Monthly Steering Committee Update
MedConnect Mobile
Sprint 6 Checkpoint · Apr 10, 2026 · Presented by C. Tyrrell
Slide 1 of 7
Program Status at a Glance
Overall
GreenSchedule
GreenScope
GreenBudget
AmberQuality
GreenRelease 1 (MVP) is live with the pilot patient cohort since Sprint 5, zero critical defects. Release 2 (full cutover) remains on track for Sprint 8, May 8.
Slide 2 of 7
Delivery Progress
Sprints complete6 of 8
Avg. velocity43 pts/sprint
Predictability~94%
Scope delivered247 / 342 pts
See the Velocity Chart and Release Burnup for full detail.
Slide 3 of 7
Release Timeline
| Milestone | Date | Status |
|---|---|---|
| Release 1 (MVP) — pilot cohort go-live | Mar 27, 2026 | Complete |
| Full historical data migration | Apr 24, 2026 | On track |
| Release 2 — full cutover & CareLink Classic decommission | May 8, 2026 | On track |
Slide 4 of 7
Top Risks
- Medium: Full historical migration (Sprint 7) is the largest remaining story — limited slack if legacy data-quality issues surface
- Medium: Budget run-rate tracking slightly ahead of plan heading into the highest-effort remaining sprint — monitored, no action needed yet
Full detail in the Agile RAIDD Log.
Slide 5 of 7
Budget
$1.85M total program budget · $1.42M spent to date (76.8%) against 77.8% of duration elapsed — effectively on track.
Slide 6 of 7
Team Health
- Both teams maintained consistent velocity and predictability across the program — no burnout indicators, no unplanned attrition
- Sprint 2's cross-team dependency friction was identified and resolved by the team itself (Sprint 2 Retrospective) — a good sign of team maturity, not an escalation the Sponsor needed to intervene on
Slide 7 of 7
Decision Requested / Next Steps
No Sponsor decision required this cycle. Program remains within approved scope, schedule, and budget tolerance. Next Steering Committee update will include the Release 2 Go/No-Go outcome following Sprint 8 Review.