Agile RAIDD Log

Download Excel

Risks, Assumptions, Issues, Dependencies, and Decisions — the same RAIDD structure as the Enrollment & Claims PM Suite, but populated the way it actually gets used on an Agile program: dependencies are mostly cross-team (tracked here and on the Jira board), and several entries trace directly back to specific ceremonies you've already seen.

4
Risks
3
Assumptions
2
Issues
3
Dependencies
5
Decisions
RisksAssumptionsIssues DependenciesDecisions

Risks

Uncertain future events that could affect the program.

IDRiskSeverityMitigationStatus
R-01Full historical data migration (Sprint 7) could surface data-quality issues in legacy archive records, requiring remediation timeMediumPre-cutover validation report + spot-check process (same pattern used successfully for Release 1's active-patient migration)Closed — migration completed within estimate
R-02Third-party video SDK's screen-share feature could require additional vendor configuration not originally scopedMediumSpike performed during Sprint 3 refinement; re-estimated MCM-123 from 5 to 8 ptsClosed — realized as a scope/estimate change, not a schedule risk
R-03Cross-team dependencies surfacing too late in a sprint to resolve without schedule impactMediumSprint 2 retro actions — dependency owner field, standing Scrum-of-Scrums agenda itemClosed — confirmed effective at Sprint 3 retro
R-04Team cost run-rate tracking slightly ahead of planned burn heading into the highest-effort remaining sprintMediumMonitored weekly against Sprint 7–8 forecast; two short-term contractors approved for Sprint 7 remediation only (see CR-02, +$42,000)Closed — program finished within budget

Assumptions

Conditions taken as true for planning purposes.

IDAssumptionValidated?
A-01The video SDK vendor's existing BAA (executed during vendor selection) covers the telehealth use case without renegotiationConfirmed — T. Brannigan, Sprint 3 Planning
A-02Both teams can sustain a consistent 2-week sprint cadence without holiday/PTO disruption beyond what was planned for in capacityHeld true
A-03The pilot patient cohort (Release 1) is representative enough to surface major usability issues before full rolloutHeld true — no major issues surfaced beyond MCM-155 feature request

Issues

Problems that have already occurred and need resolution.

IDIssueSeverityResolutionStatus
I-01MCM-111 blocked in Sprint 2 waiting on Anchor's availability engine (MCM-160) code reviewMediumSame-day escalation between Engineering Leads; review completed within hoursClosed, Sprint 2
I-02MCM-181 (rollback runbook) descoped from formal Sprint 5 board tracking, completed manually insteadLowAccepted as a one-off; no process change needed since it didn't recurAccepted

Dependencies

Cross-team or external dependencies tracked at the program level (in addition to being linked on the Jira board).

IDDependencyOwnerStatus
D-01Falcon's booking/reschedule UI (MCM-111) depends on Anchor's availability engine API (MCM-160)A. Singh (Anchor)Resolved, Sprint 2
D-02Falcon's video join flow (MCM-120) depends on Anchor's video SDK integration (MCM-121)A. Singh (Anchor)Resolved, Sprint 3–4
D-03Release 2 cutover depends on Compliance sign-off of the full historical migration validation reportT. Brannigan (Compliance)Resolved, Sprint 8

Decisions

Formal program-level decisions, each traceable to the ceremony or meeting where it was made.

IDDecisionMade AtMade By
DEC-01Definition of Done updated to require clinical workflow sign-off for scheduling/visit-launch/notes-handoff storiesProgram KickoffDr. L. Nguyen, endorsed by C. Tyrrell
DEC-02Compliance review checkpoint added before both Release 1 and Release 2 (not a single end-of-program gate)Program KickoffT. Brannigan
DEC-03Split MCM-133 into a data-mapping story and a UI story to reduce single-sprint delivery riskSprint 3 Backlog RefinementC. Tyrrell + both teams
DEC-04Hold Release 1 to the pilot cohort rather than full rollout immediately after MVP launchSprint 5 ReviewM. Delacroix (Sponsor)
DEC-05Release 2 Go/No-Go: GO — all acceptance criteria, compliance, and clinical sign-offs metSprint 8 ReviewM. Delacroix (Sponsor)
DEC-06Original 13-person, $1,850,000 resource estimate corrected to a 28-person, $3,617,000 delivery team — the initial plan staffed leads and one developer per platform but no real bench (no UX/UI design, no dedicated Provider Console frontend developer, no data migration owner, no QA test bench beyond team leads, no Business Analyst, no cross-team Solutions Architect). Corrected before Sprint 1 Planning so the real team, not the estimate, executed the program.Program Kickoff / pre-Sprint 1C. Tyrrell, approved by M. Delacroix (Sponsor)