← Federal Suite 01 · Program Setup & Authorization

Work Breakdown Structure

Download Excel Download MS Project

Full Gantt-parity schedule — every task carries a real start/finish date, duration, predecessor dependency, percent complete, and named resource assignment, matching the structure of the PM suite's own Work Breakdown Structure. Import the MS Project file into Microsoft Project (or a compatible tool) for the native Gantt chart view, or use the table below / Excel export for a flat reference.

WBS #TaskStartFinishDuration (d)Predecessors% CompleteAssigned To
11.0 Task Order Kickoff & Mobilization2026-02-022026-02-170100%
1.1Contract kickoff meeting2026-02-022026-02-021100%C. Tyrrell, D. Ferris
1.2Staffing onboarding (all 13 roles)2026-02-032026-02-0951.1100%D. Ferris
1.3Project Management Plan (CDRL A001)2026-02-102026-02-1651.2100%C. Tyrrell
1.4IMS Baseline (CDRL A002)2026-02-102026-02-1231.2100%D. Ferris
1.5Milestone: Kickoff & Baseline Complete ◆2026-02-172026-02-1701.3, 1.4100%C. Tyrrell
22.0 Requirements & Solution Architecture2026-02-182026-04-150100%
2.1Requirements gathering workshops2026-02-182026-03-09141.5100%J. Okonkwo
2.2Solution architecture design2026-03-102026-04-02182.1100%K. Lindqvist
2.3ATO-compliant cloud environment provisioning2026-04-032026-04-1372.2100%S. Vance
2.4Section 508 Test Plan (CDRL A004)2026-04-032026-04-0952.2100%P. Duvall
2.5UI/UX wireframes and design system2026-04-032026-04-1482.2100%E. Marston
2.6Milestone: Architecture & Environment Ready ◆2026-04-152026-04-1502.3, 2.4, 2.5100%K. Lindqvist
33.0 Development & Data Migration Build2026-04-032026-07-31052%
3.1Front-end component library build2026-04-162026-05-06152.660%E. Marston
3.2Front-end citizen portal UI build2026-05-072026-06-17303.160%R. Colville
3.3Back-end API development2026-04-162026-06-03352.660%H. Ibrahim
3.4Back-end data migration pipeline2026-06-042026-07-08253.360%G. Petrov
3.5CI/CD pipeline setup2026-04-142026-04-2162.3100%S. Vance
3.6System Security Plan / SSP (CDRL A005)2026-04-032026-04-30202.260%T. Abernathy
3.7Developer unit testing (front-end + back-end)2026-07-092026-07-2083.2, 3.460%E. Marston, H. Ibrahim
3.8Functional test case development2026-04-102026-04-1762.460%N. Castellano
3.9Functional test execution2026-07-212026-07-3083.7, 3.80%A. Byrne
3.10Milestone: Build Complete ◆2026-07-312026-07-3103.9, 3.60%C. Tyrrell
44.0 Section 508 / VPAT Testing (CDRL A006)2026-08-032026-08-1800%
4.1Automated accessibility regression testing2026-08-032026-08-0643.100%A. Byrne
4.2Manual VPAT testing2026-08-032026-08-1063.100%P. Duvall
4.3Independent 508 audit remediation (Mod P00001)2026-08-112026-08-1754.1, 4.20%E. Marston
4.4Milestone: Section 508 Conformance Accepted ◆2026-08-182026-08-1804.30%P. Duvall
55.0 ATO Security Assessment & Package (CDRL A007)2026-05-012026-08-1900%
5.1Security Assessment Report2026-05-012026-05-21153.60%T. Abernathy
5.2POA&M development2026-05-222026-06-0285.10%T. Abernathy
5.3ATO package submission2026-06-032026-06-0535.20%T. Abernathy
5.4Milestone Gate: ATO Granted ◆2026-08-192026-08-1905.3, 4.40%T. Abernathy
66.0 Data Migration Cutover (CDRL A009)2026-08-202026-09-1500%
6.1Data migration validation2026-08-202026-09-02105.40%G. Petrov
6.2Regression testing (full suite)2026-09-032026-09-1066.10%N. Castellano, A. Byrne
6.3Cutover execution2026-09-112026-09-1426.20%S. Vance
6.4Milestone Gate: Production Go-Live ◆2026-09-152026-09-1506.30%C. Tyrrell
77.0 Stabilization Support (Option Period)2026-09-162027-07-2200%
7.1Sustainment development support2026-09-162027-07-132156.40%E. Marston, H. Ibrahim
7.2Continuous ATO monitoring2026-09-162027-07-222226.40%T. Abernathy
7.3Regression support testing2026-09-162027-07-132156.40%N. Castellano, A. Byrne
7.4Infrastructure sustainment2026-09-162027-07-222226.40%S. Vance
88.0 Task Order Closeout (CDRL A010)2027-07-232027-08-0200%
8.1Final CDRL reconciliation & acceptance2027-07-232027-07-2737.1, 7.2, 7.3, 7.40%D. Ferris
8.2Closeout Report & Lessons Learned2027-07-282027-07-3038.10%C. Tyrrell
8.3Milestone: Task Order Closed ◆2027-08-022027-08-0208.20%C. Tyrrell

◆ = milestone (zero-duration gate). Durations are business days (8hr/day, Mon-Fri calendar). Predecessor links are finish-to-start.