← M&A Integration Suite Plan · Artifact 11 · how to read this suite

Master Schedule

Download MS Project

The dated plan, as at February 26, 2024 — five months after Day 1 and seven months before the planned TSA exit. This is the schedule the work breakdown structure is sequenced into: milestones with owners, the critical path and what actually sits on it, where float exists and where it does not, and the dependencies paced by calendars nobody on the program controls.

The critical path on this program does not run through a technical task. It runs through a queue of records being read by people. Core administration cutover cannot happen until the target's members exist correctly in ACME's systems; that requires identity resolution; identity resolution is gated by a clerical review band worked at a fixed human throughput. Every technical dependency downstream of it can be perfectly executed and the date will still be set by how many records need a human decision — a number produced by data quality nobody was permitted to measure before closing.

Table of Contents

Part I — The Plan
  1. Schedule Structure and Horizon
  2. Milestones
  3. Phase View
Part II — What Drives the Date
  1. The Critical Path
  2. Float, and the Difference Between Slack and Margin
  3. Externally Paced Dependencies
Part III — Control
  1. Schedule Risk
  2. Change and Re-baseline
Part I — The Plan

1. Schedule Structure and Horizon

Detail is planned to the horizon where information exists. Beyond it, work has a position in the sequence but not a defensible date, and is reported as on sequence rather than on schedule.

Horizon from this datePlanned toReported as
To end May 2024Task level, named ownersOn schedule / behind, with variance and recovery
June – September 2024Work package levelOn schedule, subject to the identity resolution outcome
Beyond TSA exitMilestone level⚠ On sequence — position known, date derived

2. Milestones

RefMilestoneDateStatusOwner and note
M-01Merger agreement signedFeb 13, 2023MetT. Broadnax
M-02Antitrust clearanceMay 30, 2023MetL. Hollingsworth. ⚠ Clearance to close, not permission to combine.
M-03State Form A approvalSep 12, 2023MetR. Cadwallader. One condition attached — data location.
M-04ClosingSep 29, 2023MetD. Ashmore
M-05Day 1Oct 2, 2023MetR. Villanueva. Payroll, claims, eligibility, filings. Not integration.
M-06TSA payroll & HR exitJan 2, 2024MetG. Threadgill. First service off the meter.
M-07Day 100Jan 9, 2024MetC. Tyrrell. Stabilization complete; discovery closed.
M-08Program re-baseline approvedJan 22, 2024MetSteering Committee. Class 5 estimate replaced by Class 2.
M-09Landing zone acceptedJan 15, 2024MetB. Trammell. Ten evidenced conditions.
M-10Data profiling completeApr 2024Critical⚠ Dr. A. Ravindran. Sizes the review queue. Everything below depends on it.
M-11TSA general ledger exitApr 2, 2024OpenS. Beauregard. At a fiscal period boundary.
M-12EMPI match rules acceptedMay 2024CriticalDr. A. Ravindran
M-13TSA network & compute exitJun 2, 2024OpenB. Trammell
M-14Clerical review queue clearedJul 2024Critical⚠ T. Vandiver. The pacing item. Duration is a function of queue size.
M-15TSA security operations exitJul 2, 2024OpenA. Quintanilla
M-16Parallel run reconciledAug 2024CriticalB. Nkemdirim. Zero variance on outcome and amounts.
M-17Core administration cutoverSep 2024CriticalW. Ferriday. ⚠ No rollback after this point.
M-18TSA exit completeSep 30, 2024CriticalG. Threadgill. Plan date. Contractual maximum is Mar 31, 2025.
M-19Data center vacatedSep 30, 2024OpenH. Sandifer. Zero workloads; destruction certificate.
M-20Program closeoutApr 30, 2025OpenC. Tyrrell. Residual scope to line ownership.

3. Phase View

2023 Q1 2023 Q3 2024 Q1 2024 Q3 2025 Q1 2025 Q3 GOV Pre-close planning GOV Day 1 & stabilization DATA Identity resolution critical path CORE Core admin migration critical path CLOUD Cloud migration waves INTG Integration layer TSA TSA service exits MARG Negotiated TSA margin not a plan TSA plan Sep 30, 2024 contractual max Mar 31, 2025
GOV governanceDATA identityCORE core admin CLOUD infrastructureINTG interfacesTSA service exit MARG margin
Track is carried by a monospace code beside every bar, not by color alone. Six categories cannot be reliably distinguished by hue inside a muted palette — and on a schedule chart red is already spoken for by the critical path. Critical bars therefore carry three signals at once: color, full opacity, and a heavier stroke. Redundant encoding costs a few pixels and makes the chart readable printed, projected, or by someone who does not see the palette the way it was designed.
Part II — What Drives the Date

4. The Critical Path

SeqActivityDurationWhy it cannot be compressed
CP-1Data profilingIn progressRequires the full member file loaded and standardized. ⚠ Could not begin before closing.
CP-2Match rule calibration~8 weeksThresholds are tuned against profiling output. Guessing them earlier means re-doing the queue.
CP-3Clerical review queueQueue size ÷ throughput⚠⚠ The pacing item. Onshore only, fixed human throughput, staffing scales in weeks not days.
CP-4Member load & reconciliation~6 weeksCannot start until identities are resolved
CP-5Parallel run~10 weeksSet by claim cycle, not by effort — must span a full month-end and payment cycle
CP-6Core administration cutover1 weekendShort, and irreversible
CP-7TSA exit certification~2 weeksEvidence-based; the service ends when the criteria are demonstrated
Only one activity on this chain has a duration the program can influence, and it is not the one people reach for. Adding engineers does not shorten CP-3, because the constraint is human review of member records at a quality standard that cannot be relaxed. Adding stewards does — but recruitment, onboarding and training run several weeks, so the response is measured in months. CP-5 is set by the claims calendar. CP-6 is a weekend. A schedule recovery conversation that starts with "can we add people to the migration team" has misread which task is critical.

5. Float, and the Difference Between Slack and Margin

PathFloatCharacter
Cloud migration waves 1–46 weeksGenuine slack. Waves finish ahead of the workloads that depend on them.
Integration layer build4 weeksGenuine slack, protected because interface defects surface late
TSA exits (early services)3–5 weeksSlack per service; they exit independently
Provider network rationalization⚠ Not on the critical path but not compressible either — renewal-dated
Identity resolution → cutoverZeroThe critical path. Any slip moves the TSA exit date.
TSA plan date → contractual maximum26 weeks⚠⚠ Negotiated margin, not float. See below.
The six months between the planned TSA exit and the contractual maximum is not schedule slack, and treating it as float would be the most expensive mistake available on this program. Float is what a network calculation produces — a by-product of dependencies. This margin was bought, deliberately, at signing, by negotiating an eighteen-month term for a twelve-month plan, precisely because the identity resolution work could not be sized before closing. It is a governance asset with an owner: spending any of it is a Steering Committee decision, not a scheduling adjustment a program manager makes on a Tuesday. A plan that absorbs it silently has converted protection into schedule and left nothing for the problem it was bought against.

6. Externally Paced Dependencies

DependencyPaced byConsequence of assuming otherwise
EDI trading partner re-registrationEach partner's own queueClearinghouse exit slips; providers lose electronic submission if forced
Provider contract renewalsContract anniversary datesNetwork synergy re-profiles to later cycles — a timing loss, not a value loss
Quality measurement yearAccrediting body calendar⚠ Switching mid-year invalidates the rates for that year
Broker and employer portalOpen enrollment seasonMigrating during selling season is self-inflicted revenue risk
Open appeals casesCase duration and regulationA case must complete in the system that opened it
Employee continuation periodMerger agreementCorporate consolidation cannot start early regardless of readiness
Physical transfer appliancesShipping and ingest cycleArchive transfer has float only because it started first
Seven dependencies on this schedule are governed by calendars nobody on the program controls, and none of them respond to escalation. This is characteristic of health plan integration and it catches programs that build schedules from effort estimates alone. You cannot compress an externally governed cycle by adding people to it — and a plan that assumes you can produces dates that were never achievable, discovered late, usually by a workstream lead who has been reporting green against them.
Part III — Control

7. Schedule Risk

RefRiskEffect on the date
SS-01Review queue larger than modeled⚠⚠ Moves M-14, M-16, M-17 and M-18 together. The only risk on this schedule that moves the TSA exit directly.
SS-02Parallel run surfaces variances requiring configuration reworkExtends CP-5. Absorbable within the margin, not within the plan.
SS-03Trading partner re-registration slower than plannedDelays clearinghouse exit; does not move core admin cutover
SS-04Retention loss in core administration knowledgeExtends configuration and parallel run; no direct substitute available
SS-05Restore test fails at a wave gateHolds the wave. Deliberate — the gate exists to stop exactly this.
SS-06Cutover weekend overruns⚠ No rollback. Hypercare extends; the date does not move because it cannot.
Five of these six can be absorbed without moving the program's hard date. SS-01 cannot, and that is why profiling is reported to the Steering Committee separately from the migration status. A schedule where every risk threatens the end date is a schedule nobody can prioritize; the value of naming the one that genuinely does is that attention goes there rather than being spread evenly across six.

8. Change and Re-baseline

EventTreatment
Activity slips within floatReported as variance with cause and recovery. No change request.
Activity slips onto the critical pathEscalated immediately, not at the next cadence
Milestone date movesChange request stating which constraint it protects and which it spends
Any consumption of negotiated margin⚠ Steering Committee decision, explicitly recorded. Never absorbed into the plan.
Re-baselineOccurred once, at M-08, when the estimate matured from Class 5 to Class 2. ⚠ A re-baseline is an event, not a change request — it replaces the plan rather than amending it.
The distinction in the last row is worth holding onto, because it is where change control is most often misapplied. The pre-close estimate was made without access to member-level data, at an accuracy the estimating standard describes as concept screening. Replacing it with a real estimate is not a change to the program — it is the first time the program had one. Change control governs movement away from a baseline; it cannot sensibly govern the arrival of the first credible baseline. Everything after M-08 is change-controlled against that plan, and the change log reconciles to it exactly.

Related artifacts: 1 — Integration Charter · 9 — Integration Management Plan · 10 — Work Breakdown Structure · 14 — Resource Plan · 22 — TSA Schedule & Exit Plan · 23 — Data Migration & EMPI Strategy · 35 — Cloud Migration Wave Plan · 28 — Risk Register · 44 — Change Control Log