Steering Committee Deck

Download PowerPoint
Monthly Steering Committee Update

MedConnect Mobile

Sprint 6 Checkpoint · Apr 10, 2026 · Presented by C. Tyrrell
Slide 1 of 7

Program Status at a Glance

Overall
Green
Schedule
Green
Scope
Green
Budget
Amber
Quality
Green

Release 1 (MVP) is live with the pilot patient cohort since Sprint 5, zero critical defects. Release 2 (full cutover) remains on track for Sprint 8, May 8.

Slide 2 of 7

Delivery Progress

Sprints complete6 of 8
Avg. velocity43 pts/sprint
Predictability~94%
Scope delivered247 / 342 pts

See the Velocity Chart and Release Burnup for full detail.

Slide 3 of 7

Release Timeline

MilestoneDateStatus
Release 1 (MVP) — pilot cohort go-liveMar 27, 2026Complete
Full historical data migrationApr 24, 2026On track
Release 2 — full cutover & CareLink Classic decommissionMay 8, 2026On track
Slide 4 of 7

Top Risks

Full detail in the Agile RAIDD Log.

Slide 5 of 7

Budget

$1.85M total program budget · $1.42M spent to date (76.8%) against 77.8% of duration elapsed — effectively on track.

Slide 6 of 7

Team Health

Slide 7 of 7

Decision Requested / Next Steps

No Sponsor decision required this cycle. Program remains within approved scope, schedule, and budget tolerance. Next Steering Committee update will include the Release 2 Go/No-Go outcome following Sprint 8 Review.