← Stage-Gate NPD Suite Program Status — Week Ending 16 October 2026

Weekly Program Status Report

Download Word
Program timeline · status 16 Oct 2026Read the full story →
Harborline
Aug 2025
Cancelled
Gate 0
Feb 2026
Go
Stage 1
Business case
Gate 1
Apr 2026
Recycled
Gate 1
Jun 2026
Go w/ conditions
Stage 2
Development
You are here
Gate 2
Apr 2027
Gate 3
Oct 2027
Gate 4
Feb 2028
Launch
Mar 2028
Gate 5
Sep 2028

Lighthouse Financial Services Company — Beacon Index Advantage product development program. Status as of 16 October 2026. Reporting period: the week ending on the status date. This report is read against the gate the program is driving toward — Gate 2 on 01 April 2027 — not against a generic percent-complete, because in a stage-gate program the only completion that matters is the next gate.

Weekly Status — At a Glance

Stage 2
Current Stage
17 / 40
Stage 2 Weeks (42%)
$6,950,000
Spent / $14,232,000 Released
3 / 5
Gate Conditions Closed
1
Conditions At Risk
Why no SPI/CPI. This program publishes no full-program earned-value baseline — Stages 3 and 4 are not yet funded, so a program-level schedule- and cost-performance index would be computed against a baseline that does not exist. Status is reported at stage granularity, against gate milestones, which is what the governance model authorizes. Of the $27,904,000 authorized program cost, $14,232,000 has been released through the Stage 2 tranche; the remainder releases only at future gates.

Accomplishments This Period

Planned for Next Period

Risks & Issues Requiring Attention

The open Gate 1 conditions are the live risk register for this period. Both must close before Gate 2; one is on track and one is flagged.

StatusConditionOwnerNote
At riskGC-05 — Present a hedging readiness plan with ISDA execution milestones at Gate 2M. DelacroixISDA execution with the second counterparty has not begun (DEP-06)
OpenGC-03 — Independent external actuarial peer review of GLWB rider pricing before Gate 2S. RavichandranOn track — due 26 Feb 2027
Escalation. GC-05 (hedging readiness) is at risk because ISDA execution with the second counterparty has not begun. Because the launch date is fixed, schedule risk on the hedging dependency cannot be absorbed by moving launch — it must be absorbed by starting the dependency sooner. This is raised for the Chief Risk Officer's attention and is the program's recommended focus for the coming period.

Upcoming Milestones

MilestoneDateStatus
External actuarial peer review complete (GC-03)26 Feb 2027On track
Hedging readiness plan & ISDA milestones (GC-05)12 Mar 2027At risk
Gate 2 - Development Complete & Filing Readiness01 Apr 2027Pending
Launch — Beacon Index Advantage06 Mar 2028Fixed date

Decisions & Approvals Needed

Prepared by the Program Management Office, Lighthouse Financial Services Company, and chaired from the PMO without a vote. Distribution: Gate Review Board and program sponsor. Status date 16 October 2026.