The Charter says what this program must achieve and which constraints give first. This plan says how it will be run: the operating model, how planning works when half the information is legally unavailable, what happens weekly and monthly, how decisions get made when nobody anticipated the question, and which subsidiary plans sit beneath this one. Approved April 17, 2023, five months before closing.
Table of Contents
1. The Integration Clock
The program does not run on phases or sprints. It runs on a clock set by the transaction, and every plan beneath this one is anchored to the same fixed points.
| Period | Character | What the program is doing |
|---|---|---|
| Sign to close | ⚠ Plan only | Everything designable is designed; nothing is executed against the target. Constrained by the Clean Team Protocol. |
| Day 1 | Operate | The combined entity legally and operationally functions. Not integrated. |
| Day 1 to Day 100 | Stabilize | Prove nothing broke; complete discovery; re-baseline on real information |
| Day 100 to TSA exit | Execute | Migrations, cutovers, consolidations. The bulk of the work and the bulk of the risk. |
| TSA exit to close | Transfer | Residual scope to line ownership; IMO stands down |
2. Workstream Model — Paired Leadership
Sixteen workstreams. Each has an ACME lead and a Cumberland Valley counterpart, jointly accountable for the same deliverables.
| Responsibility | ACME lead | Cumberland Valley counterpart |
|---|---|---|
| Target state design | Owns | Reviews and challenges |
| Current state accuracy | Consumes | Owns — how the target actually works, as opposed to how it is documented |
| Deliverable acceptance | Signs | Signs |
| Escalation | Either may escalate independently | Either may escalate independently |
⚠ Either counterpart may escalate independently. A target-side lead who can only raise concerns through their ACME counterpart has no escalation path at all, since the most likely subject of the concern is the counterpart's decision.
3. The IMO and What It Does Not Do
| The IMO does | The IMO does not |
|---|---|
| Maintain the plan, schedule and dependency map | Own workstream deliverables |
| Run the cadence and produce reporting | Own risks — risk owners are people who can act |
| Administer change control | Approve changes above the delegated threshold |
| Identify and force cross-workstream dependencies into the open | Resolve technical disputes on the merits |
| Measure synergy independently | Deliver synergy — the functions do that |
| Escalate | Decide what only the Steering Committee may decide |
4. Rolling Wave Planning
Detail is planned to the horizon where information exists, and no further.
| Horizon | Planned to | Why |
|---|---|---|
| Next 90 days | Task level, named owners, dated | Information is available and stable |
| 90 days to Day 1 | Deliverable level | Sequence known; detail depends on decisions not yet taken |
| Day 1 to Day 100 | Milestone level | ⚠ Substantially dependent on post-close discovery |
| Beyond Day 100 | Workstream and dependency level | Planning it in detail now would be inventing detail |
⚠ Consequence for reporting: a milestone beyond the current detailed horizon is reported as on sequence rather than on schedule, because it has a position but not yet a defensible date.
5. Cadence and Reporting
| Forum | Frequency | Attendees | Purpose |
|---|---|---|---|
| Workstream stand-up | Weekly | Paired leads + IMO analyst | Progress, blockers, dependencies raised |
| Dependency review | Weekly | IMO + affected leads | ⭐ Cross-workstream only. The meeting that exists because nobody else sees across. |
| Program review | Fortnightly | All workstream leads | Plan status, risks, change requests in flight |
| Steering Committee | Monthly + on call | Six executives | Decisions, gate approvals, escalations, synergy |
| TSA service review | Monthly | TSA Manager + provider | Service levels and exit readiness |
5.1 Reporting principles
- Variance is reported with its cause and its recovery, not as a color. A red status with no stated recovery is an announcement, not a report.
- Both synergy measures every month — run-rate and cumulative capture. Reporting only run-rate hides a timing problem until it becomes a shortfall.
- Defect and risk counts carry age. A stable count with rising age is a backlog.
- ⚠ Bad news travels at the speed of discovery. Anything threatening a rank 1 or 2 constraint escalates immediately, not at the next cadence.
6. Change Control
| Change | Approver |
|---|---|
| Cost impact under $250,000, within baseline | Program Manager |
| Cost impact $250,000 to $1,000,000 | Executive Sponsor |
| Cost impact above $1,000,000 | Integration Steering Committee |
| Any draw on management reserve | Executive Sponsor, regardless of amount |
| TSA exit date, Day 1 scope, synergy target | Steering Committee |
| Any application or vendor disposition | ⚠ Steering Committee at any dollar value |
Every change request states which constraint it protects and which it spends, against the Charter's priority order. That single field is what allows the change log to be audited against the Charter after the fact, rather than merely listed.
7. Integration Principles
Pre-agreed tie-breakers. Their purpose is to resolve the decisions nobody anticipated — the ones that would otherwise be settled by whoever is most senior in the room, or most insistent, on the day.
Day 1 means associates are paid, claims adjudicate, members can use their coverage, and regulators have their filings. Anything else is Day 100 or later. Proposals that add scope to Day 1 are refused by default.
Where the target's capability is part of the investment thesis, the burden of proof sits with consolidation, not with preservation.
Planning is permitted and free. Execution against the target before closing is prohibited and is never worth the risk.
Almost nothing on this program accelerates because people work harder. It accelerates because a dependency was identified earlier. Effort is spent on finding dependencies, not on compressing them.
Deferred scope moves to a named backlog with a named owner. Scope that merely stops being discussed has vanished, and a closeout report that cannot account for it is describing a different program.
Gates are passed by demonstrating something — a reconciled control total, a completed restore, a parallel cycle run. "Complete" is a status; evidence is a result.
Knowledge transfer is a deliverable with named receivers and acceptance criteria, never a by-product of the work happening.
8. Register of Subsidiary Plans
This plan is a hub. The detail lives in the documents below, each with its own owner and revision cycle.
| Ref | Plan | Owner | Status at issue |
|---|---|---|---|
| 10 | Work Breakdown Structure | C. Tyrrell | In progress |
| 11 | Master Schedule | C. Tyrrell | In progress |
| 12 | Program Budget | J. Petrosyan | In progress |
| 13 | Synergy Realization Plan | J. Petrosyan | Planned |
| 14 | Resource Plan | C. Tyrrell | In progress |
| 17 | Communications Plan | A. Winterbourne | In progress |
| 18 | Change & Culture Plan | A. Winterbourne | Planned |
| 19 | Retention & Key Talent Plan | D. Marchbanks | In progress |
| 20 | Application Disposition Matrix | S. Achebe | Planned |
| 21 | Vendor & Contract Disposition Matrix | H. Castellow | Planned |
| 22 | TSA Schedule & Exit Plan | G. Threadgill | Planned |
| 23 | Data Migration & EMPI Strategy | Dr. A. Ravindran | Planned |
| 24 | Cloud Migration Strategy | B. Trammell | Planned |
| 25 | Integration Architecture & Interface Plan | R. Delacroix | Planned |
| 26 | Quality Plan | W. Ferriday | Planned |
| 27 | Legal Entity Consolidation Plan | F. Underhill | In progress |
| 28 | Risk Register | C. Tyrrell (administers) | Live |
| 29 | Day 1 Readiness & Cutover Runbook | R. Villanueva | Planned |
Related artifacts: 1 — Integration Charter · 5 — Clean Team Protocol · 4 — IMO Governance Model · 10 — Work Breakdown Structure · 11 — Master Schedule · 28 — Risk Register · 44 — Change Control Log