Sprint Status Report — Sprint 6

PERIOD: Mar 30 – Apr 10, 2026 PREPARED BY: C. Tyrrell AUDIENCE: Steering Committee
Download Word
Overall Program
Green
Schedule
Green
Scope
Green
Budget
Amber
Quality
Green

Sprint Summary

Release 1 (MVP) has been live with the pilot patient cohort since Sprint 5 with no critical defects reported. Sprint 6 delivered secure patient messaging and started prescription refill request functionality, on pace for Release 2 in Sprint 8 as planned.

Accomplished This Sprint

  • Secure patient-to-care-team messaging shipped (MCM-150)
  • Provider templated-reply messaging in console (MCM-151)
  • Continued work on prescription refill request flow (MCM-152, on track for Sprint 7)
  • 42 of 44 committed points delivered (96% predictability, consistent with program average)

Planned Next Sprint (Sprint 7)

  • Complete prescription refill request + e-prescribing workflow routing (MCM-152, MCM-153)
  • Full historical patient record migration begins (MCM-143) — Anchor's primary focus
  • Pre-cutover compliance review scheduled with T. Brannigan

Risks & Issues

ItemImpactRating
Full historical migration (Sprint 7) is the single largest remaining story (13 pts) — limited slack if data-quality issues surface in legacy archive recordsCould push Release 2 cutover date if significant remediation is neededMedium
Team cost run-rate tracking slightly ahead of planned burn (see Budget below)No schedule impact; monitoring for Sprint 7–8Medium
Provider feedback requesting intake-to-notes pre-population (MCM-155)New candidate backlog item, not committed — no impact to current scopeLow

Budget Health

Program budget: $1.85M (team cost, licensing, infrastructure) · Spent to date (through Sprint 6): $1.42M (76.8%) against 77.8% of program duration elapsed — effectively on track, tracked Amber only because Sprint 7's migration remediation risk (above) could increase contractor hours if legacy data issues are more extensive than estimated.

Upcoming Milestones

MilestoneTargetStatus
Full historical data migration completeSprint 7 (Apr 24)On track
Pre-cutover compliance sign-offSprint 7Scheduled
Release 2 go-live / CareLink Classic decommissionSprint 8 (May 8)On track
Program closeout & lessons learnedPost-Sprint 8Planned