← Drug Development Suite Governing Instrument · Vitalis Therapeutics Inc.

Development Committee Charter

Download Word

Vitalis Therapeutics Inc. — The governing instrument for the VitaFlow (VTX-401) development program. Constitutes the Development Committee, defines the five gate outcomes, and bounds what the Committee may decide. The Program Charter operates under this document.

7
Seats
5
Votes
4
Quorum
5
Defined outcomes
Contents
  1. Constitution & Standing
  2. Composition
  3. Quorum, Voting & Abstention
  4. Gate Outcomes
  5. Outcome Mechanics
  6. Delegated Authority
  7. Conditions
  8. Conflict of Interest & Recusal
  9. Authority Boundaries
  10. Cadence & Between-Gate Operation
  11. Gate Preparation
  12. Escalation
  13. Board Interface
  14. Dispute Resolution
  15. Alternates, Succession & Induction
  16. Reviewing the Governance Itself
  17. Records
  18. Document Control
  19. Amendment

1. Constitution & Standing

The Development Committee is the decision authority for the VitaFlow (VTX-401) development program. It is constituted by the Board of Vitalis Therapeutics Inc. and holds delegated authority to release funding tranche by tranche against the gate structure, up to the $243,040,000 ceiling recorded in the Program Charter.

The Committee is not a steering group and not an advisory body. It decides. A gate outcome is a Committee decision, minuted, and is not subject to reversal by any individual member including the Executive Sponsor. Where the Committee cannot decide, the outcome is HOLD — not an informal continuation.

Delegation boundary. The Committee may release tranches, issue and close conditions, approve changes within the authorized ceiling, and terminate the program. It may not raise the ceiling, alter the gate structure itself, or approve a change that takes the program outside the indication scope recorded at §3 of the Program Charter. Each of those is a Board matter.

2. Composition

MemberSeatVote
C. TyrrellProgram Director — Chair, seated from the PMONo vote
Dr. A. OkoyeChief Medical Officer — Executive SponsorVoting
Dr. H. VasquezChief Scientific OfficerVoting
Dr. P. RaghunathanSVP, Regulatory StrategyVoting
M. ThornburyChief Financial OfficerVoting
J. BarringtonSVP, Market Access & CommercialVoting
Dr. I. SolbergChief Quality OfficerObserver, no vote

Seven seats, 5 votes. Two seats do not vote, for different reasons.

Why the Chair does not vote

The Chair is the Program Director — the person accountable for the program's progress. A person accountable for progress who also votes on whether progress is sufficient is being asked to mark their own work, and the structural conflict does not disappear because everyone in the room is acting in good faith. Decision D-09 separates the two roles: the Chair certifies that evidence meets the recorded standard, and the Committee decides what the evidence means.

Why the Chief Quality Officer observes rather than votes

Quality obligations are not tradeable. A vote implies a position that can be outweighed by four others; GxP compliance cannot be outvoted (§7). The CQO therefore sits with full access, full speaking rights and a standing entry in the minutes, but no vote — because a vote would mischaracterize the nature of the obligation.

3. Quorum, Voting & Abstention

A gate cannot be held early. A gate may be re-scheduled later, but not brought forward to suit a calendar, because the criteria at §5 depend on evidence that exists only after the work is done. Gate 4 was scheduled deliberately after the End-of-Phase-2 meeting of 19 May 2026 for exactly this reason.

4. Gate Outcomes

Five outcomes are defined. A gate produces one of them and nothing else — there is no informal “proceed and we will sort it out”.

OutcomeEffectWhen it applies
GOThe stage passes. The next tranche is released in full and work proceeds against the approved scope.All must-meet criteria satisfied; no should-meet criterion scored below the threshold.
GO WITH CONDITIONSThe stage passes and the tranche is released, but named conditions are attached with owners, due dates and a recorded evidence standard. Failure to close a condition is itself a gate matter at the following gate.All must-meet criteria satisfied; one or more should-meet criteria scored at the threshold, where the gap is closeable inside the next stage without changing scope.
RECYCLEThe stage does not pass, but the concept survives. The program returns to the stage it was in, with a defined remediation scope and a re-convening date. No new tranche is released; remediation is funded from contingency against a named draw.A must-meet criterion is unsatisfied but is remediable with work the program can actually perform.
HOLDWork stops and funding is suspended pending an external event — an agency response, a competitor filing, a portfolio decision above the program. The program is not cancelled and the roster is not released.The decision cannot be taken on information the program is able to produce.
KILLThe program terminates. Remaining tranches are not released, the roster is released, and a closure accounting is produced within thirty days recording spend, salvage and what is transferable to other programs.A must-meet criterion is unsatisfied and is not remediable, or the business case no longer clears the hurdle on any defensible set of assumptions.
RECYCLE is the outcome most often missing from real governance models, and its absence is why programs drift. Without it, a committee facing an unsatisfied must-meet criterion has only two usable options — pass anyway, or kill a viable asset — and will almost always choose to pass anyway with an informal understanding. RECYCLE gives the committee somewhere to put a genuine “not yet”, with a remediation scope, a funded draw and a dated re-convening.

5. Outcome Mechanics

§4 defines what each outcome means. This section defines what each one requires, because an outcome with no procedural consequence is a label rather than a decision.

GO

The Chair issues a release notice against the next tranche within two working days. Vendor work packages for that stage are authorized by separate notice (see the Program Budget §6). No further Committee action.

GO WITH CONDITIONS

The tranche releases in full — conditions do not withhold funding, because a condition that starves the stage it attaches to cannot be closed. Each condition is entered in the register within five working days with owner, due date and verification method. The Chair reports condition status at every monthly checkpoint, and open conditions are a standing item at the next gate regardless of whether they are due.

RECYCLE

No tranche releases. The Chair produces a remediation scope within ten working days: what specifically must change, what it costs, who owns it, and the date the gate re-convenes. Remediation is funded from contingency against a named draw, which makes the cost of a recycle visible rather than absorbed. The roster is retained — releasing a team and rebuilding it is almost always more expensive than carrying it through a remediation window.

HOLD

Work stops on everything except the standing pools identified in the Program Budget §3 — regulatory affairs, program management, and the minimum required to maintain regulatory obligations and participant safety. A HOLD does not suspend pharmacovigilance, safety reporting, or the care of participants already dosed. The Chair sets a review date; an indefinite HOLD converts to KILL at the second review.

KILL

Remaining tranches are cancelled. A closure accounting is produced within thirty days recording total spend, contractual exit cost, salvage value, and what transfers to other programs — data, methods, qualified vendors, regulatory precedent. Participants already dosed are managed to protocol-defined follow-up; a program may be terminated commercially while continuing clinical obligations, and the two are budgeted separately.

KILL is not failure and is not treated as such. Given the probability of success recorded in the Program Charter §2, most development programs should end in KILL — that is what a portfolio of options means. A governance system that treats termination as a career event will not receive honest evidence at gates, which makes every other provision in this charter decorative.

6. Delegated Authority

Not every commitment reaches the Committee. Authority is delegated by value, and the thresholds exist so that the Committee's time is spent on decisions that matter rather than on approvals that merely feel important.

LevelThresholdConditions
Functional lead$250,000Within an approved stage tranche and against an approved work package.
Program Director (Chair)$1,500,000Within an approved stage tranche. Reported to the Committee at the next checkpoint.
Development Committee$24,960,000Any commitment within the authorized ceiling, including release of the full contingency reserve. Requires a minuted vote.
Board of DirectorsNo limitAny increase to the ceiling, any change to the gate structure, any indication-scope change.
The thresholds bind within a released tranche, not against the ceiling. A functional lead with $250,000 authority cannot spend it against a stage the Committee has not funded. Delegation governs who approves; tranche release governs whether the money exists. Confusing the two is how programs commit spend they have no authority to make.

Delegated commitments are reported upward at the next checkpoint, not sought in advance. A lead who splits a commitment into portions below their threshold to avoid escalation has breached this provision regardless of whether each portion was individually within authority.

7. Conditions

A GO WITH CONDITIONS outcome attaches conditions. Every condition carries, at issue and in the minutes:

  1. A named single owner — never a function, never two people.
  2. A due date, which may fall inside the stage or at the following gate.
  3. A verification method — what specific evidence will demonstrate closure.
  4. The criterion or risk the condition addresses, cross-referenced.
The verification method is fixed at issue and cannot be renegotiated at closure. This is the single most important provision in this document. A condition whose evidence standard can be softened when it comes due is not a condition; it is a note. The Chair verifies against the standard recorded when the condition was issued, and a request to change that standard is a Committee decision requiring a vote, minuted as such.

Live conditions at the status date

RefConditionOwnerDueStatus
GC-01Complete analytical method re-qualification at Aldergate for all three methodsDr. K. Oyelaran18 Dec 2026open
GC-02Confirm the cardiovascular sub-study protocol with the DMC before first CV-cohort dosingDr. S. Aldridge30 Nov 2026closed
GC-03Stand up the payer evidence plan and hold the first advisory boardsJ. Barrington31 Mar 2027at-risk

Full issue records, evidence standards and closure evidence live in the Gate Conditions Register.

8. Conflict of Interest & Recusal

A member declares a conflict where they hold a personal or financial interest in a vendor under consideration, or where they own the work being assessed at that gate.

A declared conflict results in recusal from the vote and from the deliberation, not merely from the vote. A member who remains in the room while a decision is discussed has participated in it. Recusal is minuted, and quorum is calculated on the remaining voting seats.

The Chair holds a standing structural conflict on every gate — the Chair owns program progress — which is why the Chair holds no vote at all rather than recusing gate by gate.

9. Authority Boundaries

Four matters lie outside the Committee's authority entirely. None of them can be reached by a vote, however unanimous.

MatterWho holds itWhy
Recommendation to pause or stop a trial for safetyIndependent Data Monitoring CommitteeGovernance may decide whether a program continues to be funded. It may not decide whether it is safe to continue dosing. The DMC is unblinded and the Committee is not; the recommendation is binding (C-05).
GxP compliance — GLP, GCP, cGMPRegulatory obligationNot a quality target that may be traded against cost or schedule. A gate cannot authorize a deviation (C-01).
Expedited safety reporting to the agencyPharmacovigilance, under regulationRuns on the regulatory clock, independent of program governance and of gate timing (C-04).
Site-level human subject protectionInstitutional Review BoardsSite activation follows IRB approval and is not accelerable by program decision (C-03).
The distinction that matters. A committee that believes it can vote on any question in front of it will eventually vote on one it has no business deciding, and it will do so under schedule pressure with the best of intentions. Naming the boundaries in the governing instrument — before the pressure arrives — is the only protection that works.

10. Cadence & Between-Gate Operation

ForumCadencePurpose
Gate reviewAt each gateDecision. Outcome per §4, minuted with the vote record.
Committee checkpointMonthlyStanding review of conditions, contingency draws and material risk movement. No gate authority; escalates to an extraordinary gate if required.
Program reviewFortnightlyChair and functional leads. Operational; produces the status report the Committee reads.
Extraordinary gateOn callConvened by the Chair or any two voting members where an event materially changes the basis of a prior decision.

Between gates the Chair maintains the conditions register and the readiness assessment for the next gate, so that a gate is a decision on a known position rather than a discovery exercise.

11. Gate Preparation

A gate is a decision on a known position, not a discovery exercise. The preparation timetable below runs in working days relative to the gate date and is the mechanism that makes that true.

DayStep
-30Chair issues the gate notice, criteria set and evidence schedule to functional leads.
-20Functional leads submit evidence packs. Late submission is recorded, not accommodated.
-15Chair certifies evidence against the recorded standard; deficiencies returned once.
-10Readiness assessment circulated to the Committee with the Chair's certification.
-5Committee members submit written questions; owners respond in writing before the gate.
Gate dayGate convenes. Deliberation, scoring, decision, conditions.
+5Minutes circulated including the score sheet and any conditions with owners and dates.
Deficient evidence is returned once. At day −15 the Chair certifies evidence against the recorded standard. Material deficiencies are returned to the owner with one opportunity to correct. Evidence still deficient at day −10 goes to the Committee as deficient, and the relevant criterion is scored on what was actually tabled.

The alternative — extending the deadline until the evidence improves — converts the gate from a decision point into a negotiation about readiness, which is the failure this timetable exists to prevent.

Between gates the Chair maintains the conditions register and the readiness assessment for the next gate, so the day −10 circulation is an update to a document the Committee has been watching rather than a first sight of the program's position.

12. Escalation

  1. Functional lead to Chair — anything that threatens a dated commitment.
  2. Chair to Committee — any matter that would change scope, breach a tranche, draw contingency, or place a condition at risk.
  3. Committee to Board — a ceiling increase, a change to the gate structure, an indication-scope change, or a KILL recommendation.

Escalation is not a failure state and is not held against the escalating party. The failure state is a program that absorbs a problem inside a stage and presents it at a gate as a fait accompli.

13. Board Interface

The Board constitutes the Committee and funds the program. It does not sit at gates and does not review gate decisions. Four things travel upward:

ReportTimingContent
Gate outcome notificationWithin 5 working days of every gateOutcome, vote record, conditions issued. Notification, not approval.
Quarterly program reportQuarterlySpend against released authority, contingency position, condition status, material risk movement, forecast to completion.
Exception reportWithin 5 working days of the triggerAny HOLD or KILL outcome, any DMC stopping recommendation, any regulatory action, any forecast breach of the ceiling.
Ceiling or scope requestAs requiredThe only category requiring a Board decision rather than a Board notification.
Three of the four are notifications; only one is a request. That asymmetry is deliberate. A Board that reviews gate outcomes becomes a second gate, and a program that knows its gate decision will be re-litigated upward will manage the Board rather than the gate. The Board holds the ceiling and the scope; the Committee holds everything inside them.

14. Dispute Resolution

Disagreement between functions is normal in a program where clinical, manufacturing, regulatory and commercial timelines genuinely compete. Three routes, in order:

  1. Between functional leads — resolved by the leads, with the Chair informed if the disagreement affects a dated commitment.
  2. Escalated to the Chair — the Chair decides, provided the decision sits within an approved tranche and does not alter scope. The decision and its rationale are minuted at the next program review.
  3. Escalated to the Committee — where the disagreement concerns scope, cost above the Chair's threshold, or a matter on which the Chair holds a conflict.
One dispute type does not follow this route. A disagreement about whether a safety signal requires action is not a program dispute and does not resolve through program governance. It goes to the Data Monitoring Committee and to Pharmacovigilance, whose obligations run independently of this charter (§8). A functional lead who raises a safety concern and is overruled by the Chair has a route directly to the Chief Medical Officer and the Chief Quality Officer, and that route cannot be closed by any provision of this document.

15. Alternates, Succession & Induction

16. Reviewing the Governance Itself

A governance system that is never assessed will drift toward whatever is comfortable. The Committee reviews its own operation annually against five measures.

MeasureInterpretation
Gate held on baselined dateTarget: within 4 weeks. Slippage indicates evidence production is not keeping pace with the gate calendar.
Conditions closed by due dateTarget: 100%. A pattern of extensions indicates conditions are being used to defer decisions rather than to close gaps.
Conditions reopened after closureTarget: zero. A reopened condition means the verification method was inadequate at issue.
Decisions reversed within two gatesTarget: zero. Reversal indicates the original decision was taken on insufficient evidence.
Escalations raised by functional leadsNo target. A count of zero is a warning sign, not a success — it usually means problems are being absorbed rather than surfaced.
The last measure is the one that matters most and is the easiest to misread. A program reporting zero escalations is not a well-run program; it is almost always a program where leads have learned that raising a problem is costlier than absorbing it. The measure has no target for that reason — it is read as a signal about culture, not as a performance indicator.

17. Records

Minutes record: attendance and quorum, the evidence tabled, the criteria assessment, the vote by name, any abstention with its stated reason, the outcome, and any conditions with their verification methods. Minutes are circulated within five working days and approved at the next forum.

The gate record is not amended after approval. Where a subsequent gate revises a figure or supersedes a decision, that is recorded at the later gate; the earlier record stands as it was. A governance history that is tidied retrospectively cannot be audited, and the tidying is usually where the interesting information was.

18. Document Control

19. Amendment

This charter is amended only by the Board of Vitalis Therapeutics Inc., on a recommendation carried by the Committee. The Committee cannot amend the instrument that constitutes it. Amendments are effective from the next gate and are not applied retrospectively to decisions already taken.