← Aerospace Suite 00 · Program Foundations

Work Breakdown Structure

Download Excel Download MS Project

Full Gantt-parity schedule — every task carries a real start/finish date, duration, predecessor dependency, percent complete, and named resource assignment, matching the structure of the PM suite's own Work Breakdown Structure. Import the MS Project file into Microsoft Project (or a compatible tool) for the native Gantt chart view, or use the table below / Excel export for a flat reference.

WBS #TaskStartFinishDuration (d)Predecessors% CompleteAssigned To
1Phase 1: Qualification & First Article2026-02-022026-06-090100%
1.1Production tooling design2026-02-022026-03-0926100%A. Whitfield
1.2Production tooling fabrication2026-03-102026-04-22321.1100%A. Whitfield
1.3Raw material qualification (PPAP)2026-02-022026-02-2518100%S. Pham
1.4Initial composite layup (tooling qualification run, S/N 0001)2026-04-232026-04-3061.2, 1.3100%K. Rutherford
1.5NDT ultrasonic scan (initial run)2026-05-012026-05-0531.4100%L. Vance
1.6Quality inspection (initial run, dimensional + visual)2026-05-062026-05-1141.5100%B. Solis
1.7FAI full dimensional layout2026-05-122026-05-1851.6100%M. Osei
1.8FAI documentation (AS9102 Form 1/2/3 package)2026-05-192026-05-2241.7100%R. Kessler
1.9MRB-001 disposition (edge-trim rework)2026-05-252026-05-2951.8100%R. Kessler
1.10Rework and FAI re-inspection2026-06-012026-06-0861.9100%K. Rutherford, B. Solis
1.11Milestone Gate: FAI Accepted, Customer Source Inspection Witness ◆2026-06-092026-06-0901.10100%C. Tyrrell
2Phase 2: Production Ramp & Steady-State2026-06-102027-06-14052%
2.1Production release authorization2026-06-102026-06-1011.11100%C. Tyrrell
2.2Composite layup production ramp (3-technician rotation)2026-06-112027-06-072582.155%K. Rutherford, T. Alvarado, C. Okwuosa
2.3NDT inspection (production rate)2026-06-112027-05-242482.155%L. Vance
2.4Quality inspection (production rate, 2-inspector rotation)2026-06-112027-05-242482.155%B. Solis, N. Vasquez
2.5MRB case management (MRB-002 through MRB-005)2026-06-112027-03-172002.155%J. Ferraro
2.6Supplier PPAP maintenance & incoming lot verification2026-06-112027-05-312532.155%S. Pham
2.7Purchase order execution & supplier scheduling2026-06-112027-03-172002.155%R. Bianchi
2.8Preventive maintenance program (layup fixture, post MRB-004)2026-06-112026-06-24102.140%M. Osei
2.9Program status reporting & RAIDD log maintenance2026-06-112027-05-312532.155%D. Okafor
2.10Milestone: Program Closeout2027-06-082027-06-1452.2, 2.3, 2.4, 2.5, 2.6, 2.7, 2.8, 2.90%C. Tyrrell

◆ = milestone (zero-duration gate). Durations are business days (8hr/day, Mon-Fri calendar). Predecessor links are finish-to-start.