← Drug Development Suite Financial Record · Vitalis Therapeutics Inc.

Contingency Register

Download Excel

Vitalis Therapeutics Inc. — Every draw against the $26,040,000 contingency reserve for the VitaFlow (VTX-401) program: what it funded, who approved it, and what the rejected alternative was. Status at 15 October 2026.

$26.0M
Reserve
$9.1M
Drawn
$17.0M
Remaining
2
Draws
Contents
  1. Purpose & Rules
  2. Draw Authority
  3. Register
  4. How the Reserve Was Sized
  5. Outside the Reserve
  6. Why Each Entry Records a Rejected Alternative
  7. Draw Records
  8. Reading the Two Draws Together
  9. Forecast
  10. Requests Declined
  11. Remaining Reserve

1. Purpose & Rules

The contingency reserve for the VitaFlow (VTX-401) program is $26,040,000, 12% of the $217,000,000 base program. This register records every draw against it.

Draw Authority

Who may approve a draw depends on its size, and what evidence they must see depends on the same thing.

AmountApproverRecordingEvidence required
Up to $500,000Program DirectorNotified to the Committee at the next checkpoint.Operational recovery within an authorized stage.
$500,001 – $2,500,000Committee Chair with CFO concurrenceMinuted at the next Committee meeting.Requires a written statement of the rejected alternative.
Above $2,500,000Full Development CommitteeFormal decision, recorded in the register.Requires alternatives assessment and an impact statement on the remaining reserve.
Any draw that would exhaust the reserveBoardEscalated. The reserve sits inside the ceiling.Exhausting contingency is a ceiling matter, not a contingency matter.
Delegated authority exists so that small recoveries do not wait for a committee. A site activation problem that costs $300,000 to fix should be fixed in the week it appears, not at the next scheduled meeting six weeks later.

The threshold is set where it is because it is small enough that a series of Chair-approved draws cannot quietly consume the reserve, and large enough to cover the operational recoveries that actually arise.
That final line is routinely got wrong, and expensively. Exhausting the reserve is not a contingency decision that the Committee can take. The reserve sits inside the $243,040,000 ceiling, so a draw that would empty it is a statement that the program is approaching its authorized limit — which is a Board matter and a different conversation entirely.

2. Register

RefDrawAgainstTypeApprovedAmount
CD-01Cardiovascular outcomes sub-studyCR-02Approved change20 Apr 2026$7,200,000
CD-02CMC analytical method transfer recoveryI-02Materialised issue24 Mar 2026$1,850,000
Total drawn$9,050,000
Reserve remaining$16,990,000

35% of the reserve is consumed with the largest cost pool — Phase 3, at $109,100,000 — still running. That is a position worth watching rather than an alarm, and the distinction turns on what the two draws actually are.

3. How the Reserve Was Sized

12% of base is a choice, not a convention, and the number encodes a judgment about what kind of program this is.

ConsiderationEffect on the percentage
Stage of the program at authorizationLate-phase programs carry less uncertainty per dollar than early ones. Published practice puts 10–15% on late-phase work and 15–20% on early phase.
Concentration of spend58% of base sits in one stage. A reserve has to be adequate against the stage that dominates, not against the average stage.
Proportion of cost that is external83%. Contracted work varies less than internal effort, which argues for a lower reserve — but change orders are the mechanism by which it varies, and they are not free.
Regulatory dependencyAn agency expectation can add scope at any time. CR-02 is exactly that case, and it alone consumed 28% of the reserve.
The reserve is sized against what a gate cannot foresee, not against estimating error. A program that treats contingency as a buffer for bad estimates will consume it on ordinary variance and have nothing left when an agency asks for a study. Ordinary variance belongs inside the stage tranche; the reserve exists for scope that could not have been known.

4. Outside the Reserve

Naming the exclusions is what stops a reserve from becoming a general-purpose fund.

The third exclusion is the one that bites. A program that has drawn its full reserve has not run out of contingency — it has reached its ceiling, which is a Board matter and a very different conversation. The reserve is a mechanism for absorbing surprise within an authorization, not for extending one.

3. Why Each Entry Records a Rejected Alternative

Most contingency registers record an amount, a date and a one-line reason. That is enough to audit whether the money was authorized, and not nearly enough to judge whether it was spent well.

The question a reader has eighteen months later is not “was this approved?” — it plainly was, or it would not be in the register. The question is what else could have been done, and was the choice defensible on what was known at the time? That information exists only at the moment of decision. If it is not written down then, it is gone, and the draw becomes unreviewable: an amount with a justification attached and no way to test it.

The discipline has a second effect. Requiring the alternative to be stated forces the Committee to have identified one. A draw request that cannot articulate what the program would otherwise do is not a decision between options — it is a request to make a problem go away, and it should be harder to approve than it usually is.

4. Draw Records

CD-01 — Cardiovascular outcomes sub-study

FieldRecord
Amount$7,200,000 (28% of reserve)
Drawn againstCR-02 — approved change
Approved20 April 2026
Decided byDevelopment Committee

Rationale

Added on agency expectation recorded at the End-of-Phase-2 meeting. Carried as a change with a named draw rather than absorbed into the Phase 3 estimate, so that later variance analysis attributes it to a governance decision rather than to poor estimation.

Alternative considered and rejected

Decline the sub-study and accept the likelihood of a post-marketing requirement negotiated during review. Rejected: a commitment negotiated from weakness during review is worse than a study designed on the program's own terms.

CD-02 — CMC analytical method transfer recovery

FieldRecord
Amount$1,850,000 (7% of reserve)
Drawn againstI-02 — materialised issue
Approved24 March 2026
Decided byDevelopment Committee

Rationale

Method transfer to Aldergate failed first-pass acceptance on two of three methods. Funds an embedded CMC team on site and a re-qualification campaign.

Alternative considered and rejected

Manage within the Stage 4 tranche. Rejected: it would have absorbed a recovery cost into stage spend and hidden the only draw in this program that carries a lesson.

5. Reading the Two Draws Together

They consume the reserve at similar orders of magnitude — $7,200,000 and $1,850,000 — and they mean entirely different things.

CD-01 — CR-02CD-02 — I-02
OriginA choice the program madeSomething that went wrong
Foreseen?Yes — arose from a known agency expectationNo — was not on any risk register
What it buysScope: a study designed on the program's termsRecovery: getting back to where the plan assumed the program already was
LessonNone. The mechanism worked as intended.Technical transfer between organizations is systematically under-registered
Reporting these as a single “contingency consumed” figure would hide the only one of the two that carries a lesson. 35% consumed is a number. $7,200,000 of deliberate scope plus $1,850,000 of recovery from an unregistered risk is an assessment — and the second half of it is the part that should change how the program treats the next technical transfer.

7. Forecast

$16,990,000 remains against one pivotal read-out, one filing, a review period and a pre-approval inspection.

Remaining exposureReserve implication
PPQ campaign failureThree consecutive batches. A failure costs the sequence plus investigation — the largest single plausible draw remaining.
Pre-approval inspection findingR-07, rated Low. Remediation cost depends entirely on what is found.
Agency information requests during reviewUsually absorbed in regulatory effort; a request for new analysis is not.
Enrolment recovery beyond the current planAdditional sites are the recovery lever, and sites cost money.
Phase 3 read-outNo reserve implication. A failed pivotal does not draw contingency — it ends the program.
Everything above is mechanical. The last row is not. A contingency reserve funds recovery from problems that money can fix. It does not fund a molecule that does not work.

That is the correct reading of R-01 and R-02, and it means the reserve position — while worth watching — is not the thing to watch most closely. The largest uncertainty in this program has no financial mitigation at all.

Requests Declined

A register that records only approvals is a record of spending, not a record of control.

DateRequestAmountReason declined
2027-04-11Additional biomarker sub-study$3,200,000Scientifically interesting, not required for the filing and not in the TPP. Contingency is not a mechanism for funding scope the gate did not authorize.
2028-02-27Accelerated EU dossier preparation$2,400,000EU filing is explicitly out of scope (Charter §4). A declined scope item does not return as a contingency request.
2029-05-09Additional launch market research$900,000Commercial launch investment sits under a separate authorization. Declined on jurisdiction, not on merit.

Total declined: $6,500,000 — more than half again the $1,850,000 drawn for I-02.

Read the three reasons together — none of them is “too expensive.”

The biomarker sub-study was declined because contingency is not a mechanism for funding scope the gate did not authorize. The EU dossier was declined because a scope item the Charter explicitly excluded does not return through a side door. The market research was declined on jurisdiction, not merit — commercial launch investment has its own authorization and this reserve is not it.

Each of the three was, in isolation, a reasonable thing to want. A reserve that funds reasonable things is a general-purpose budget with a more respectable name, and it will not be there when an agency asks for a cardiovascular outcomes sub-study.

6. Remaining Reserve

MeasureAmount
Reserve at authorization$26,040,000
Drawn to date$9,050,000
Remaining$16,990,000
Remaining as % of unspent base14.6%

$16,990,000 remains against what is left of the program: completion of both pivotal trials and the cardiovascular sub-study, database lock, the NDA submission, the review period, and the pre-approval inspection.

Expressed against unspent base rather than against the original ceiling, the reserve is 14.6% — below the 12% the program was authorized with. That is the honest way to read it. A reserve percentage quoted against the original base flatters a program that has spent half its money, because the risk that remains is not proportional to the money already spent.

The exposure that is not in this register. The largest remaining uncertainty in this program is whether the pivotal trials meet their endpoints, and no contingency reserve covers that. A reserve funds recovery from problems that money can fix. It does not fund a molecule that does not work — which is the correct reading of R-01 and R-02, and the reason the reserve position, while worth watching, is not the thing to watch most closely.