← Stage-Gate NPD Suite Traced to Gate Decisions, Both Ends

Requirements Traceability Matrix

Download Word
Program timeline · status 16 Oct 2026Read the full story →
Harborline
Aug 2025
Cancelled
Gate 0
Feb 2026
Go
Stage 1
Business case
Gate 1
Apr 2026
Recycled
Gate 1
Jun 2026
Go w/ conditions
Stage 2
Development
You are here
Gate 2
Apr 2027
Gate 3
Oct 2027
Gate 4
Feb 2028
Launch
Mar 2028
Gate 5
Sep 2028

Lighthouse Financial Services Company — Every product, regulatory and operational requirement for Beacon Index Advantage, traced to the gate that authorized it and the gate that will verify it. Status as at 16 October 2026.

18
Requirements traced
14
Active
2
Withdrawn, still traceable
1
Excluded by decision
Contents
  1. Why This Matrix Traces to Gates, Not Just to Tests
  2. Active Requirements
  3. Withdrawn and Excluded — Kept Traceable on Purpose
  4. Forward Trace
  5. Verification Coverage by Gate
  6. Traceability Gaps
  7. Document Control

1. Why This Matrix Traces to Gates, Not Just to Tests

A conventional traceability matrix runs one direction: requirement → design → build → test case → result. That is necessary here too, and §4 carries it. But it is not sufficient in a stage-gate program, because a requirement in this program has two decision endpoints, not one.

The practical consequence: a requirement can be traced to the exact decision that created it and the exact decision that will close it. That is a stronger claim than "it has a test case," and it is the claim a gate actually needs — because at a gate the question is not "was this tested?" but "is the Board entitled to rely on this being done?"

2. Active Requirements

IDRequirementSourceAuth.VerifiedStatus
PR-01Single-premium deferred fixed indexed annuity chassisGate 0 concept · D-01G0G3Active
PR-02Seven-year declining surrender-charge scheduleGate 0 conceptG0G3Active
PR-03Optional GLWB rider (not embedded)D-05G0G3Active
PR-04Fixed account crediting strategyD-03 launch setG1G2Active
PR-05One-year point-to-point on the Calder Balanced 5, cappedD-03 launch set · DEP-04G1G2Active
PR-06One-year performance-triggered crediting strategyD-03 launch setG1G2Active
PR-09Compact-route filing across member statesD-06 · A-02G1G3Active
PR-10Separate SERFF filings for California and FloridaD-06 · DEP-02G1G3Active
PR-12Compliant hypothetical performance illustrationsNAIC #275 · R-08G1G2Active
PR-13Suitability and best-interest advisor trainingNAIC Model Reg #275G1G4Active
PR-15Extension of the incumbent admin platform (no new system)D-07 · A-04G1G2Active
PR-16GLWB risk transfer via reinsuranceDEP-05G1G3Active
PR-17New business issue and policyholder servicing capabilityGate 1 scopeG1G4Active
PR-18Distribution through existing IMO/BD relationships onlyA-05G1G4Active
PR-14In-house hedging of the GLWB guaranteeD-08 · A-06G1G4At risk
PR-14 is the only active requirement carrying an at-risk trace. In-house hedging of the GLWB guarantee runs through GC-05 to ISDA execution under DEP-06, where one of two counterparties has not begun negotiation. The requirement is authorized, the design exists, and the verification chain is incomplete at a point outside the program's control. Every other document in this suite flags the same item from a different angle — which is the register agreement you want, not duplication.

3. Withdrawn and Excluded — Kept Traceable on Purpose

Two crediting strategies were cut at Gate 1 under GC-01, recorded as decision D-03. They remain in this matrix as withdrawn rows rather than being deleted from it.

IDRequirementSourceAuth.VerifiedStatus
PR-07Participation-rate crediting strategyGate 0 concept (5-strategy set)G0Withdrawn
PR-08Monthly-averaged crediting strategyGate 0 concept (5-strategy set)G0Withdrawn
PR-11New York excluded from launch scopeA-03 · D-02 · GC-02G1Excluded by decision
An RTM that deletes cut requirements cannot answer the most common question asked of a launched product: “why doesn't it do X?” With PR-07 and PR-08 retained, the answer is a citation rather than an argument: withdrawn at Gate 1 on 11 June 2026 under GC-01, recorded as D-03, because the incumbent platform and illustration engine could not support them (R-04, I-02) and their forecast contribution did not justify building the capability. The build allocation returned to reserve.

The distinction between withdrawn and excluded is deliberate and is not cosmetic. PR-07 and PR-08 were in scope and were removed. PR-11 — New York — was never in launch scope; it is an exclusion with a deferral memorandum recording the conditions under which it would be revisited. Collapsing the two would make a considered scope decision look like a cut, and a cut look like a considered scope decision.

4. Forward Trace

The conventional chain, requirement through to the evidence that closes it.

IDTrace
PR-01Product spec → contract form filing → Compact submission → issue testing
PR-02Product spec → contract form → illustration engine → admin platform config
PR-03Rider spec → pricing basis → GC-03 external review → contract form → hedging
PR-04Product spec → admin platform config → illustration validation
PR-05Index license → pricing → illustration validation → hedging instrument selection
PR-06Product spec → admin platform config → illustration validation
PR-07Withdrawn at Gate 1 under GC-01 (D-03). Platform could not support it without custom development (R-04); build allocation returned to reserve. Not deferred — out of scope.
PR-08Withdrawn at Gate 1 under GC-01 (D-03). Illustration engine could not produce compliant hypothetical performance (I-02). Not deferred — out of scope.
PR-09Filing plan → IIPRC submission (DEP-01) → approval → state activation
PR-10Filing plan → SERFF submissions → department review → state activation
PR-11Scope exclusion, closed under GC-02. Deferral memorandum filed; filing plan, distribution footprint and Stage 4 training scope all derive from it.
PR-12Illustration spec → Brightpath build → validation vs filed methodology
PR-13Training spec → enablement build → delivery → completion records at Gate 4
PR-14Hedging design → GC-05 readiness plan → ISDA execution (DEP-06) → live shadow book
PR-15Cordelane SOW → configuration (DEP-03) → issue and servicing testing
PR-16Halverson Re term sheet → treaty → capital treatment confirmation
PR-17Ops design → process build → end-to-end test with trained staff at Gate 4
PR-18Channel plan → GC-04 written commitments → appointment and licensing pipeline

5. Verification Coverage by Gate

Verifying gateRequirementsIDs
G25PR-04, PR-05, PR-06, PR-12, PR-15
G36PR-01, PR-02, PR-03, PR-09, PR-10, PR-16
G44PR-13, PR-14, PR-17, PR-18
— (no verifying gate)3PR-07, PR-08, PR-11

Verification load concentrates at Gate 3 — regulatory approval, reserve adequacy and final rates all land together — and at Gate 4, where operational and distribution readiness is demonstrated rather than planned. Gate 2's share is smaller than it looks: three of its requirements were made materially easier by the GC-01 scope reduction, since the two strategies the illustration engine could not support are no longer in the set it must validate.

6. Traceability Gaps

IDGap
TG-01No requirement traces to a benefit. The matrix traces requirements to gates and to test evidence, but nothing links PR-05 (the capped indexed strategy) to BEN-05 (crediting mix), or PR-18 (channel) to BEN-01 (volume). A product can therefore satisfy every requirement and still miss its business case, and this matrix would show full coverage throughout. The Benefits Realization Plan carries the benefit side; the two documents are not joined.
TG-02Two requirements are verified by parties outside the program. PR-09 and PR-10 close only when regulators approve (DEP-01, DEP-02). The program can evidence submission quality and nothing further; the requirement's closure is not within its gift.
TG-03PR-13 verification is a completion record, not an effectiveness measure. Advisor training under NAIC #275 is verified at Gate 4 by delivery and completion records. Whether the training changed advisor behavior is a market-conduct question no gate in this program asks.
TG-04No requirement covers the post-launch window. Every row verifies at or before Gate 4. Gate 5 reviews outcomes, not requirements — so nothing in this matrix has a verification point after 06 Mar 2028.

7. Document Control

VersionDateChange
1.005 Feb 2026Opened at Gate 0 with the concept requirement set, including the five proposed crediting strategies.
1.111 Jun 2026Gate 1 authorizations recorded. PR-07 and PR-08 moved to withdrawn under GC-01 / D-03; PR-11 recorded as excluded under GC-02 / D-02. No row deleted.
1.216 Oct 2026PR-14 trace marked at risk following the September program review (GC-05 / DEP-06). Traceability gaps TG-01..TG-04 formalized.

Maintained by C. Tyrrell, NPD Program Manager and Chair of the Gate Review Board. Related: Gate Decision Framework · Gate Conditions Register · RAIDD Log · Benefits Realization Plan (see TG-01).