Why this exists, and why it's light: this program never ran a formal SAFe Program Increment (PI)
Planning event or Agile Release Train — two teams didn't warrant that overhead (see the Team Charter and
Glossary). But Release 1 and Release 2 functioned as informal Program Increments, and it's worth showing that
structure explicitly: team-level objectives with business-value scoring, and risks tracked in the SAFe-standard
ROAM format (Resolved / Owned / Accepted / Mitigated) — the parts of PI Planning that added real value here,
without the full ceremony.
PI 1 (informal) — Release 1 / MVP
Sprints 1–5 · Jan 19–Mar 27, 2026
| Team | Objective | Business Value (1–10) | Outcome |
|---|---|---|---|
| Falcon | Patients can register, book, and complete a video visit end-to-end on mobile | 9 | Achieved |
| Falcon | Reconnect gracefully within a 5-minute window after a dropped video connection | 7 | Achieved |
| Anchor | Provider console supports full daily schedule view and one-tap visit launch | 8 | Achieved |
| Anchor | Active-patient records migrated with a validated, zero-critical-defect data-integrity report | 10 | Achieved |
ResolvedVideo SDK BAA coverage confirmed pre-PI
MitigatedScreen-share entitlement gap — re-estimated & absorbed in Sprint 3–4
OwnedCross-team dependency visibility — owned by C. Tyrrell, addressed via Scrum-of-Scrums change
PI 2 (informal) — Release 2 / Cutover
Sprints 6–8 · Mar 30–May 8, 2026
| Team | Objective | Business Value (1–10) | Outcome |
|---|---|---|---|
| Falcon | Patients can securely message their care team and request prescription refills | 8 | Achieved |
| Anchor | Provider visit notes push directly into the EHR without manual re-entry | 9 | Achieved |
| Anchor | Full historical patient migration complete; CareLink Classic fully decommissioned | 10 | Achieved |
| Falcon | Release 2 regression pass with zero critical defects at cutover | 9 | Achieved |
OwnedHistorical migration data-quality risk — owned by A. Singh, resolved via CR-02 contractor support
AcceptedCompressed final regression window (CR-03 trade-off) — accepted by Sponsor + Compliance
ResolvedFull historical migration validated with zero critical defects
Predictability across both informal PIs: 8 of 8 objectives achieved (100%) — consistent with the program's overall ~94% story-point predictability on the Velocity Chart.