Agile RACI

Download Excel

Responsibility assignment for the recurring activities that keep an Agile program running — distinct from a PMBOK RACI in that most rows are ceremony ownership and backlog decisions, not deliverable sign-off. Where PM Suite's RACI splits into a Deliverable Sign-off matrix and a separate Governance-Process matrix, this program keeps a single table, since MedConnect Mobile's two-team, 18-week scope doesn't generate enough distinct governance-process decisions (approving a Change Request, accepting a risk) to justify a second table the way a larger, longer-running program would — those decisions are instead covered activity-by-activity below, alongside the ceremony ownership they're adjacent to.

A few patterns are worth reading the table for, not just looking up individual cells. First: the Product Owner (D. Ashworth) is Accountable for more rows than anyone else, which is expected in a Scrum structure — the PO is the single point where backlog, release, and steering-committee accountability converge, even though the actual Responsible work for most ceremonies sits with the Scrum Masters and Engineering Leads who run them day to day. Second: Dev Teams are never Accountable for anything on this table — they're Responsible for delivering against ceremonies and sign-offs, but accountability for those ceremonies existing and functioning sits with the Scrum Masters and Engineering Leads who own them. Third, and most telehealth-specific: Dr. Nguyen (CMIO) and T. Brannigan (Compliance) appear as Accountable only twice each, on the two rows that exist specifically because this is a healthcare-adjacent product — clinical workflow sign-off and PHI/compliance review — and Consulted on Definition of Done sign-off for exactly the same reason (marked with an asterisk below). Everywhere else on this table, they're Informed at most, which is intentional: their authority is narrow and specific (see Program Governance §9's veto language), not a general oversight role over every ceremony.

RResponsible AAccountable CConsulted IInformed
Activity D. Ashworth
Product Owner
C. Tyrrell
Agile Delivery Lead
Scrum Masters
(Marsh / Okafor)
Eng. Leads
(Whitfield / Singh)
Dev Teams M. Delacroix
Sponsor
Dr. Nguyen
CMIO
T. Brannigan
Compliance
Backlog prioritizationA/RCICICCI
Writing acceptance criteriaACICCCC
Sprint Planning facilitationCCA/RRR
Daily Standup facilitationIIA/RCR
Scrum-of-Scrums facilitationIA/RRRI
Sprint Review / DemoARRRRIII
Sprint RetrospectiveIIA/RCR
Definition of Done sign-off (per story)ACCRRC*C*
Clinical workflow sign-offCICIA/R
PHI / compliance reviewIICIA/R
Release/go-live decisionARCCACC
Steering Committee reportingCA/RIII
Cross-team dependency resolutionIARR
Change Request approval (Tier 2, see Governance §3)CRICAII
Vendor SLA / scorecard review (PulseConnect)IIA/RI
Vendor offboarding certification (Vantix)ICIA/R

*Consulted only when the story touches PHI or a clinical workflow — see Definition of Done, telehealth-specific additions.

The last three rows above were added to make this table a complete cross-reference with the Program Governance Model's decision-rights tiers and vendor governance sections, rather than covering ceremonies alone — a Change Request's approval path, and each vendor relationship's ongoing accountability, are responsibility-assignment questions just as much as who runs standup is.