Project Catalyst is on baseline. Four weeks into Phase 0 (Foundation) of a 36.5-month, $99.0M program, the program is tracking to its approved schedule and cost baselines with no variances. Foundation work is advancing on four parallel fronts — AI Readiness Assessment, CoE charter & governance framework, platform vendor selection, and BRD-01 requirements preparation.
The ten anticipated program risks are logged and monitored; none has materialized. No escalations require Board action this period. The near-term critical path is the AI Readiness Report (25 Sep) and the Phase 0 gate (6 Nov).
| KPI | Target | Current | Status |
|---|---|---|---|
| Schedule Performance Index (SPI) | ≥ 0.95 | 1.00 | On baseline |
| Cost Performance Index (CPI) | ≥ 0.95 | 1.00 | On baseline |
| Milestones met on time | 100% | 1 of 1 (Kickoff) | On track |
| Realized risks / issues | 0 open high | 0 | Clear |
| Governance boards operational | 3 by Phase 0 gate | Chartering (2 of 3 drafted) | In progress |
| Model validation criteria defined | By Phase 1 gate | Not yet due | On plan |
| Independent Model Validation queue | 5–10 business days | Not yet active (ramps Ph2) | On plan |
| Function | Lead | Phase-0 Load |
|---|---|---|
| Program Leadership & PMO | C. Tyrrell / T. Valdez | Heavy |
| Enterprise Architecture | D. Chen | Heavy |
| AI Governance & CoE | S. Khurana | Ramping |
| BRD delivery teams (01/02/03) | Workstream leads | Light — ramp by phase |
| QA / Testing & Independent Model Validation | QA Lead / P. Okafor | Ramps Phase 2 |
| Role | Body | Responsibility |
|---|---|---|
| Executive Sponsor (Chair) | Executive Steering Board | Business ownership, budget authority, escalation |
| Program Director — C. Tyrrell | ESB (reports in) | Delivery accountability, program reporting |
| PMO Lead — T. Valdez | ESB | Controls, schedule, EVM, reporting cadence |
| AI Governance Director — S. Khurana | AI Governance Board | Model risk, responsible-AI, model approvals |
| Chief Enterprise Architect — D. Chen | EARB | Architecture, security, integration |
| Program Finance — A. Rodriguez | ESB | Budget, EVM, contingency recommendations |
| Independent Model Validation — P. Okafor | Second line | Independent model validation sign-off |
| Legal / Compliance / SOX | Standing reviewers | Regulatory, contractual, financial-controls review |