CDRL — Contract Data Requirements List

Download Excel

The CDRL is the numbered, contractual list of every deliverable this Task Order requires, each tied to a specific due date, format, and government acceptance authority. Unlike a commercial deliverables list, missing or late CDRL items are a contract compliance issue, not just a schedule slip.

CDRL #DeliverableFormatDueAcceptance AuthorityStatus
A001Project Management PlanPDFTask Order + 30 daysCORAccepted
A002Integrated Master Schedule (IMS)MS Project / PDFTask Order + 30 daysCORAccepted
A003Risk Management Plan (RAIDD Log baseline)PDFTask Order + 30 daysCORAccepted
A004Section 508 Test PlanPDFTask Order + 60 daysCORPending
A005System Security Plan (SSP)PDFTask Order + 90 daysISSO / CORPending
A006Section 508 / VPAT Compliance Test ReportPDF + VPATTask Order + 180 daysCORPending
A007Authority to Operate (ATO) PackagePDF PackageTask Order + 210 daysAgency Authorizing OfficialPending
A008Monthly Status ReportPDF, monthly5th of each monthCORRecurring — current
A009Data Migration Plan & Validation ReportPDFTask Order + 150 daysCORPending
A010Task Order Closeout ReportPDFEnd of Period of PerformanceCOR / COPending