← M&A Integration Suite Register · Artifact 44 · how to read this suite

Change Control Log

Download Excel

Log closed January 31, 2025 — after the final change request was dispositioned and before program closeout. 12 change requests were raised across the program. This log is the reconciliation between the post-close cost baseline and the actual outturn: the approved requests bridge the two exactly, and every figure on this page is computed from that bridge rather than reported independently.

Contents

  1. The complete log
  2. Reconciliation to the cost baseline
  3. Which constraint each request spent
  4. The rejections, and why they matter more than the approvals
  5. The deferrals — what was actually cut
  6. Schedule impact

1. The complete log

RefRequestDispositionCostScheduleConstraint protectedConstraint spent
CR-001Extend integration layer to cover 270/271 real-time eligibilityApproved$780,000Day 1 integrityCost
CR-002Add second data-steward cohort for the clerical review bandApproved$1,240,000Data integrityCost
CR-003Add 12 offshore data stewards to work down the review queueRejected
CR-004TSA extension, three months, core admin and IT servicesApproved$3,450,00013 wkData integritySchedule margin and cost
CR-005Extend IMO and workstream leads through revised TSA exitApproved$1,260,00013 wkData integrityCost
CR-006Refactor claims adjudication rules engine during migrationRejectedTSA exit date
CR-007Provider network rationalization phase 2DeferredSchedule and costScope
CR-008Care management advanced analytics moduleDeferredSchedule and costScope
CR-009Migrate claims history beyond 7 yearsApproved with modificationTSA exit dateScope (depth of history)
CR-010Accelerate member ID card reissue ahead of Day 1Approved$410,000Day 1 integrityCost
CR-011Second Azure landing zone for the retained mainframe facadeApproved$460,000Day 1 integrityCost
CR-012Retention bonus pool extension for Cumberland Valley key talentWithdrawn
Approved change — 6 requests$7,600,00013 wk

Every row names what it protects and what it spends, and that is what makes this log auditable against the charter rather than merely complete. The charter ranks the program's constraints: the contractual maximum on transitional services and Day 1 integrity are hard, synergy is firm, cost flexes, and scope flexes first. A change request that protects a hard constraint by spending a flexible one is the ranking working. One that protects cost by spending data integrity would be the ranking inverted — and a log without these two columns cannot show the difference.

2. Reconciliation to the cost baseline

LineAmountNote
Post-close base estimate$51,800,000Class 2, set at re-baseline
Contingency at 8%$4,144,000Held inside the baseline against identified risk
Cost baseline$55,944,000The figure change control governs
Management reserve$4,200,000Outside the baseline; released by the sponsor
Authorized funding$60,144,000Baseline plus reserve
Bridge
Approved change requests (6)$7,600,000Sum of the approved column above
Absorbed by contingency−$4,144,000Contingency fully consumed
Drawn from management reserve$3,456,000Sponsor decision, not a program one
Actual outturn$59,400,000Cost baseline plus the reserve draw
Variance against cost baseline+$3,456,000Over the baseline
Variance against authorized funding−$744,000Inside authorization
Management reserve remaining$744,000Returned unspent

The two variance lines say opposite things and both are true, which is exactly why a program must state which baseline it is reporting against. Measured against the cost baseline the program is over by $3,456,000. Measured against authorized funding it came in under by $744,000. Neither figure is spin: the baseline is what change control governs, and the reserve is what the sponsor holds for the things a baseline cannot anticipate. A program that reports only the first looks like it failed; one that reports only the second looks like nothing happened. The reserve was drawn, it was drawn by the person authorized to draw it, and it was not exhausted — $744,000 went back. That is the whole story and it takes both lines to tell it.

3. Which constraint each request spent

Read the last two columns of the log together and a pattern appears that the dispositions alone do not show. Every approved request spent cost, schedule margin or scope. None spent data integrity or Day 1 integrity, and the two requests that would have — offshore stewards and higher throughput — are the two that were refused.

A change control log is where a charter's constraint order is either honored or quietly abandoned, and the abandonment never announces itself. Under pressure, the cheapest-looking option is usually the one that spends a constraint nobody is measuring — quality, data integrity, a capability with no owner. Those spends do not appear as variance. They appear later, in somebody else's operating year, in a form that cannot be traced back to the meeting that caused them. The columns exist so that a decision to spend an unmeasured constraint would have to be written down as such at the moment it was taken.

4. The rejections, and why they matter more than the approvals

Two requests were rejected and one was approved only with modification. They carry more information about how the program was governed than the six approvals do, because an approval records what a program was willing to fund and a rejection records what it was not willing to trade.

CR-012 was withdrawn, and a withdrawal is worth logging rather than deleting. A retention bonus pool extension was raised and then withdrawn by the originator once attrition came in below the trigger threshold. Nothing was decided and nothing was spent. Keeping the row shows a control process that was used to test a question rather than only to ratify decisions already made — and a log containing only approvals and refusals is usually a log that was written after the fact.

5. The deferrals — what was actually cut

Two requests were deferred to a Year 2 backlog, together representing $1,900,000 of value moved out of the program. Each carries a named owner who accepted the deferral: CR-007 — J. Kirkendall, VP Network Management · CR-008 — Dr. M. Ellsworth, Chief Medical Officer.

The value stays visible in synergy reporting rather than being removed from the denominator. Removing it would raise every remaining percentage and make the program look better for having delivered less.

Scope is the constraint the charter allows to flex first, and it is the one most programs leave untouched while cost and schedule absorb everything. A program that returns to its sponsor asking only for money and time has not tested its own priorities. But a deferral with no named owner is not a deferral — it is an abandonment that will be rediscovered by whoever was expecting the capability. These two are the honest test of that: the program closed, the backlog transferred to an organization that did not make the original commitment, and whether the value is ever retrieved depends entirely on whether those two names still hold it.

6. Schedule impact

Approved change added 13 weeks to the transitional services term. Two requests carry that impact — the extension itself and the program leadership required to run alongside it — and they cover the same weeks rather than consecutive ones.

The extension consumed negotiated margin between the exit plan and the contractual maximum. It did not breach the maximum, and margin remained at exit. Blowing a contractual maximum is a governance failure; spending a buffer that was deliberately negotiated at signing is the buffer doing its job.

Related artifacts: 43 — Steering Committee Deck · 12 — Program Budget · 41 — Synergy Realization Tracker · 1 — Integration Charter