IMS — Integrated Master Schedule

Download Excel

A federal IMS is a work-breakdown-structured schedule with formal milestone gates tied directly to CDRL due dates and the ATO go-live gate — it's your familiar Gantt discipline, with the milestones now carrying contractual weight rather than just internal tracking.

WBS #Milestone / TaskStartFinishTied ToStatus
1.0Task Order Kickoff & MobilizationMo. 1Mo. 1PWSComplete
1.1Project Management Plan (CDRL A001)Mo. 1Mo. 1CDRL A001Complete
1.2IMS Baseline (CDRL A002)Mo. 1Mo. 1CDRL A002Complete
2.0Requirements & Solution ArchitectureMo. 2Mo. 3PWSIn Progress
2.1Section 508 Test Plan (CDRL A004)Mo. 2Mo. 2CDRL A004In Progress
3.0Development & Data Migration BuildMo. 3Mo. 6PWSNot Started
3.1System Security Plan / SSP (CDRL A005)Mo. 3Mo. 3CDRL A005Not Started
4.0Section 508 / VPAT Testing (CDRL A006)Mo. 6Mo. 6CDRL A006Not Started
5.0ATO Security Assessment & Package (CDRL A007)Mo. 6Mo. 7CDRL A007Not Started
G1Milestone Gate: Authority to Operate GrantedMo. 7ATO PackageGate
6.0Data Migration Cutover (CDRL A009)Mo. 7Mo. 7.5CDRL A009Not Started
G2Milestone Gate: Production Go-LiveMo. 8ATO + Data MigrationGate
7.0Stabilization Support (Option Period)Mo. 8Mo. 14PWS OptionNot Started
8.0Task Order Closeout (CDRL A010)Mo. 14Mo. 14CDRL A010Not Started