Overall Program
Green
Schedule
Green
Scope
Green
Budget
Amber
Quality
Green
Sprint Summary
Release 1 (MVP) has been live with the pilot patient cohort since Sprint 5 with no critical defects reported. Sprint 6 delivered secure patient messaging and started prescription refill request functionality, on pace for Release 2 in Sprint 8 as planned.
Accomplished This Sprint
- Secure patient-to-care-team messaging shipped (MCM-150)
- Provider templated-reply messaging in console (MCM-151)
- Continued work on prescription refill request flow (MCM-152, on track for Sprint 7)
- 42 of 44 committed points delivered (96% predictability, consistent with program average)
Planned Next Sprint (Sprint 7)
- Complete prescription refill request + e-prescribing workflow routing (MCM-152, MCM-153)
- Full historical patient record migration begins (MCM-143) — Anchor's primary focus
- Pre-cutover compliance review scheduled with T. Brannigan
Risks & Issues
| Item | Impact | Rating |
|---|---|---|
| Full historical migration (Sprint 7) is the single largest remaining story (13 pts) — limited slack if data-quality issues surface in legacy archive records | Could push Release 2 cutover date if significant remediation is needed | Medium |
| Team cost run-rate tracking slightly ahead of planned burn (see Budget below) | No schedule impact; monitoring for Sprint 7–8 | Medium |
| Provider feedback requesting intake-to-notes pre-population (MCM-155) | New candidate backlog item, not committed — no impact to current scope | Low |
Budget Health
Program budget: $1.85M (team cost, licensing, infrastructure) · Spent to date (through Sprint 6): $1.42M (76.8%) against 77.8% of program duration elapsed — effectively on track, tracked Amber only because Sprint 7's migration remediation risk (above) could increase contractor hours if legacy data issues are more extensive than estimated.
Upcoming Milestones
| Milestone | Target | Status |
|---|---|---|
| Full historical data migration complete | Sprint 7 (Apr 24) | On track |
| Pre-cutover compliance sign-off | Sprint 7 | Scheduled |
| Release 2 go-live / CareLink Classic decommission | Sprint 8 (May 8) | On track |
| Program closeout & lessons learned | Post-Sprint 8 | Planned |