PI Objectives (Light SAFe)

Download Word
Why this exists, and why it's light: this program never ran a formal SAFe Program Increment (PI) Planning event or Agile Release Train — two teams didn't warrant that overhead (see the Team Charter and Glossary). But Release 1 and Release 2 functioned as informal Program Increments, and it's worth showing that structure explicitly: team-level objectives with business-value scoring, and risks tracked in the SAFe-standard ROAM format (Resolved / Owned / Accepted / Mitigated) — the parts of PI Planning that added real value here, without the full ceremony.

PI 1 (informal) — Release 1 / MVP

Sprints 1–5 · Jan 19–Mar 27, 2026
TeamObjectiveBusiness Value (1–10)Outcome
FalconPatients can register, book, and complete a video visit end-to-end on mobile9Achieved
FalconReconnect gracefully within a 5-minute window after a dropped video connection7Achieved
AnchorProvider console supports full daily schedule view and one-tap visit launch8Achieved
AnchorActive-patient records migrated with a validated, zero-critical-defect data-integrity report10Achieved
ResolvedVideo SDK BAA coverage confirmed pre-PI
MitigatedScreen-share entitlement gap — re-estimated & absorbed in Sprint 3–4
OwnedCross-team dependency visibility — owned by C. Tyrrell, addressed via Scrum-of-Scrums change

PI 2 (informal) — Release 2 / Cutover

Sprints 6–8 · Mar 30–May 8, 2026
TeamObjectiveBusiness Value (1–10)Outcome
FalconPatients can securely message their care team and request prescription refills8Achieved
AnchorProvider visit notes push directly into the EHR without manual re-entry9Achieved
AnchorFull historical patient migration complete; CareLink Classic fully decommissioned10Achieved
FalconRelease 2 regression pass with zero critical defects at cutover9Achieved
OwnedHistorical migration data-quality risk — owned by A. Singh, resolved via CR-02 contractor support
AcceptedCompressed final regression window (CR-03 trade-off) — accepted by Sponsor + Compliance
ResolvedFull historical migration validated with zero critical defects

Predictability across both informal PIs: 8 of 8 objectives achieved (100%) — consistent with the program's overall ~94% story-point predictability on the Velocity Chart.