RACI Matrix — Responsibility Assignment

Download Word

This matrix defines who is Responsible (does the work), Accountable (owns the outcome and signs off), Consulted (provides input before the decision), and Informed (notified after the decision) for 18 key program activities across 10 governance roles. It operationalizes the decision rights defined in the Governance Model §4 and the authority hierarchy in the Program Charter §11. Red-bordered cells indicate blocking authority — the activity cannot proceed without that role's approval.

R Responsible — does the work A Accountable — owns outcome, signs off C Consulted — input before decision I Informed — notified after decision A★ Blocking — cannot proceed without approval
Activity Exec Sponsor
(M. Kavanagh)
Program Dir
(C. Tyrrell)
PMO Lead
(T. Valdez)
AI Gov Dir
(S. Khurana)
Validation Lead
(P. Okafor)
Chief Architect
(D. Chen)
CISO
(M. Hassan)
VP Compliance
(J. Martinez)
Gen Counsel
(R. Thorne)
BRD Lead
(per BRD)
Program Authorization & Governance
Charter approval & baselineA★RCCICICCI
Phase-gate sign-offA★RRA★CA★CCIC
Governance Model maintenanceARCRICIICI
Scope & Requirements
JAD session facilitationIRRRICCCCR
Requirements sign-offIIRA★IA★AAAA
Scope change approvalA★RCCICIIIC
AI Model Governance
Model design concept approvalIIIA★CCCIIR
Independent model validationIIICA★ICIII
Model production releaseICIA★A★CCIIR
Fairness / bias testingIIIARIICCC
Shadow AI dispositionCCIA★ICIIII
Technical & Security
Architecture design approvalICICIA★CIIR
Security architecture sign-offIIICICA★IIC
Emergency production halt (AI incident)IIIRCIRIII
Financial & Resource
Budget change >$500KA★RCIIIIIIC
Contingency drawdown >$1MA★RCIIIIIII
Vendor contract >$500KA★RCIICIICI
Regulatory & Compliance
Regulatory compliance interpretationIIICIIIARI

Reading This Matrix

Blocking Authority (A★)

Red-bordered cells marked A★ indicate blocking authority — the activity literally cannot proceed without that role's approval. This is the matrix's most important feature. Three examples:

The "R but not A" Distinction

The Program Director (C. Tyrrell) is R (Responsible — does the work) on many activities but A (Accountable — owns the outcome) on very few. This reflects the matrix management reality: the Program Director coordinates, prepares, and presents — but the governance boards own the decisions. The Program Director prepares the phase-gate package; the three boards decide whether the gate passes. The Program Director prepares the change request; the Executive Steering Board decides whether to approve it.

Emergency Production Halt

Row 14 (Emergency production halt) shows both the AI Governance Director and the CISO as R — either can independently trigger a production halt for an AI model incident. This is deliberate: an AI hallucination incident (S. Khurana's domain) and a security breach (M. Hassan's domain) both require immediate response, and neither should have to wait for the other's availability.