4. Gate conditions

IDConditionOwnerDateStatus
GC-01Reduce launch crediting strategies from five to threeD. FalknerClosed 21 Jul 2026Closed
GC-02Remove New York from launch scope and issue a deferral memorandumA. NkemeluClosed 03 Jul 2026Closed
GC-03Independent external actuarial peer review of GLWB rider pricing before Gate 2S. RavichandranDue 26 Feb 2027Open
GC-04Re-validate distribution volume assumptions with the three largest IMO partnersR. CastellanosClosed 14 Aug 2026Closed
GC-05Present a hedging readiness plan with ISDA execution milestones at Gate 2M. DelacroixDue 12 Mar 2027At Risk

3 of 5 closed. Full verification methods, evidence and the post-closure efficacy findings are in the Gate Conditions Register — this dashboard carries status only, so there is one place where condition detail can be wrong.

5. Top open risks

IDRiskOwnerScore
R-05Hedging readiness (ISDA, derivatives ops, daily rebalance) lags launchM. Delacroix20
R-07Distribution partners deprioritize against competitor launches in the same quarterR. Castellanos16
R-06Pricing assumptions (lapse, GLWB utilization) prove unsupportable under external peer reviewS. Ravichandran15
R-01IIPRC review extends past the standard clock over a non-standard GLWB rider featureP. Hollingsworth12
R-03Option budget compresses if index option costs rise, pushing the illustrated cap below competitiveS. Ravichandran12

Scores are probability × impact, re-scored at the status date. The two highest are the two that rose since Gate 1, and both sit behind the conditions still open — the risk register and the condition register agreeing from opposite directions, which is the intended behavior and would be a defect if they diverged. Movement, response and the full twelve-risk register are in the RAIDD Log.

Concentration is the finding, not the scores

Three separate registers now point at the same narrow front: the two risks that rose since Gate 1 sit behind the two conditions still open, which sit in front of the must-meet criteria currently off-track. That triple agreement is worth naming because it changes what “mitigation” means — the program does not have five medium problems to work in parallel; it has one concentrated exposure (hedging readiness and the distribution commitment gap) wearing three reporting formats. It also identifies the failure mode this dashboard should be watched for: if the registers ever stop agreeing — a risk falling while its condition stays open, a condition closing while its must-meet stays off-track — the divergence is more likely a bookkeeping error than a real change, and the Register's post-closure efficacy check exists for exactly that suspicion.

6. Schedule position

MilestoneDatePosition
Gate 1 (second convening)11 Jun 2026Closed — GO WITH CONDITIONS 4–0–1
Stage 2 — Development15 Jun 2026 → 26 Mar 2027Week 18 of 41 — compressed from 46 weeks
Gate 201 Apr 2027167 days out — not yet convened
Gate 328 Oct 2027Planned; Stage 3 unfunded
Gate 424 Feb 2028Planned; Stage 4 unfunded
Launch06 Mar 2028Unmoved since Gate 0
The launch date has never moved, and that is where the schedule pressure went. The Gate 1 recycle cost six weeks. Rather than moving launch, the program absorbed the loss by compressing Stage 2 from 46 weeks to 41. Reporting “launch on schedule” without that sentence beside it would be true and misleading at the same time — the schedule held because a stage was shortened, not because the loop was free.

7. What would make this dashboard lie

Stated deliberately, because a status report that cannot describe its own failure modes is decoration.

The lie this dashboard is most likely to tell next

Every failure mode above is a misreading a careful reader can refuse. The dangerous one is different in kind: staleness wearing precision. Every figure here carries the 16 October 2026 status date, and the month between refreshes is exactly the window in which an ISDA negotiation stalls or an IMO commitment quietly softens. A reader who treats a four-week-old “on-track” as a current fact is being misled by typography — the pill looks as fresh as the day it was rendered. The mitigation is structural rather than editorial: the monthly refresh regenerates this page, the Gate Conditions Register and the Readiness Assessment from the same evidence in the same pass, so the three documents can be wrong but cannot disagree — and a reader who finds them disagreeing has found a stale copy, not a controversy.

8. Reporting cadence

WhenWhatTo whom
WeeklyStatus report — progress, blockers, condition movementSponsor and team leads
MonthlyThis dashboard, refreshed with the Gate Conditions Register and Gate 2 Readiness Assessment against the same evidenceGate Review Board
Ten business days before Gate 2Final dashboard tabled inside the gate packageGate Review Board

Maintained by C. Tyrrell, NPD Program Manager and Chair of the Gate Review Board. Related: Gate 2 Readiness Assessment · Gate Conditions Register · RAIDD Log · Program Budget · Methodology Guide §5 (why no EVM).