How the program engages and runs the vendors it hires, issued August 28, 2023. This is distinct from two adjacent documents and the boundary matters: the Vendor & Contract Disposition Matrix deals with contracts the program inherited and must keep, novate or exit; the Consulting SOW is one engagement's own paper. This plan governs everything the program buys — what each statement of work must contain, how performance is measured, and how a vendor is exited.
Table of Contents
- Mandatory Statement of Work Content
- Warranty, Support and Version Obligations
- Individual Statements of Work
1. Scope and Boundaries
| Document | Covers | Boundary |
|---|---|---|
| This plan | Vendors the program engages | Onboarding, SOW content, performance, escalation, exit |
| 21 — Disposition Matrix | Contracts the program inherited | ⚠ Keep, novate, consolidate or terminate. Change-of-control mechanics. |
| 8 — Consulting SOW | The Arrington engagement itself | One instrument, plus the three-tier contracting model |
| 22 — TSA Exit Plan | Cheatham Mutual Holdings | ⚠ The divesting parent is governed by the TSA, not by a program SOW |
2. Vendor Register and Engagement Model
| Ref | Vendor | Vehicle | ACME owner | What they are engaged to deliver |
|---|---|---|---|---|
| VN-01 | Arrington Advisory Group | Deliverable SOW | D. Ashmore | Program management, identity resolution, integration and cloud architecture |
| VN-02 | Rutherford Cloud Operations | Fixed price + T&M | B. Trammell | Co-managed cloud operations against a contracted step-down. ⚠ Software and platform terms apply — see §5. |
| VN-03 | Gallatin EDI Assurance | Fixed price | W. Ferriday | X12 transaction assurance across five transaction sets |
| VN-04 | Two Rivers Talent Partners | Staff aug | T. Vandiver | Data stewards for clerical review. ⚠ ACME directs the work and owns the outcome. |
| VN-05 | Harpeth Clean Team Services | Fixed price | L. Hollingsworth | Pre-close information barrier. Terminates at closing. |
| VN-06 | Madison Data Systems — EMPI platform | License + support | Dr. A. Ravindran | ⚠ Software purchase. Warranty, support and version terms are mandatory — see §5. |
| VN-07 | Azure — cloud platform | Consumption | B. Trammell | Infrastructure and managed database services. Business associate agreement in place. |
| VN-08 | Murfreesboro Secure Logistics — transfer appliances | Fixed price | D. Fontenot | Five appliances, archive transfer. Chain of custody and destruction certificate. |
3. Onboarding Gate
No vendor performs work before every condition is met. Each is evidenced, not asserted.
| Ref | Condition | Evidence |
|---|---|---|
| ON-01 | Business associate agreement executed | ⚠ Required before any access to member data, not before go-live. Signed instrument on the BAA register. |
| ON-02 | Security review completed | Assessment on file; findings closed or accepted by the CISO with a named accepter |
| ON-03 | Insurance certificates current | Professional liability, cyber, workers compensation at contracted limits |
| ON-04 | Data location commitment | ⚠ No member data outside the United States. Contractual, not policy. |
| ON-05 | Named personnel and background checks | Individuals identified; substitution requires ACME agreement for key roles |
| ON-06 | Access provisioned to least privilege | Just-in-time elevation where privileged access is needed; standing admin access is not granted |
| ON-07 | SOW executed with §4 content complete | ⚠ An incomplete SOW is not a fast start; it is an unpriced obligation |
4. Mandatory Statement of Work Content
Every program SOW carries these clauses. Anything absent is escalated to Procurement before signature rather than negotiated during delivery.
| Clause | Applies to | Requirement |
|---|---|---|
| Deliverables and acceptance criteria | All | What "done" means, tested how, accepted by whom. ⚠ Acceptance criteria written before work starts, not at invoice time. |
| Named key personnel | All | Individuals named; substitution of key roles requires ACME agreement |
| Rate card and vehicle | All | Deliverable, fixed price or time and materials, stated explicitly. ⚠ Not left to be inferred from how invoices arrive. |
| Data handling and location | All | Business associate terms, encryption, retention, onshore constraint |
| Security obligations | All | Incident notification window, right to audit, subcontractor flow-down |
| Warranty period | Software, hardware, cloud | See §5 |
| Support model and staffing | Software, hardware, cloud | See §5 |
| Version and upgrade obligations | Software, cloud | See §5 |
| Knowledge transfer | All | A deliverable with named receivers and acceptance, not a by-product |
| Termination and transition out | All | Notice period, transition assistance obligation, data return format |
| Intellectual property and license scope | Software | ⚠ Who owns configuration and custom rules built during the program |
| Change control | All | Scope changes priced and approved before work, against the program's thresholds |
5. Warranty, Support and Version Obligations
These apply wherever the program acquires software, hardware, or an external cloud service — the EMPI platform, the cloud platform, the managed service, and the transfer appliances.
| Ref | Term | What the SOW must specify |
|---|---|---|
| SW-01 | Warranty period | Duration from acceptance, and what it covers. ⚠ A warranty running from delivery rather than acceptance can expire before the product is in production use. |
| SW-02 | Defect remediation service levels | Response and resolution times by severity, using the program's severity definitions rather than the vendor's |
| SW-03 | Support staffing | Named support contacts, coverage hours, on-call obligation, and escalation path. ⚠ Coverage must extend to cutover weekends and hypercare. |
| SW-04 | Version updates and patches | Who applies them, in what window, and who tests. Security patches on a defined clock separate from feature releases. |
| SW-05 | Backward compatibility and interface stability | ⚠ Notice period before a change that breaks an existing interface, and who pays for the remediation |
| SW-06 | End-of-life and end-of-support notice | Minimum notice before a version leaves support, and the obligation to provide a migration path |
| SW-07 | Escrow or continuity | For any product where a vendor failure would stop operations |
| SW-08 | Environment coverage | Whether support covers non-production. ⚠ A test environment nobody will fix stops testing. |
6. Individual Statements of Work
Each engaged vendor has its own instrument. These are the representative SOWs behind the register in §2 — scope, vehicle, term and the §4 and §5 clauses that apply to each.
| Ref | Statement of work | Vehicle | §5 terms that apply |
|---|---|---|---|
| VN-01 | Arrington — program management and specialist advisory | Deliverable | Not applicable — services only. Knowledge transfer and key personnel apply. |
| VN-02 | Rutherford — co-managed cloud operations | Fixed price + T&M | ⚠ SW-02, SW-03, SW-04, SW-08. Step-down milestones are acceptance-gated. |
| VN-03 | Gallatin — X12 transaction assurance | Fixed price | SW-02 for tooling defects. Test environment coverage under SW-08. |
| VN-04 | Two Rivers — data steward staff augmentation | Staff aug | Not applicable. ⚠ Co-employment guardrails and substitution terms apply instead. |
| VN-05 | Harpeth — clean team services | Fixed price | Not applicable. Terminates at closing; output scope defined by protocol. |
| VN-06 | EMPI platform — license, implementation and support | License + support | All of SW-01 to SW-08. ⚠ Configuration and match-rule IP explicitly ACME's. |
| VN-07 | Azure — cloud platform consumption | Consumption | SW-04, SW-05, SW-06 through platform terms. BAA executed. |
| VN-08 | Transfer appliance service | Fixed price | SW-01, SW-03. Chain of custody and certified destruction. |
7. Performance Management
| Vendor | Measured on | Cadence |
|---|---|---|
| Rutherford Cloud Operations | Step-down milestones evidenced, incident response, access discipline | Check-in every 3 weeks; written status weekly |
| Two Rivers Talent Partners | ⚠ Steward retention and time-to-productive, not hours billed | Check-in every 3 weeks; written status weekly |
| Gallatin EDI Assurance | Transaction coverage, defect detection rate, aging | Monthly check-in; written status weekly |
| Madison Data Systems | Support response against SW-02, patch currency | Monthly |
| Arrington Advisory Group | Deliverable acceptance on first submission | Continuous; formal review at each gate |
8. Escalation and Remedy
| Level | Trigger | Owner | Action |
|---|---|---|---|
| 1 | Missed deliverable or service level | ACME vendor owner | Raised at the next check-in with a recovery date |
| 2 | Repeat miss, or a recovery date missed | C. Tyrrell | Written notice; remediation plan required within five business days |
| 3 | Remediation plan fails | H. Castellow | Contractual remedy invoked — service credits, withheld payment, or step-in |
| 4 | Material breach | D. Ashmore + Legal | ⚠ Termination assessed against transition risk, not against frustration |
9. Transition Out
| Requirement | Standard |
|---|---|
| Transition assistance | Contracted obligation with a defined period, not goodwill |
| Data and artifact return | ⚠ In a usable, documented format. "Available on request" is not a format. |
| Configuration and IP | ACME retains configuration, rules and documentation built during the engagement |
| Access revocation | Same-day on exit, evidenced. Includes subcontractor accounts. |
| Knowledge transfer acceptance | Reverse-shadowing: ACME performs unaided while the vendor observes |
| Surviving obligations | Confidentiality, business associate terms and record retention continue past termination |
Schedule A — Register of Engaged Suppliers and Signatories
Every supplier the program engages, the instrument that binds them, and the officer authorized to execute on their behalf. Issued with this plan on August 28, 2023 and updated as instruments are executed.
| Ref | Supplier and authorized signatory | Instrument | Vehicle | ACME owner | Warranty terms |
|---|---|---|---|---|---|
| VN-01 | Arrington Advisory Group G. Hollowell, Managing Principal | ARR-2023-01 | Deliverable statement of work | D. Ashmore | none — services only |
| VN-02 | Rutherford Cloud Operations D. Pennington, President | SOW-02 | Fixed price for the operating baseline, time and materials for project work | B. Trammell | 4 of 8 |
| VN-03 | Gallatin EDI Assurance M. Everly, Managing Director | SOW-03 | Fixed price, deliverable-based | W. Ferriday | 2 of 8 |
| VN-04 | Two Rivers Talent Partners R. Sowell, President | SOW-04 | Time and materials, staff augmentation | T. Vandiver | none — services only |
| VN-05 | Harpeth Clean Team Services E. Sandlin, Managing Partner | SOW-05 | Fixed price, engaged through ACME Legal | L. Hollingsworth | none — services only |
| VN-06 | Madison Data Systems A. Thornbury, Senior Vice President, Contracts | SOW-06 | Perpetual license + implementation services + annual support | Dr. A. Ravindran | 8 of 8 |
| VN-07 | Microsoft Azure T. Hargrove, Vice President, Enterprise Agreements | SOW-07 | Consumption, ordered under ACME's existing enterprise agreement | B. Trammell | 3 of 8 |
| VN-08 | Murfreesboro Secure Logistics C. Wexler, Director of Secure Logistics | SOW-08 | Fixed price per appliance rotation | D. Fontenot | 2 of 8 |
Related artifacts: 8 — Consulting SOW & Engagement Model · 9 — Integration Management Plan · 12 — Program Budget · 14 — Resource Plan · 17 — Communications Plan · 21 — Vendor & Contract Disposition Matrix · 22 — TSA Schedule & Exit Plan · 24 — Cloud Migration Strategy