← M&A Integration Suite Authorizing Document · Artifact 1 · how to read this suite

Integration Charter

Download Word

This Charter authorizes the ACME Health / Cumberland Valley Integration Program and grants the Program Manager authority to apply organizational resources to integration activities. It is the highest-authority document in the program; every other artifact — the Integration Management Plan, the disposition matrices, the TSA exit plan, every statement of work — derives its authority from this Charter and must be consistent with it. Approved by the Integration Steering Committee on February 27, 2023, two weeks after execution of the definitive agreement and seven months before expected closing. Amendment requires Steering Committee approval under the change control thresholds in Section 12.

This document was written before closing and knows only what was knowable then. The budget, schedule and scope recorded here reflect the deal-model estimate prepared under the constraints of the Clean Team Protocol, which barred examination of member-level data. It is an AACE Class 5 estimate and is stated as such in Section 9. It was superseded by a formal re-baseline after closing. Nothing in this Charter has been retrospectively corrected — a charter edited to match the outcome is not a charter.

Table of Contents

Part I — Authorization and Business Case
  1. Charter Authorization
  2. Transaction Summary and Strategic Rationale
  3. Integration Objectives and Success Criteria
  4. Constraint Priority Order
Part II — Scope and Approach
  1. Integration Thesis — Absorb, Preserve, Best-of-Both
  2. Scope Inclusions and Exclusions
  3. Milestones and the Integration Clock
Part III — Governance and Resources
  1. Governance, Authority and Delegation
  2. Budget Authorization and Estimate Class
  3. Program Organization
  4. Assumptions, Constraints and Principal Risks
  5. Change Control Thresholds
  6. Approval
Part I — Authorization and Business Case

1. Charter Authorization

AttributeProvision
ProgramACME Health / Cumberland Valley Integration Program
Charter dateFebruary 27, 2023
Executive SponsorD. Ashmore, EVP & Chief Financial Officer, ACME Health
Program ManagerC. Tyrrell, Arrington Advisory Group — engaged under Deliverable SOW (Artifact 8)
Authorizing bodyIntegration Steering Committee
Effective periodCharter date through program close, following exit of all Transition Services Agreements
Authorized budget$52,500,000
Estimate classAACE Class 5 — see Section 9.3

2. Transaction Summary and Strategic Rationale

ItemDetail
AcquirerACME Health — approximately 1,800,000 members
TargetCumberland Valley Health Plan — approximately 420,000 members, a subsidiary of Cheatham Mutual Holdings
Combined membership2,220,000
Transaction value$1,200,000,000
StructureCarve-out. ACME Health acquires Cumberland Valley Health Plan from its parent, Cheatham Mutual Holdings. Cumberland Valley then merges into ACME Health, which is the surviving entity.
Definitive agreementFebruary 13, 2023
Conditions to closeHSR waiting period expiration; Tennessee Department of Commerce and Insurance Form A approval
Expected closeEnd of Q3 2023
Synergy commitment$85,000,000 run-rate by end of Year 3

2.1 Why the board approved this transaction

The synergy target is the number every artifact in this program ultimately answers to. $85M run-rate by Year 3 is not an aspiration recorded in a business case — it is the figure on which the board approved a $1.2B transaction. The Synergy Realization Plan decomposes it by source and owner; the Synergy Tracker reports against it monthly. A program that delivers on time and on budget while missing this number has failed.

3. Integration Objectives and Success Criteria

An integration program is not measured the way a project is. On-time and on-budget are secondary here. The two measures that determine whether this program succeeded are synergy capture and TSA exit — and both can be missed by a program that hit every date and spent exactly what it forecast. The criteria below are written accordingly.
#ObjectiveSuccess criterion — measurable, dated
O-1Legal and operational Day 1On the first business day post-close: all associates paid, claims adjudicating in both platforms, member ID cards issued, all regulatory filings current, no service interruption
O-2Exit all Transition Services AgreementsFinal TSA terminated no later than September 30, 2024 (12 months post-close), against a contractual maximum of March 31, 2025
O-3Synergy capture$85,000,000 run-rate by end of Year 3, with Year 1 and Year 2 cumulative capture tracked against the deal model curve
O-4Member identity resolutionSingle enterprise member index across the combined book, with an audited false-positive merge rate below the threshold set in the EMPI specification
O-5Platform consolidationCore administration consolidated to the ACME platform per the Application Disposition Matrix; Cumberland Valley platform decommissioned
O-6Cloud foundation establishedAzure landing zone operational before the first migration wave, with FinOps controls and a signed Business Associate Agreement in place
O-7Retention of critical knowledgeNo unplanned departure of a retention-covered role before its TSA-exit dependency is discharged
O-8Regulatory and privacy integrityNo reportable privacy incident, no adverse regulatory finding, no gun-jumping allegation

4. Constraint Priority Order

Every program encounters a moment where something must give. This Charter states in advance which constraint gives first, so that decisions made under pressure eighteen months from now can be tested against a rule set before the pressure existed.

RankConstraintClassBasis
1TSA contractual maximum — 18 monthsHardA contractual wall, not a target. Breaching it is a governance failure that no cost saving offsets. It is never the thing that gives.
2Day 1 regulatory and operational integrityHardMembers must have coverage they can use and regulators must have their filings. Not negotiable at any price.
3Synergy run-rate target — $85MFirmThe basis on which the board approved the transaction. May shift in timing; may not be abandoned.
4Program costFlexesThe Steering Committee may authorize additional funding from contingency and management reserve where doing so protects ranks 1–3.
5Program scopeFlexes firstDeferred scope moves to a Day 100+ or Year 2 backlog with a named owner and a date. It does not disappear.
The order is counterintuitive and that is the point. On most programs cost and schedule are the hard constraints and scope is defended. Here the schedule constraint that matters is a contract term with a counterparty, the operational constraint is a regulatory obligation, and money is the most flexible thing available — because every month of TSA overrun costs more than the fix would have. A Program Manager who defends the budget at the expense of the TSA date has the priority order backwards.
How this section is meant to be used. Every change request raised against this program must state which constraint it protects and which it spends. A change request that spends rank 4 to protect rank 1 should ordinarily be approved. One that spends rank 1 to protect rank 4 should ordinarily be rejected, regardless of the sums involved. This Charter is therefore not merely an authorizing document — it is the standard against which the Change Control Log can be audited after the fact.
Part II — Scope and Approach

5. Integration Thesis — Absorb, Preserve, Best-of-Both

There is no single correct integration depth. An acquirer may buy a business and leave it standing, absorb it entirely, or select between the two operating models function by function. This program adopts a mixed thesis, decided per function against a single test: does combining this function create value, or destroy the value we paid for?

FunctionDispositionRationale
Claims & core administrationAbsorbPure scale economics. Two adjudication platforms serving one membership is duplicated cost with no offsetting benefit. Largest single synergy source.
Care managementPreserveThe target measurably outperforms. Migrating this function to ACME's model would destroy a capability the transaction was partly undertaken to acquire.
Provider networkBest-of-bothRationalize market by market toward the stronger contracted position rather than defaulting to either party's network.
Member servicesPreserve to Day 100, then absorbAbsorbing member-facing operations at Day 1 risks a visible service collapse at the moment of maximum member and regulator attention. Sequenced deliberately.
Finance, HR, IT infrastructureAbsorbStandard corporate function consolidation. No differentiated capability to protect.
Actuarial & underwritingAbsorbSingle rating methodology required for the combined book; regulatory filings must be made by one entity.
Every row here is a decision an interviewer can push on, which is why the rationale column exists. The two rows worth defending hardest are care management — where the disciplined answer is that you do not integrate the thing you bought — and member services, where the phased approach accepts twelve months of duplicated cost to avoid a Day 1 service failure in front of the state regulator. Both are choices to spend rank 4 to protect rank 2.

6. Scope Inclusions and Exclusions

6.1 In scope

6.2 Explicitly out of scope

ExcludedReason and owner
Product and benefit plan design harmonizationFollows integration; owned by Product. Constrained by filed plan years and cannot precede them.
Rate convergence between the two booksActuarial workplan, post-integration. Subject to filing cycles and regulatory approval.
Facility consolidation beyond lease expiry decisionsCorporate Real Estate. Program addresses only leases requiring a decision inside the integration window.
Brand consolidation and market re-launchMarketing. Timing is a commercial decision independent of operational integration.
Any activity prior to closing that constitutes operational control of the targetProhibited by the Clean Team Protocol, Section 8. Planning is in scope; execution is not.

7. Milestones and the Integration Clock

An integration program does not run on phases or sprints. It runs on a clock set by the transaction, and the fixed points below are the ones the Steering Committee governs against.

MilestoneDateDefinition
Definitive agreementFebruary 13, 2023Signed. Clean Team Protocol takes effect March 6.
Regulatory clearanceQ2–Q3 2023HSR waiting period expiration and Tennessee DOI Form A approval. Conditions to closing.
CloseEnd of Q3 2023Ownership transfers. Antitrust barrier dissolves. Integration execution may begin.
Day 1First business day post-closeThe combined entity legally and operationally functions. Not integrated.
Day 10099 days after Day 1Stabilization complete, integration execution at full run rate, first synergy tranche realized.
TSA exit — planSeptember 30, 202412 months post-close. The program's committed target.
TSA exit — contractual maximumMarch 31, 202518 months post-close. The rank 1 hard constraint. Six months of deliberately negotiated margin.
Program closeFollowing final TSA exitIMO stands down; residual scope transfers to line ownership with named owners.
Day 1 does not mean integrated, and conflating the two is the classic first-timer error. Day 1 means associates get paid, claims adjudicate, members can present a card and receive care, and regulators have their filings. It does not mean one platform, one network, one member index or one operating model. Everything else is Day 100 or later. A program that promises the board an integrated company on Day 1 has promised something no integration has ever delivered.
On the six-month gap between the TSA plan and the TSA maximum. The 12-month plan and the 18-month contractual limit are different numbers on purpose. The gap is negotiated margin, agreed at signing, against the possibility that post-close discovery reveals conditions the pre-close estimate could not see. Consuming that margin is a planned use of a deliberately purchased buffer. Breaching the 18-month limit is a governance failure. The Charter treats those two outcomes as categorically different, and Section 4 ranks them accordingly.
Part III — Governance and Resources

8. Governance, Authority and Delegation

8.1 Integration Steering Committee

MemberRoleSeat rationale
D. AshmoreEVP & CFO, ACME — Executive Sponsor, ChairOwns the synergy commitment made to the board
R. VillanuevaChief Operating Officer, ACMEOwns Day 1 operational integrity
M. KessingerPresident & CEO, Cumberland ValleyTarget-side authority; required for decisions binding target operations post-close
T. BroadnaxSVP Corporate Development, ACMEOwns the deal model the program is measured against
L. HollingsworthGeneral Counsel, ACMERegulatory approvals, gun-jumping compliance, entity consolidation
S. AchebeChief Information Officer, ACMEOwns the platform and cloud decisions carrying most of the execution risk

The Committee meets monthly and on call for gate decisions. It is the sole approver of change requests above the thresholds in Section 12, of the Application and Vendor Contract Disposition Matrices, and of Day 1 go/no-go.

8.2 The Program Manager is a consultant, and the authority is written rather than organizational

The Program Manager is engaged through Arrington Advisory Group under a deliverable statement of work. He leads the Integration Management Office and employs no one in it. Every person in the IMO and every workstream lead reports to an ACME or Cumberland Valley line manager, not to the Program Manager.

This is a real governance problem and the Charter is where it gets solved. An internal program director carries positional authority into a room. A consultant does not. If the authority is not written down and visibly conferred by the Sponsor, it does not exist — and the first workstream lead who declines a request discovers that in front of everyone. The delegations below are therefore explicit, and the escalation path is short by design.
The Program Manager is authorized toThe Program Manager may not
Direct integration activity across all workstreams, including sequencing, dependency resolution and deliverable acceptanceHire, terminate, or alter the compensation of any person
Convene the Steering Committee and set its agendaCommit either entity to a contract or external obligation
Approve change requests below the Section 12 thresholdsApprove changes to the TSA term, the synergy target, or Day 1 scope
Draw on program contingency within the approved cost baselineDraw on management reserve without Sponsor approval
Escalate any workstream matter directly to the Executive Sponsor without intermediate approvalOverride a decision reserved to Legal, Compliance, or the Clean Team Protocol
Require workstream leads to report against the program plan and to justify varianceDirect staff augmentation personnel as employees — see 8.3

8.3 A limit that is easy to breach without noticing

Personnel engaged through staff augmentation are contracted resources, not employees. Placing them on organization charts, assigning them company titles, or directing their daily work in the manner of a line manager creates co-employment and worker-classification exposure. The Resource Plan records the contract vehicle for every named individual for this reason, and the distinction between a deliverable SOW — where the vendor owns the outcome — and staff augmentation — where ACME owns the outcome and rents the hours — is maintained throughout the program's contracting documents.

9. Budget Authorization and Estimate Class

ComponentAmountControl
Integration base estimate$42,000,000Program Manager, within baseline
Contingency at 15%$6,300,000Program Manager, for realized in-scope risk
Cost baseline$48,300,000Measurement baseline for earned value reporting
Management reserve at 10% of base$4,200,000Executive Sponsor only — for unknown-unknowns outside the baseline
Total authorized$52,500,000Steering Committee

9.1 Contingency and management reserve are different instruments

Contingency sits inside the cost baseline and covers identified risks that materialize — it is the priced expectation that some of the risk register comes true. Management reserve sits outside the baseline, is not part of any performance measurement, and covers scope the program did not know existed. Drawing on contingency is program management. Drawing on management reserve is an admission that the program encountered something it did not foresee, which is why it requires the Sponsor.

9.2 What this budget does not include

9.3 Estimate class — and why it is stated here

This is an AACE Class 5 estimate. Expected accuracy is approximately −20% to +50%. It was prepared during the pre-close period under the Clean Team Protocol, which barred the estimators from examining member-level data or testing target records against ACME's. The 15% contingency is not conservatism — it is the arithmetically appropriate response to a legally imposed information deficit. A formal re-baseline is planned once post-close discovery and data profiling are complete, at which point the estimate is expected to move to Class 2 and contingency to reduce as uncertainty resolves. That re-baseline is a planned event, not a change request, and it is authorized by this Charter.

Recording the estimate class in the Charter serves a specific purpose: it makes the later variance interpretable. A program that states Class 5 up front and then re-baselines is behaving as expected. A program that presents a Class 5 estimate as though it were definitive, and then explains the variance afterward, is not.

10. Program Organization

The program is staffed across four labor categories — ACME employees, Cumberland Valley employees, onshore and offshore consultants from Arrington Advisory Group, and specialist vendors. Full detail sits in the Resource Plan and Org Chart; the Charter records the structure and the two structural features that distinguish it.

BodyComposition and accountability
Integration Steering CommitteeSix executives per Section 8.1. Decision authority.
Integration Management OfficeProgram Manager, PMO analyst, synergy and financial analyst, change and communications lead, TSA manager. Coordination and control.
WorkstreamsSixteen, each with an ACME lead and a Cumberland Valley counterpart. Execution.
Clean TeamFour, third-party, pre-close only. Dissolves at closing and does not join the program.
Specialist vendorsEDI transaction assurance; staff augmentation for data stewardship; cloud platform.

10.1 Every workstream is paired

No workstream has a single lead. Each has an ACME lead and a Cumberland Valley counterpart, jointly accountable. This doubles the number of people in every meeting and is worth it: a workstream run only by the acquirer makes decisions without the knowledge of how the target actually operates, and a workstream run only by the target makes decisions the acquirer will not honor.

10.2 The organization changes shape at closing

The pre-close organization and the post-close organization are different populations, not the same population with more people. The Clean Team exists only before closing. Data stewards cannot exist before closing, because the member-level data they work is not lawfully available. The Resource Plan is therefore maintained in two states, and the transition between them is a planned Day 1 event.

11. Assumptions, Constraints and Principal Risks

11.1 Assumptions — if any of these fail, the plan changes

AssumptionIf it fails
Regulatory approvals are obtained without conditions materially restricting integrationScope and schedule re-planned; conditions may bind data location or timing
Target data quality is broadly consistent with diligence representationsIdentity resolution effort and duration increase; migration window at risk
Retention-covered target staff remain through their TSA-exit dependenciesKnowledge loss; TSA extension likely
ACME's core platform absorbs target volume without material re-architecturePlatform work becomes a critical path item
TSA services can be exited incrementally rather than as a single eventExit becomes a big-bang cutover with materially higher risk
The second assumption is the one that carries the most risk and the least evidence. It rests on diligence representations and aggregate reporting, because the Clean Team Protocol barred any test of it against ACME's own records. It is recorded here as an assumption rather than a finding for exactly that reason, and it is the assumption the post-close profiling work is designed to test first.

11.2 Constraints

11.3 Principal risks at charter

RefRiskCharter-level response
R-01Member identity resolution proves materially harder than modeledStaffed data stewardship with an SLA; conservative match thresholds; contingency sized against it
R-02Attrition of critical target staff before TSA exitRetention agreements on identified roles; knowledge transfer as a tracked deliverable
R-03First-time cloud adoption under a fixed deadlineRehost-first migration strategy; landing zone before any wave; refactoring deferred out of the integration window
R-04Vendor change-of-control rights disrupt Day 1Pre-close contract sweep; consents and novations prepared for immediate post-close execution
R-05Business Associate Agreements not re-executed for the surviving entityTracked to completion as a Day 1 gate condition; a miss is a privacy exposure, not an administrative one
R-06Systems cannot integrate directly within the coexistence periodIntegration layer with a canonical model, sized for a coexistence period measured in years rather than a tactical bridge

12. Change Control Thresholds

ChangeApproverNotes
Cost impact under $250,000, within baselineProgram ManagerLogged; reported to Steering monthly
Cost impact $250,000 to $1,000,000Executive SponsorContingency draw; Steering notified
Cost impact above $1,000,000Integration Steering CommitteeFormal change request required
Any draw on management reserveExecutive SponsorRegardless of amount
Any change to the TSA exit dateIntegration Steering CommitteeMust state impact against the 18-month contractual maximum
Any change to Day 1 scopeIntegration Steering CommitteeRank 2 constraint; presumption against approval
Any change to the synergy targetSteering Committee and board notificationThe board approved the transaction on this figure
Scope deferral to a post-integration backlogProgram Manager, with Steering ratificationRequires a named owner and a date. Scope may be deferred; it may not be deleted silently.
The last row is the one that keeps the program honest. Deferred scope with a named owner and a date is a program decision. Deferred scope with neither is scope that vanished, and a closeout report that cannot account for what was dropped and where it went is describing a program that did not happen as written.

13. Approval

NameRoleApproval
D. AshmoreEVP & CFO, ACME Health — Executive SponsorApproved February 27, 2023
R. VillanuevaChief Operating Officer, ACME HealthApproved February 27, 2023
M. KessingerPresident & CEO, Cumberland Valley Health PlanApproved February 27, 2023
T. BroadnaxSVP Corporate Development, ACME HealthApproved February 27, 2023
L. HollingsworthGeneral Counsel, ACME HealthApproved February 27, 2023
S. AchebeChief Information Officer, ACME HealthApproved February 27, 2023
C. TyrrellProgram Manager, Arrington Advisory GroupAcknowledged February 27, 2023
The Program Manager acknowledges this Charter; he does not approve it. A charter is conferred on a program manager by the sponsoring organization. One that the program manager approves is a proposal.

Related artifacts: 2 — Deal Summary & Investment Thesis · 4 — IMO Governance Model · 5 — Clean Team Protocol · 8 — Consulting SOW & Engagement Model · 20 — Application Disposition Matrix · 44 — Change Control Log