Kickoff Deck · Portfolio Demo

CWP-700 Composite Wing Panel Production

Download PowerPoint
Program Kickoff · Phase 1, Day 1

CWP-700 Composite Wing
Panel Production Program

Eighteen months. Twenty-five people across two phases. One First Article Meridian will actually accept.
May 15, 2026Kickoff Date
C. TyrrellProgram Manager
25Team Members (Both Phases)
1
Agenda

What We'll Cover Today

1
Welcome & Program Context
2
Why This Program Matters
3
Success Criteria
4
Scope: In and Out
5
The Program Team
6
Milestone Timeline
7
Budget Overview
8
How We'll Work Together
9
Risks We're Watching
10
Next Steps & Q&A
2
Welcome

Glad You're Here

Nine of us are in the room today. Sixteen more join as we ramp to two-shift production — every one of them is on this deck too.

Acme's delivery team and Meridian's Program Office are aligning today on program scope, the staged qualification approach, and working cadence before Phase 1 begins. Quick round of introductions: name, role, and what you're most excited (or nervous) about.

25
Named Team, Both Phases
18
Months, Phase 1 + 2
2
Production Shifts
3
The Business Case

Why We're Doing This

A Tier 1 composite supplier's quality history is a leading indicator of First Article outcomes on a new part number — and Meridian was watching ours closely.

This is Acme's first dedicated production contract for the M7 platform, awarded after a competitive source-selection process. Full detail lives in the Program Charter.

$5.2M
Total Program Budget
Month 8
Production Ramp Begins
4
Success Criteria

What Success Looks Like

1
First Article Inspection accepted by Meridian within the Phase 1 schedule
2
Phase 2 ramps to full contracted rate with on-time delivery performance
3
Program closes within the $5.2M budget, $0 variance to baseline
4
All MRB dispositions closed with documented root cause and corrective action
5
Zero nonconformances reach Meridian undetected
5
Scope

Where the Lines Are

In Scope

  • Design-to-print manufacture of composite trailing-edge wing panels
  • Tooling design, fabrication, and qualification
  • First Article Inspection per AS9102
  • Steady-state production at contracted rate
  • MRB support, supplier quality, and lot-level traceability

Out of Scope

  • Engineering design of the wing panel itself (Meridian-owned)
  • Final aircraft assembly and flight test
  • Any ITAR-controlled defense-article work (commercial program)
  • Tooling design beyond the CWP-700 panel family
6
The Program Team

Everyone Who's Building This

C. Tyrrell
Program Manager
R. Kessler
Quality Engineering Lead (AS9100 Owner)
M. Osei
Manufacturing Engineer

Engineering

L. VanceMaterials / NDT Engineer
A. WhitfieldPhase 1 · Tooling Engineer
J. FerraroPhase 2 · MRB Chair / Sr. QE

Quality & Supply Chain

S. PhamSupplier Quality Engineer
D. OkaforProgram Coordinator
R. BianchiPhase 2 · Buyer / Procurement
H. LindgrenPhase 2 · Doc Control / CM
V. CastellanosPhase 2 · EHS & Facilities

Production — Shift 1

K. RutherfordLayup Tech, Shift 1 Lead
T. AlvaradoPhase 2 · Layup Tech
M. VartanPhase 2 · Autoclave / Cure Tech
D. HalvorsenPhase 2 · Trim & Drill Tech
R. AchebePhase 2 · NDT Technician
B. SolisQuality Inspector

Production — Shift 2

C. OkwuosaPhase 2 · Layup Tech, Shift 2 Lead
P. MensahPhase 2 · Layup Tech
A. DelacroixPhase 2 · Layup Tech
J. WhitbyPhase 2 · Layup Tech
S. OkoroPhase 2 · Autoclave / Cure Tech
L. FontainePhase 2 · Trim & Drill Tech
K. SorensenPhase 2 · NDT Technician
N. VasquezPhase 2 · Quality Inspector

All 25, same as the Resource Plan and Org Chart. Phase 2 tags mark the 16 who join as we ramp to two-shift production — not omitted, just not onboarded yet: Resource Plan · Org Chart

7
Timeline

The Road to Full Rate

Kickoff
May 15
Tooling Qualified
Month 3
First Article Accepted
Month 6
Production Ramp Begins
Month 7
Full Rate Achieved
Month 12
Program Closeout
Month 18

Full interactive schedule: WBS/Gantt Console

8
Budget

Where the Money Goes

$5.2M
TOTAL BUDGET
Labor — 25-Person Team
Tooling, Fixtures & FAI Testing
Materials & Travel
Program Management Reserve

This is a fixed-price contract — Acme bears the internal cost risk of scrap or rework, not Meridian. Getting this budget right matters.

Full detail and the 25-person rate card: Resource Plan

9
Working Together

How We'll Stay in Sync

CadenceForumPurpose
WeeklyProgram Status ReviewSchedule, budget, RAIDD review
Bi-weekly (weekly Phase 2)Quality Review BoardOpen MRB cases, FAI status, supplier quality
MonthlyJoint Program Review with MeridianDelivery performance, open issues, schedule
Once, end of Phase 1FAI Gate ReviewFormal go/no-go for Phase 2 production release

Full governance model and decision rights: Program Governance Model

10
Eyes Open

Risks We're Watching From Day One

!
Single-source composite material lead time
!
NDT capacity sized for the wrong production phase
!
Tight tooling-qualification schedule
!
Customer source-inspection scheduling

Full risk register: RAIDD Log

11
Next Steps

What Happens Next

1
Tooling concept design begins immediately (layup mandrel, trim/drill fixture)
2
Supplier quality kickoff with raw material sources this week
3
First Weekly Program Status Review scheduled for next week
12

Let's Build a First Article Meridian Accepts the First Time.

C. Tyrrell, Program Manager
CWP-700 Composite Wing Panel Production Program
13