The dated plan, as at February 26, 2024 — five months after Day 1 and seven months before the planned TSA exit. This is the schedule the work breakdown structure is sequenced into: milestones with owners, the critical path and what actually sits on it, where float exists and where it does not, and the dependencies paced by calendars nobody on the program controls.
The critical path on this program does not run through a technical task. It runs through a queue of records being read by people. Core administration cutover cannot happen until the target's members exist correctly in ACME's systems; that requires identity resolution; identity resolution is gated by a clerical review band worked at a fixed human throughput. Every technical dependency downstream of it can be perfectly executed and the date will still be set by how many records need a human decision — a number produced by data quality nobody was permitted to measure before closing.
Detail is planned to the horizon where information exists. Beyond it, work has a position in the sequence but not a defensible date, and is reported as on sequence rather than on schedule.
Horizon from this date
Planned to
Reported as
To end May 2024
Task level, named owners
On schedule / behind, with variance and recovery
June – September 2024
Work package level
On schedule, subject to the identity resolution outcome
Beyond TSA exit
Milestone level
⚠ On sequence — position known, date derived
2. Milestones
Ref
Milestone
Date
Status
Owner and note
M-01
Merger agreement signed
Feb 13, 2023
Met
T. Broadnax
M-02
Antitrust clearance
May 30, 2023
Met
L. Hollingsworth. ⚠ Clearance to close, not permission to combine.
M-03
State Form A approval
Sep 12, 2023
Met
R. Cadwallader. One condition attached — data location.
M-04
Closing
Sep 29, 2023
Met
D. Ashmore
M-05
Day 1
Oct 2, 2023
Met
R. Villanueva. Payroll, claims, eligibility, filings. Not integration.
M-06
TSA payroll & HR exit
Jan 2, 2024
Met
G. Threadgill. First service off the meter.
M-07
Day 100
Jan 9, 2024
Met
C. Tyrrell. Stabilization complete; discovery closed.
M-08
Program re-baseline approved
Jan 22, 2024
Met
Steering Committee. Class 5 estimate replaced by Class 2.
M-09
Landing zone accepted
Jan 15, 2024
Met
B. Trammell. Ten evidenced conditions.
M-10
Data profiling complete
Apr 2024
Critical
⚠ Dr. A. Ravindran. Sizes the review queue. Everything below depends on it.
M-11
TSA general ledger exit
Apr 2, 2024
Open
S. Beauregard. At a fiscal period boundary.
M-12
EMPI match rules accepted
May 2024
Critical
Dr. A. Ravindran
M-13
TSA network & compute exit
Jun 2, 2024
Open
B. Trammell
M-14
Clerical review queue cleared
Jul 2024
Critical
⚠ T. Vandiver. The pacing item. Duration is a function of queue size.
M-15
TSA security operations exit
Jul 2, 2024
Open
A. Quintanilla
M-16
Parallel run reconciled
Aug 2024
Critical
B. Nkemdirim. Zero variance on outcome and amounts.
M-17
Core administration cutover
Sep 2024
Critical
W. Ferriday. ⚠ No rollback after this point.
M-18
TSA exit complete
Sep 30, 2024
Critical
G. Threadgill. Plan date. Contractual maximum is Mar 31, 2025.
M-19
Data center vacated
Sep 30, 2024
Open
H. Sandifer. Zero workloads; destruction certificate.
M-20
Program closeout
Apr 30, 2025
Open
C. Tyrrell. Residual scope to line ownership.
3. Phase View
GOV governanceDATA identityCORE core adminCLOUD infrastructureINTG interfacesTSA service exitMARG margin
Track is carried by a monospace code beside every bar, not by color alone. Six categories cannot be reliably distinguished by hue inside a muted palette — and on a schedule chart red is already spoken for by the critical path. Critical bars therefore carry three signals at once: color, full opacity, and a heavier stroke. Redundant encoding costs a few pixels and makes the chart readable printed, projected, or by someone who does not see the palette the way it was designed.
Part II — What Drives the Date
4. The Critical Path
Seq
Activity
Duration
Why it cannot be compressed
CP-1
Data profiling
In progress
Requires the full member file loaded and standardized. ⚠ Could not begin before closing.
CP-2
Match rule calibration
~8 weeks
Thresholds are tuned against profiling output. Guessing them earlier means re-doing the queue.
CP-3
Clerical review queue
Queue size ÷ throughput
⚠⚠ The pacing item. Onshore only, fixed human throughput, staffing scales in weeks not days.
CP-4
Member load & reconciliation
~6 weeks
Cannot start until identities are resolved
CP-5
Parallel run
~10 weeks
Set by claim cycle, not by effort — must span a full month-end and payment cycle
CP-6
Core administration cutover
1 weekend
Short, and irreversible
CP-7
TSA exit certification
~2 weeks
Evidence-based; the service ends when the criteria are demonstrated
Only one activity on this chain has a duration the program can influence, and it is not the one people reach for. Adding engineers does not shorten CP-3, because the constraint is human review of member records at a quality standard that cannot be relaxed. Adding stewards does — but recruitment, onboarding and training run several weeks, so the response is measured in months. CP-5 is set by the claims calendar. CP-6 is a weekend. A schedule recovery conversation that starts with "can we add people to the migration team" has misread which task is critical.
5. Float, and the Difference Between Slack and Margin
Path
Float
Character
Cloud migration waves 1–4
6 weeks
Genuine slack. Waves finish ahead of the workloads that depend on them.
Integration layer build
4 weeks
Genuine slack, protected because interface defects surface late
TSA exits (early services)
3–5 weeks
Slack per service; they exit independently
Provider network rationalization
—
⚠ Not on the critical path but not compressible either — renewal-dated
Identity resolution → cutover
Zero
The critical path. Any slip moves the TSA exit date.
TSA plan date → contractual maximum
26 weeks
⚠⚠ Negotiated margin, not float. See below.
The six months between the planned TSA exit and the contractual maximum is not schedule slack, and treating it as float would be the most expensive mistake available on this program. Float is what a network calculation produces — a by-product of dependencies. This margin was bought, deliberately, at signing, by negotiating an eighteen-month term for a twelve-month plan, precisely because the identity resolution work could not be sized before closing. It is a governance asset with an owner: spending any of it is a Steering Committee decision, not a scheduling adjustment a program manager makes on a Tuesday. A plan that absorbs it silently has converted protection into schedule and left nothing for the problem it was bought against.
6. Externally Paced Dependencies
Dependency
Paced by
Consequence of assuming otherwise
EDI trading partner re-registration
Each partner's own queue
Clearinghouse exit slips; providers lose electronic submission if forced
Provider contract renewals
Contract anniversary dates
Network synergy re-profiles to later cycles — a timing loss, not a value loss
Quality measurement year
Accrediting body calendar
⚠ Switching mid-year invalidates the rates for that year
Broker and employer portal
Open enrollment season
Migrating during selling season is self-inflicted revenue risk
Open appeals cases
Case duration and regulation
A case must complete in the system that opened it
Employee continuation period
Merger agreement
Corporate consolidation cannot start early regardless of readiness
Physical transfer appliances
Shipping and ingest cycle
Archive transfer has float only because it started first
Seven dependencies on this schedule are governed by calendars nobody on the program controls, and none of them respond to escalation. This is characteristic of health plan integration and it catches programs that build schedules from effort estimates alone. You cannot compress an externally governed cycle by adding people to it — and a plan that assumes you can produces dates that were never achievable, discovered late, usually by a workstream lead who has been reporting green against them.
Part III — Control
7. Schedule Risk
Ref
Risk
Effect on the date
SS-01
Review queue larger than modeled
⚠⚠ Moves M-14, M-16, M-17 and M-18 together. The only risk on this schedule that moves the TSA exit directly.
SS-02
Parallel run surfaces variances requiring configuration rework
Extends CP-5. Absorbable within the margin, not within the plan.
SS-03
Trading partner re-registration slower than planned
Delays clearinghouse exit; does not move core admin cutover
SS-04
Retention loss in core administration knowledge
Extends configuration and parallel run; no direct substitute available
SS-05
Restore test fails at a wave gate
Holds the wave. Deliberate — the gate exists to stop exactly this.
SS-06
Cutover weekend overruns
⚠ No rollback. Hypercare extends; the date does not move because it cannot.
Five of these six can be absorbed without moving the program's hard date. SS-01 cannot, and that is why profiling is reported to the Steering Committee separately from the migration status. A schedule where every risk threatens the end date is a schedule nobody can prioritize; the value of naming the one that genuinely does is that attention goes there rather than being spread evenly across six.
8. Change and Re-baseline
Event
Treatment
Activity slips within float
Reported as variance with cause and recovery. No change request.
Activity slips onto the critical path
Escalated immediately, not at the next cadence
Milestone date moves
Change request stating which constraint it protects and which it spends
Any consumption of negotiated margin
⚠ Steering Committee decision, explicitly recorded. Never absorbed into the plan.
Re-baseline
Occurred once, at M-08, when the estimate matured from Class 5 to Class 2. ⚠ A re-baseline is an event, not a change request — it replaces the plan rather than amending it.
The distinction in the last row is worth holding onto, because it is where change control is most often misapplied. The pre-close estimate was made without access to member-level data, at an accuracy the estimating standard describes as concept screening. Replacing it with a real estimate is not a change to the program — it is the first time the program had one. Change control governs movement away from a baseline; it cannot sensibly govern the arrival of the first credible baseline. Everything after M-08 is change-controlled against that plan, and the change log reconciles to it exactly.