← Drug Development Suite Schedule, Scope & Resource · Vitalis Therapeutics Inc.

Milestone & Deliverable Plan

Download Excel
28
Milestones
16
Met at status date
15
The program can move
3
Nobody can move
Contents
  1. What a Milestone Is
  2. The Register
  3. Four Kinds of Milestone, and Who Can Actually Move One
  4. The Evidence Standard
  5. Position at the Status Date
  6. The One Ordering That Is Not Negotiable

1. What a Milestone Is

A milestone is a state, not an event, and not a piece of work. “Database locked” is a milestone because it is either true or it is not. “Phase 3 progressing well” is not a milestone; it is an opinion with a date attached. The distinction sounds pedantic until a program is three weeks from a gate and needs to know whether something happened.

RuleWhy it holds
A milestone is binaryNinety per cent complete is zero per cent complete. Partial credit is what turns a schedule into a narrative, and it is the mechanism by which a program reports green for eighteen months and then slips six.
It has one named ownerNot a function — a person. A milestone owned by “Clinical Operations” is owned by nobody at the moment it is missed.
Its evidence standard is fixed when the milestone is DEFINEDNot when it is claimed. The same discipline the Committee applies to gate conditions, for the same reason: the party who wants the milestone closed should never also be the party who decides what closing it requires.
It is dated from the schedule, not typed inEvery date in the register below is read from the integrated schedule. The two documents cannot disagree, because there is only one set of dates.
A deliverable is a thing; a milestone is a momentThe Statistical Analysis Plan is a deliverable. “SAP approved” is a milestone. Programs that conflate the two end up tracking documents that exist in draft forever.
The test for a well-formed milestone: could two people who disagree about the program's health still agree on whether this one has been met?

If the answer is no, the milestone is a status report wearing a milestone's clothes, and it will be argued about at precisely the moment the program can least afford the argument.

2. The Register

28 dated commitments across the life of the program. 16 met at the status date, 12 forecast.

RefDateMilestoneOwnerTypeEvidence standardAt Oct 15, 2026
M-01Dec 31, 2022Gate 1 — IND-Enabling ReadinessC. TyrrellInternalMinuted Committee decision with the scored criteria attachedMet
M-02Jun 30, 2023Investigational New Drug application (IND) submittedDr. P. RaghunathanRegulatoryAgency acknowledgment of receipt with an IND number assignedMet
M-03Jul 30, 2023IND in effectDr. P. RaghunathanStatutoryDay 30 elapsed with no clinical hold communicated — silence IS the evidenceMet
M-04Sep 30, 2023Phase 1 first participant dosedDr. R. MolyneuxInternalFirst dose recorded in the EDC against a signed consentMet
M-05Apr 13, 2024Phase 1 topline & dose selectionDr. S. AldridgeInternalTopline tables reviewed and the dose recommendation signed by the CMOMet
M-06Apr 22, 2024End-of-Phase-1 meeting heldDr. P. RaghunathanRegulatoryFDA official minutes received — not the sponsor's notesMet
M-07May 31, 2024Gate 3 — Phase 2 ReadinessC. TyrrellInternalMinuted Committee decision; Stage 3 tranche releasedMet
M-08Aug 31, 2024Phase 2 first participant randomizedDr. R. MolyneuxInternalInteractive Response Technology (IRT) randomization record against a signed, dated consent formMet
M-09Dec 31, 2024Phase 2 last participant randomizedDr. R. MolyneuxContractualIRT record; triggers a Contract Research Organization (CRO) milestone paymentMet
M-10Oct 24, 2025Phase 2 database lockDr. F. AchterbergInternalLock certificate countersigned by data management and the study statisticianMet
M-11Dec 9, 2025Phase 2 dose selection confirmedDr. S. AldridgeInternalDose rationale memo accepted by the Committee as Gate 4 evidenceMet
M-12Jan 9, 2026EOP2 briefing package submittedDr. P. RaghunathanRegulatoryAgency acknowledgment; the 30-day clock before the meeting starts hereMet
M-13May 19, 2026End-of-Phase-2 meeting heldDr. P. RaghunathanRegulatoryFDA official minutes; agreed initial Pediatric Study Plan (iPSP) due within 60 daysMet
M-14Jun 30, 2026Gate 4 — Phase 3 InitiationC. TyrrellInternalMinuted decision, conditions recorded with verification methods fixed at issueMet
M-15Jun 30, 2026Phase 3 first site activatedDr. R. MolyneuxInternalGreen-light letter issued — contract executed, IRB approved, site trainedMet
M-16Aug 30, 2026Registration batches releasedDr. K. OyelaranInternalThree batch records reviewed and dispositioned by Quality AssuranceMet
M-17Sep 30, 2027Phase 3 last participant randomizedDr. R. MolyneuxContractualIRT record; largest single CRO milestone payment in the program
M-18Dec 30, 2027Process validation completeDr. K. OyelaranInternalProcess Performance Qualification (PPQ) report approved; variability within the Stage 1 prediction
M-19Jul 30, 2028Statistical analysis plan approvedDr. F. AchterbergInternalSigned SAP, dated BEFORE the lock certificate
M-20Aug 5, 2028Pivotal database lockDr. F. AchterbergInternalLock certificate; unblinding authorization issued only after it
M-21Aug 10, 2028Pre-NDA meeting heldDr. P. RaghunathanRegulatoryFDA official minutes; content and format agreed
M-22Sep 30, 2028Gate 5 — New Drug Application (NDA) SubmissionC. TyrrellInternalMinuted decision; Stage 5 tranche released
M-23Oct 12, 2028NDA submittedDr. P. RaghunathanRegulatorySubmission receipt from the electronic gateway
M-24Dec 11, 2028Filing acceptanceDr. P. RaghunathanStatutoryDay-74 letter confirming filing and the review clock
M-25Jun 12, 2029Pre-approval inspection closedDr. I. SolbergRegulatoryInspection closeout; any Form 483 observation responded to within 15 working days
M-26Oct 11, 2029Action dateFDAStatutoryThe agency's action — nothing the sponsor produces is evidence of this
M-27Oct 11, 2029Gate 6 — Approval & LaunchC. TyrrellInternalMinuted decision taken on approval as an INPUT, not a forecast
M-28Nov 1, 2029First commercial shipmentL. WhitcombeContractualShipment confirmation against a released, serialized lot

3. Four Kinds of Milestone, and Who Can Actually Move One

The most useful column in the register is not the date. It is the type, because the type tells you what happens if the program wants to move it.

TypeCountShareWhat it means for the program
Internal1554%The program can move it. It still costs credibility.
Contractual311%Moving it costs money — it triggers a payment or a change order.
Regulatory725%The agency controls the date or the acceptance. The sponsor controls only readiness.
Statutory311%Arithmetic performed by somebody else. Not movable by anyone in this program.
Only 15 of 28 milestones are the program's to move.

The rest are held by a contract, by an agency, or by statute. That ratio is worth sitting with, because the instinct under schedule pressure is to look for the date that can give — and 13 of these cannot, at any price the program is able to pay.

The statutory three are the sharpest case. Filing acceptance is sixty days from submission and the action date is ten months from filing acceptance. Nobody in this program can move either. They are arithmetic performed by somebody else, and the only sponsor behavior that touches them is the kind that makes them worse.

The contractual three deserve their own note, because they carry a conflict that is easy to miss. Both Phase 2 and Phase 3 last-participant-randomized trigger milestone payments to Meridian. That is a normal and sensible contracting structure — it aligns the vendor with the thing the program actually needs. It also means the party that benefits from the milestone being declared is the party in the best position to declare it. Which is why the evidence standard for both is the IRT randomization record rather than a CRO status report: the system of record is neutral, and the sponsor reads it directly.

4. The Evidence Standard

Every row in the register carries one, and they are deliberately specific. Three patterns in them are worth naming.

PatternExampleThe reasoning
The evidence is external to the program“FDA official minutes received — not the sponsor's notes” (M-06, M-13, M-21)The sponsor's record of a meeting is a recollection. The agency's minutes are the record, they arrive within thirty days, and where the two differ the sponsor's is not the one that counts.
The evidence is an absence“Day 30 elapsed with no clinical hold communicated” (M-03)An IND is an exemption, not a permission. Nobody sends a letter saying it worked. Silence is the evidence, which is a genuinely uncomfortable thing to record as a milestone and is exactly why it should be recorded as one.
The evidence is a countersignature“Lock certificate countersigned by data management and the study statistician” (M-10, M-20)Two functions with different incentives both have to be willing to sign. A single signature on a database lock is a control that has been designed to be passable.
The evidence standard is fixed at definition and is not renegotiable at claim time.

This is the same rule the Committee applies to gate conditions, and it exists for the same failure. When a milestone is a week late, there is always a reasonable case for a slightly weaker proof: the data is in hand even if the certificate is not signed, the meeting happened even if the minutes have not arrived, the batches are made even if Quality has not dispositioned them. Each case is individually reasonable.

A standard that can be renegotiated by the person who needs it relaxed is not a standard. The program's answer is that the milestone is simply not met yet, which is a smaller and more honest statement than it feels like at the time.

5. Position at the Status Date

16 of 28 met, every one of them on or close to its planned date, and the program is nonetheless carrying a known schedule exposure. Both things are true, and holding them together is the point of this section.

Position
Milestones met16 of 28
Next milestone duePhase 3 last participant randomized — Sep 30, 2027, Dr. R. Molyneux
Milestone most at riskM-17 Phase 3 last participant randomized — 76 participants behind curve, and treatment duration is fixed at 68 weeks after it
Milestones the program could move if it had to15
A clean milestone record is not the same as a healthy program, and this is the artifact where that gap is most visible.

Every milestone met so far was met because it was defined as a state with a proof. None of them measures whether the program is on course for the ones ahead. The enrolment shortfall does not show up anywhere in the register until M-17 is missed — at which point it is roughly two years too late to respond.

Milestones are lagging indicators by construction. That is not a flaw; it is what makes them trustworthy. But it means a program that manages only its milestone register is steering by the wake, and it is why the register is read alongside the leading indicators in the enrolment dashboard rather than instead of them.

6. The One Ordering That Is Not Negotiable

Most of the register could be resequenced under pressure without damaging anything but confidence. Two rows could not.

RefMilestoneDate
M-19Statistical analysis plan approvedJul 30, 2028
M-20Pivotal database lockAug 5, 2028

The SAP is signed before the database is locked, and the database is locked before anyone is unblinded. The gap between those two milestones is 6 days, which is tight, and under schedule pressure it is exactly the kind of gap somebody proposes to close by running the two in parallel.

Reverse those two and the trial result becomes unfalsifiable.

An analysis plan written after the data is visible is not a plan; it is a description of a choice already made, and no reviewer can tell the difference between a pre-specified analysis and a well-chosen one after the fact. The entire evidentiary value of a pivotal trial rests on the sequence being provable: blind data review assigns the analysis populations while still blinded, the SAP is signed, the database is locked, and only then is anyone unblinded.

This ordering is asserted in the fact base. If a future edit dates the SAP after the lock, nothing in this suite builds — which is a strange place to enforce a scientific principle, and the right place, because it is the only one that cannot be talked out of it.

Everything else in this register is a commitment. This one is a constraint, and the difference is worth carrying: a commitment can be renegotiated with the people it was made to, and a constraint cannot be renegotiated with anybody.