IMS — Integrated Master Schedule

Download Excel

A federal IMS is a work-breakdown-structured schedule with formal milestone gates tied directly to CDRL due dates and the ATO go-live gate — it's your familiar Gantt discipline, with the milestones now carrying contractual weight rather than just internal tracking.

WBS #Milestone / TaskStartFinishPredecessor(s)Status
1.0Task Order Kickoff & MobilizationMay 18, 2026May 28, 2026Complete
1.1Project Management Plan (CDRL A001)May 18, 2026Jun 15, 20261.0Complete
1.2IMS Baseline (CDRL A002)May 18, 2026Jun 16, 20261.0Complete
1.3RAIDD Log Baseline (CDRL A003)May 18, 2026Jun 17, 20261.0Complete
1.4Team Onboarding (13 Base Period roles)May 18, 2026Jun 7, 20261.0Complete
2.0Requirements & Solution ArchitectureJun 17, 2026Jul 17, 20261.1, 1.2In Progress
2.1Solution Architecture BaselineJun 17, 2026Jul 2, 20262.0Complete
2.2Section 508 Test Plan (CDRL A004)Jul 2, 2026Aug 1, 20262.0In Progress
2.3GFE / VPN Connectivity EstablishedJun 17, 2026Jun 27, 20262.0Complete
2.4Legacy Data Profiling (R-02 mitigation)Jul 2, 2026Aug 1, 20262.0In Progress
3.0Development & Data Migration BuildJul 17, 2026Nov 14, 20262.1Not Started
3.1System Security Plan / SSP (CDRL A005)Aug 1, 2026Aug 31, 20262.1Not Started
3.2Front-End Build (Portal UI)Jul 17, 2026Oct 15, 20262.1Not Started
3.3Back-End Build (API / Eligibility Integration)Jul 17, 2026Oct 15, 20262.1Not Started
3.4Data Migration Pipeline BuildAug 1, 2026Oct 15, 20262.4Not Started
3.5Data Migration Dry Run #1Aug 16, 2026Aug 16, 20263.4Not Started
3.6Data Migration Dry Run #2Oct 15, 2026Oct 15, 20263.4, 3.5Not Started
4.0Section 508 / VPAT Testing (CDRL A006)Nov 14, 2026Nov 29, 20262.2, 3.2Not Started
4.1Automated WCAG Scan PassNov 14, 2026Nov 17, 20264.0Not Started
4.2Manual Assistive-Technology TestingNov 17, 2026Nov 27, 20264.1Not Started
4.3VPAT Report Finalization & COR SubmissionNov 27, 2026Nov 29, 20264.2Not Started
5.0ATO Security Assessment & Package (CDRL A007)Nov 29, 2026Dec 29, 20263.1, 4.3Not Started
5.1Independent Security Control AssessmentNov 29, 2026Dec 14, 20263.1Not Started
5.2POA&M RemediationDec 14, 2026Dec 24, 20265.1Not Started
5.3ATO Package Submission to Agency AODec 24, 2026Dec 29, 20265.2Not Started
G1Milestone Gate: Authority to Operate GrantedDec 29, 20265.3Gate
6.0Data Migration Cutover (CDRL A009)Dec 29, 2026Jan 13, 20273.6, G1Not Started
6.1Final Production Data MigrationDec 29, 2026Jan 8, 2027G1Not Started
6.2Data Migration Validation Report (CDRL A009)Jan 8, 2027Jan 13, 20276.1Not Started
G2Milestone Gate: Production Go-LiveJan 13, 20276.2Gate
7.0Stabilization Support (Option Period)Jan 13, 2027Jul 12, 2027G2Not Started
7.1Hypercare Support (first 30 days post go-live)Jan 13, 2027Feb 12, 2027G2Not Started
7.2Continuous ATO MonitoringJan 13, 2027Jul 12, 2027G1Not Started
7.3Defect-Fix SustainmentFeb 12, 2027Jul 12, 20277.1Not Started
8.0Task Order Closeout (CDRL A010)Jun 27, 2027Jul 12, 20277.0Not Started
8.1CDRL Closeout CertificationJun 27, 2027Jul 7, 20278.0Not Started
8.2Lessons Learned FinalizationJun 27, 2027Jul 7, 20278.0Not Started
8.3Task Order Closeout Report (CDRL A010)Jul 7, 2027Jul 12, 20278.1, 8.2Not Started

This is the milestone-level schedule of record. For task-level decomposition — every task assigned to a named individual across all 13 delivery-team members — see the Work Breakdown Structure.