← Agile/Scrum Suite 25 · Governance & Stakeholder

Change Control Log

Download Excel

Three formal Change Requests were raised on this program — all affecting a baselined commitment (budget or schedule), which is why they went through this formal path rather than ordinary backlog reprioritization (see Change Handling in Agile for where that line sits). All three were approved and implemented.

CR-01
Additional Staging/Load-Test Environment
Implemented
CostRaised: Sprint 4Approved By: M. Delacroix (Sponsor)
Cost Impact
+$18,000
Schedule Impact
None
Scope Impact
None

A. Singh flagged that load-testing the video visit infrastructure against a production-realistic patient volume required a dedicated staging environment separate from the shared dev/test environment already in use — running load tests there risked disrupting both teams' daily work. Requested and approved as a one-time infrastructure cost ahead of Release 1 hardening (Sprint 5).

Outcome if not approved: Load testing would have run against the shared environment, risking test interference for both teams during Release 1's critical hardening sprint. Approved same-week to avoid that risk.
CR-02
Contractor Support for Sprint 7 Data Migration Remediation
Implemented
CostRaised: Sprint 6Approved By: M. Delacroix (Sponsor)
Cost Impact
+$42,000
Schedule Impact
None (absorbed)
Scope Impact
None

Ahead of Sprint 7's full historical record migration, early data-quality spot-checks on the legacy archive surfaced more inconsistent field mappings than the original migration pipeline (built in Sprint 1) was designed to handle automatically. Rather than risk the Sprint 8 cutover date, Anchor requested two short-term contractors for Sprint 7 only to build additional remediation scripts. This is the change referenced as risk R-04 in the RAIDD Log and the Sprint 6 Status Report's Amber budget rating.

Outcome if not approved: Anchor's existing team would have had to absorb the remediation work inside Sprint 7's existing capacity, risking either the migration quality or the Sprint 8 cutover date. Approved to protect the fixed cutover date instead.
CR-03
Extend Pre-Cutover Compliance Review Window (2 Days → 5 Days)
Implemented
ScheduleRaised: Sprint 7Approved By: M. Delacroix (Sponsor) + T. Brannigan (Compliance)
Cost Impact
None
Schedule Impact
Internal only — no program-end slip
Scope Impact
None

The full historical migration's larger-than-planned remediation effort (see CR-02) meant Compliance needed more than the originally planned 2 business days to validate the archive before Release 2 cutover. The Sprint 8 sprint boundary and May 8 go-live date did not move — instead, the final regression-testing window inside Sprint 8 was compressed from 4 days to 1 day to make room. This trade-off was explicitly accepted (not silently absorbed) and logged as an accepted residual risk rather than a schedule slip.

Outcome if not approved: Either the compliance review would have been rushed on the original 2-day window (unacceptable risk on a PHI/patient-safety validation), or the May 8 cutover date would have slipped. The team chose to compress regression testing instead, with Compliance and the Sponsor both explicitly signing off on that trade-off.
Summary
Approval Authority (Decision-Rights Tiering)

Backlog reprioritization within approved scope: Product Owner decides directly, no CR needed. Anything affecting the cost baseline, the release date, or a compliance-relevant timeline: Sponsor approval required (and Compliance co-approval when the change touches a PHI/patient-safety review, as in CR-03). This program never required a full Steering Committee vote for a CR — appropriate to its size, compared to the Enrollment & Claims program's heavier approval chain for its $7M baseline.