Program Status Report

Download Word

Weekly status report snapshot for the CWP-700 Composite Wing Panel Production Program, taken mid-Phase 2 (Production Ramp & Steady-State), showing overall program health, budget, schedule, and open quality items.

Program Health

DimensionStatusComment
ScheduleGreenPhase 2 production rate on track; Phase 1 FAI 3-week buffer was fully consumed but did not slip the overall program end date.
BudgetGreenActuals tracking to the $3,500,000 total program budget; no reserve draw to date.
QualityYellowNDT queue backlog (RAIDD I-02) added ~4 days to panel release cycle time; mitigation (second NDT technician) in place.
ScopeGreenNo engineering changes from Meridian Aircraft Co. since contract baseline (RAIDD A-01 holding).

This Period

Next Period