Co-Managed Cloud Operations

⇩ Download Word

Operation of ACME's Azure estate under a co-managed model with a contracted step-down, so that operational capability transfers to ACME on a schedule rather than by intention. ⚠ The step-down milestones are acceptance-gated: Supplier is not paid for a phase until ACME demonstrates the capability that phase transfers.

1. Parties, Instrument and Term

AttributeProvision
ClientACME Health
SupplierRutherford Cloud Operations
InstrumentSOW-02, issued under the Master Services Agreement
Vendor register referenceVN-02 in the Vendor Management Plan
VehicleFixed price for the operating baseline, time and materials for project work
ACME ownerB. Trammell, VP Infrastructure
EffectiveAugust 28, 2023 — ⚠ subject to execution under §7
TermFrom landing zone acceptance through the final step-down boundary.
Governing documentVendor Management Plan §4 and §5. ⚠ Clauses in those sections are mandatory and are reproduced here in full rather than incorporated by reference.

2. Scope of Services

RefElementProvision
SC-01Platform operationsMonitoring, patching, backup verification and incident response across the estate, to the service tiers in the Quality Plan.
SC-02Migration wave supportEngineering support to each migration wave, including rollback execution.
SC-03Landing zone maintenancePolicy guardrails, network, identity and logging maintained to the design.
SC-04Step-down capability transfer⚠ Four contracted phases. Each transfers a defined capability to ACME and is accepted only when ACME performs it unaided.
SC-05FinOps operationsTagging enforcement, showback reporting, and reservation recommendations. ⚠ Recommendations only — commitment decisions are ACME's.
SC-06On-call rotaNamed engineers, with ACME engineers progressively taking primary through the step-down.

3. Deliverables and Acceptance

⚠ Acceptance criteria are stated here, before work begins. A deliverable is accepted when the criterion is demonstrated, not when Supplier declares it complete.

RefDeliverableAcceptance criterion
DL-01Service commencementMonitoring, alerting and on-call live across the estate
DL-02Step-down phase 1 acceptedACME performs routine operations unaided for one full cycle
DL-03Step-down phase 2 acceptedACME performs patching and backup verification unaided
DL-04Step-down phase 3 accepted⚠ ACME leads incident response; Supplier advises only
DL-05Step-down phase 4 acceptedACME operates independently; Supplier moves to advisory retainer
DL-06Operations runbooksHanded over and rehearsed by the receiving ACME team

4. Service Levels

LevelResponseResolutionDefinition
Severity 115 minutesContinuous effortProduction outage, Tier 0 or 1
Severity 21 hour8 hoursDegraded service, no workaround
Severity 34 hours3 business daysDegraded, workaround exists
Severity 41 business dayNext maintenance windowRequest or cosmetic

5. Warranty, Support and Version Obligations

The obligations below are mandatory under Vendor Management Plan §5 and are not subject to negotiation on price. They govern the period after acceptance, which is where the cost of an incomplete statement of work is actually incurred.

RefTermProvision
SW-02Defect remediation service levelsResponse and resolution by severity, using ACME's severity definitions from the Quality Plan, not Supplier's. Severity 1 — a defect harming a member or breaching a regulatory obligation — carries a 1 hour response and continuous effort to resolution.
SW-03Support staffing and coverageNamed support contacts with a defined escalation path. ⚠ Coverage extends to cutover weekends and hypercare periods on the program calendar, not Supplier's standard business hours. Coverage windows are listed by date in an annex updated at each wave.
SW-04Version updates and patchesSupplier states who applies updates, in what window, and who tests. Security patches run on a clock separate from feature releases. ACME approves the timing of any update to a production environment.
SW-08Environment coverage⚠ Support covers non-production environments. A test environment nobody will fix stops testing, which stops the program.
SW-03 coverage is stated against the program's wave calendar, not Supplier's standard hours. Every migration wave cutover falls on a weekend by design, which is precisely when a platform behaves unexpectedly and least when Supplier's standard support would be available.

6. General Conditions

RefClauseProvision
GC-01Governing agreementThis statement of work is issued under the Master Services Agreement between ACME Health and Rutherford Cloud Operations. Where the two conflict, the Master Services Agreement governs except on scope, price and schedule, which this instrument governs.
GC-02Contracting party across the close⚠ Executed before closing by ACME Health. Cumberland Valley Health Plan becomes a beneficiary at closing without further action; no novation is required because ACME is the contracting party throughout.
GC-03Key personnelNamed individuals in §2 may not be substituted without written agreement. A substitution without agreement is a material failure, not an administrative change.
GC-04SubcontractingNo subcontracting without prior written consent. All obligations of this instrument flow down to any approved subcontractor, including data-handling and audit rights.
GC-05Data handling and location⚠ No member-level data is processed, stored or accessed outside the United States. This is a contractual obligation, not a policy preference, and derives from a condition of the state insurance approval.
GC-06Business associate agreementA business associate agreement is executed before any access to protected health information, and remains in force through the retention period after termination.
GC-07Security incident notificationSupplier notifies ACME within 24 hours of discovering a suspected security or privacy incident. ⚠ The clock runs from discovery, not from confirmation.
GC-08Audit rightsACME may audit compliance on 10 business days' notice, and without notice following a reported incident.
GC-09InsuranceProfessional liability, cyber liability and workers compensation maintained at the limits in the Master Services Agreement; certificates provided before work begins and on renewal.
GC-10Change controlScope changes are priced and approved before work begins, against the program's thresholds ($250,000 Program Manager, $1,000,000 Executive Sponsor, above that the Steering Committee). ⚠ Work performed before approval is performed at Supplier's risk.
GC-11Intellectual propertyRunbooks, automation, infrastructure-as-code and configuration produced under this instrument are the property of ACME Health. Supplier retains its own tooling and methodology.
GC-12Knowledge transferKnowledge transfer is a deliverable with named receivers and an acceptance test, not a by-product of the work. Acceptance is by reverse shadowing: ACME performs unaided while Supplier observes.
GC-13Termination for convenienceACME may terminate on 30 days' written notice. Supplier is paid for work accepted and work in progress to the termination date.
GC-14Transition assistance⚠ On termination for any reason, Supplier provides transition assistance for up to 90 days at the rates in §4, and returns all data and artifacts in a documented, usable format. "Available on request" is not a format.
GC-15Surviving obligationsConfidentiality, business associate terms, data return and record retention survive termination.
GC-16IndependenceSupplier confirms no engagement with Cumberland Valley Health Plan, Cheatham Mutual Holdings, or any party adverse to the transaction, and will disclose any such engagement arising during the term.

7. Execution

This statement of work is not effective until executed by an authorized signatory of both parties and endorsed by ACME Legal. ⚠ Work performed before execution is performed at Supplier's risk and is not payable.

For ACME Health
D. Ashmore
EVP & Chief Financial Officer · Executive Sponsor
Date: _______________
For Rutherford Cloud Operations
D. Pennington
President · authorized signatory
Date: _______________
Procurement approval
H. Castellow
VP Procurement, ACME Health
Date: _______________
Four signatures rather than two, and each one is a different check. The business owner confirms the work is wanted and funded; the supplier's officer binds their firm; Procurement confirms the commercial terms match the framework agreement; Legal confirms the clauses that only matter later — data handling, liability, termination and the §5 obligations — are actually present. ⚠ The signature most often skipped under schedule pressure is the legal one, and it is the only one that reads the parts of the document nobody expects to need.

Related: 21A — Vendor Management Plan · 8 — Consulting SOW & Engagement Model · 21 — Vendor & Contract Disposition Matrix · 26 — Quality Plan