Physical transfer of the 340 TB historical claims archive to Azure using encrypted transfer appliances. ⚠ This instrument exists because the archive cannot cross the network inside the migration window — the arithmetic is in the Cloud Migration Wave Plan — and it works only because the archive is cold.
1. Parties, Instrument and Term
| Attribute | Provision |
|---|---|
| Client | ACME Health |
| Supplier | Murfreesboro Secure Logistics |
| Instrument | SOW-08, issued under the Master Services Agreement |
| Vendor register reference | VN-08 in the Vendor Management Plan |
| Vehicle | Fixed price per appliance rotation |
| ACME owner | D. Fontenot, Senior Cloud Engineer |
| Effective | August 28, 2023 — ⚠ subject to execution under §7 |
| Term | From execution through completion of archive transfer and certified destruction. |
| Governing document | Vendor Management Plan §4 and §5. ⚠ Clauses in those sections are mandatory and are reproduced here in full rather than incorporated by reference. |
2. Background and Purpose
A 340 TB historical claims archive must reach Azure before the data center exits, and the arithmetic in the Cloud Migration Wave Plan shows it cannot cross the network inside the window. Supplier moves it physically on encrypted appliances. Why the boundary is drawn here: ACME selects and stages the data and verifies the restore; Supplier is responsible for custody and integrity in transit. ⚠ The instrument works only because the archive is cold — a moving data set cannot be shipped.
3. Definitions
These terms carry the meaning below wherever they appear in this Statement of Work. Where a term is also defined in the Master Services Agreement and the two differ, the Master Services Agreement governs under §15.
| Term | Meaning in this Statement of Work |
|---|---|
| Acceptance | Written confirmation by ACME that a Deliverable meets its stated Acceptance Criterion, or expiry of the review period in §5.1 without written rejection. |
| Acceptance Criterion | The objective, demonstrable condition stated against each Deliverable in §5. ⚠ A criterion that cannot be demonstrated is not a criterion. |
| Deliverable | An item Supplier is contractually obliged to produce under §5. |
| Defect | A failure of delivered scope to perform in accordance with its Acceptance Criterion or the as-built documentation — as distinct from a request for new or changed function, which is a Change Order. |
| Client Dependency | An obligation of ACME under §6 on which Supplier performance depends. |
| Warranty Period | The 90 calendar days following Acceptance of the Deliverable concerned. ⚠ Not from delivery, and not from execution. |
| PHI | Protected health information as defined under HIPAA, in respect of which the Business Associate Agreement at GC-06 governs. |
| Change Order | A written amendment under §9, executed by the same authorities that executed this Statement of Work. |
4. Scope of Services
4.1 In scope — Supplier delivered
| Ref | Element | Provision |
|---|---|---|
| SC-01 | Appliance provision | 5 encrypted appliances, rotated until the archive is transferred. |
| SC-02 | Chain of custody | ⚠ Documented custody from ACME data center to Azure ingest, with signature at every transfer of possession. |
| SC-03 | Encryption | Data encrypted at rest on the appliance with keys held only by ACME. Supplier cannot read the data it transports. |
| SC-04 | Transport and insurance | Insured transport at replacement value of the media plus notification cost in the event of loss. |
| SC-05 | Ingest verification | Checksums verified on ingest; a failed appliance is re-run at Supplier cost. |
| SC-06 | Certified destruction | ⚠ Appliance media sanitized to standard after successful ingest, with a certificate of destruction per appliance. |
4.2 Out of scope
The following are not Supplier scope under this instrument. They are stated because an exclusion nobody wrote down is an argument waiting to happen at the moment it is least affordable.
| Ref | Excluded | Where it sits instead |
|---|---|---|
| EX-01 | Data selection | ACME identifies what is transferred; Supplier moves it. |
| EX-02 | Archive restoration testing | Restore verification is ACME scope. |
| EX-03 | Network transfer | ⚠ Out of scope by design — the archive cannot cross the network inside the window. |
5. Deliverables and Acceptance
Acceptance Criteria are stated here, before work begins. ⚠ A Deliverable is accepted when its criterion is demonstrated, not when Supplier declares it complete.
| Ref | Deliverable | Acceptance criterion |
|---|---|---|
| DL-01 | Appliances delivered on the rotation schedule | Against the wave plan calendar |
| DL-02 | Chain of custody records | Complete and signed for every rotation |
| DL-03 | Ingest verification report | Checksums matched, record counts reconciled |
| DL-04 | Certificates of destruction | ⚠ One per appliance. The engagement is not complete without all of them. |
5.1 Acceptance process
Supplier submits each Deliverable in writing. ACME has 10 business days from submission to accept it or to reject it in writing. A rejection must cite the Acceptance Criterion the Deliverable fails and state what would satisfy it; a rejection doing neither is not a rejection for the purposes of this clause. Supplier remedies and resubmits, and the review period restarts for the resubmitted Deliverable only. A Deliverable neither accepted nor rejected within 10 business days is deemed accepted.
Deemed acceptance protects the supplier, and that is why it belongs in ACME's own template. Without it a client that simply goes quiet suspends payment indefinitely while the supplier carries the cost. ⚠ It also creates the obligation ACME is most likely to fail: C-04 in §6 is a real dependency with a named owner, and on this program the review window repeatedly falls during cutover, when the people qualified to review are the people running it.
6. Client Responsibilities and Dependencies
Supplier performance is conditional on ACME meeting the following. Failure of a Client Dependency does not entitle Supplier to additional payment except through an approved Change Order under §9, but may entitle Supplier to a schedule adjustment of no more than the period of the delay.
| Ref | ACME obligation | ACME owner | Timing |
|---|---|---|---|
| C-01 | Stage the archive and confirm it is cold before each rotation | D. Fontenot | Per rotation |
| C-02 | Provide secure physical custody at both ends | A. Quintanilla, CISO | Per rotation |
| C-03 | Provide encryption keys under ACME sole control | A. Quintanilla, CISO | Before first rotation |
| C-04 | Accept or reject each Deliverable within the review period in §5.1 | D. Fontenot | Per submission |
⚠ A dependency without a named owner and a date is a wish. These are the clauses a supplier cites when the program slips, and ACME cannot argue with them after the fact — which is precisely the reason to agree them before the work starts rather than once it is late.
7. Fees and Payment
⚠ Fee amounts are carried in the Program Budget and the Vendor Management Plan and are not restated here. What this section fixes is what triggers payment — the term that decides which party carries risk between milestones.
| # | Payment milestone | Deliverable | % of SOW value |
|---|---|---|---|
| 1 | Execution and mobilization | — | 10% |
| 2 | Acceptance of DL-01 | DL-01 | 21% |
| 3 | Acceptance of DL-02 | DL-02 | 21% |
| 4 | Acceptance of DL-03 | DL-03 | 21% |
| 5 | Acceptance of DL-04 | DL-04 | 22% |
| 6 | Warranty exit and closeout | — | 5% |
Payment falls due thirty days after Acceptance of the linked Deliverable under §5.1 — not on submission, and not on invoice.
The five per cent held to warranty exit is the point of this schedule. It is small enough to be uncontroversial at signature and disproportionately effective afterwards, because it keeps Supplier commercially engaged through the period when defects actually surface. A schedule that fully discharges at go-live removes Supplier's incentive at exactly the moment ACME first depends on the thing working.
8. Key Personnel and Service Levels
Supplier shall not replace personnel named as key without ACME's written consent, and shall provide a replacement of equivalent capability at its own cost where it does. Defect response runs to the levels below, measured from ACME's report.
| Level | Response | Resolution | Definition |
|---|---|---|---|
| Appliance failure in transit | Replacement within 3 business days | — | At Supplier cost |
| Failed ingest | Re-run within 5 business days | — | At Supplier cost |
| Custody record | Same day | — | ⚠ A gap in custody is a reportable incident |
| Destruction certificate | 10 business days after ingest | — | Per appliance |
9. Change Orders
Any change to scope, Deliverables, Acceptance Criteria, service levels or fees takes effect only through a written Change Order executed by the same authorities that executed this Statement of Work under §17. Work performed without an executed Change Order is performed at Supplier's risk and is not payable.
⚠ The signature-parity requirement is the operative half of this clause. Scope creep on an integration program is rarely a decision; it is an accumulation of small agreements between people who each lacked authority to make them. Requiring the original signatories makes every increment visible to the person accountable for the commitment.
10. Warranty
| Ref | Provision |
|---|---|
| WR-01 | Supplier warrants that delivered scope will perform in accordance with its Acceptance Criterion for 90 calendar days following Acceptance of the Deliverable concerned. ⚠ The period runs from Acceptance, not delivery — Vendor Management Plan §5, SW-01. |
| WR-02 | Defects reported during the Warranty Period are remediated at no additional charge, to the service levels in §8. |
| WR-03 | Attribution. Whether an item is a Defect (Supplier remediates) or a change (ACME pays) is determined against the Deliverable's Acceptance Criterion and the as-built documentation. Disputed items escalate under §12 and are classified as they arise, never batched to warranty exit. |
| WR-04 | Defects unresolved at warranty exit are recorded with an agreed remediation path. Warranty exit does not extinguish an unresolved Defect. |
| WR-05 | Remediation of a Defect re-starts the Warranty Period for the remediated component only. |
WR-03 settles the predictable argument in advance. Every warranty period produces the same dispute: is this a defect you fix, or a change I pay for? Agreeing the classification basis at signature — when neither party knows which side of it they will be on — is worth more than any amount of goodwill negotiated later, once the answer has become financially consequential to someone.
11. Warranty, Support and Version Obligations
The obligations below are mandatory under Vendor Management Plan §5 and are not subject to negotiation on price. They govern the period after acceptance, which is where the cost of an incomplete statement of work is actually incurred.
| Ref | Term | Provision |
|---|---|---|
| SW-01 | Warranty period | Supplier warrants the delivered software will perform materially in accordance with its documentation for twelve months from ACCEPTANCE. ⚠ Acceptance, not delivery — a warranty running from delivery can expire before the product is in production use. |
| SW-03 | Support staffing and coverage | Named support contacts with a defined escalation path. ⚠ Coverage extends to cutover weekends and hypercare periods on the program calendar, not Supplier's standard business hours. Coverage windows are listed by date in an annex updated at each wave. |
12. Governance and Escalation
| Level | Forum | ACME | Escalates when |
|---|---|---|---|
| Operational | Weekly supplier check-in — individual, never joint | D. Fontenot | Delivery, defects and dependencies in the ordinary course |
| Program | IMO weekly | C. Tyrrell, Program Manager | A dependency or Defect threatens a program milestone |
| Commercial | Procurement review | H. Castellow, VP Procurement | Fees, Change Orders, or performance against §8 service levels |
| Executive | Integration Steering Committee | D. Ashmore, CFO and Sponsor | Termination is contemplated, or a dispute is unresolved after thirty days |
⚠ Suppliers are met individually and never together. A joint forum means discussing one supplier's delivery problems in front of another who may bid for the same work next year — and a supplier will not tell you its delivery lead has resigned with a competitor in the room. Cross-supplier dependencies are brokered through the program.
13. Limitation of Liability
Each party's aggregate liability arising out of or in connection with this Statement of Work is limited to the fees paid and payable under it in the twelve months preceding the event giving rise to the claim. Neither party is liable for indirect or consequential loss.
The following are excluded from that cap and are unlimited:
| Ref | Uncapped liability |
|---|---|
| LL-01 | Breach of confidentiality. |
| LL-02 | Any breach, loss or unauthorized disclosure of PHI, and any breach of the Business Associate Agreement at GC-06. |
| LL-03 | Indemnity against third-party claims that delivered scope infringes intellectual property rights. |
The cap is a formula rather than a figure, and that matters on a program of this length. A cap fixed in dollars at signature stops tracking the exposure as the engagement grows; a rolling twelve-month cap moves with what Supplier is actually being paid. ⚠ The three carve-outs are the ones ACME cannot accept a cap on, because each can cost more than the whole instrument is worth — a PHI breach is priced by regulators and by the number of members affected, not by what the supplier was paid to prevent it.
14. Termination and Transition Assistance
| Ref | Provision |
|---|---|
| TM-01 | For cause. Either party may terminate on written notice for material breach not remedied within 30 days of notice specifying the breach and what would remedy it. ⚠ Repeated breach of the same obligation is material whether or not each instance is. |
| TM-02 | For convenience. ACME may terminate on 60 days' written notice, paying for Deliverables accepted and work properly performed to the termination date and for no other amount. ⚠ Supplier holds no equivalent right during the TSA exit window. |
| TM-03 | Insolvency. Either party may terminate immediately on the other's insolvency, administration or equivalent process. |
| TM-04 | Transition assistance. On termination or expiry for any reason, Supplier provides transition assistance for up to 90 days at the rates then in effect — ACME data in an agreed format, as-built configuration documentation, and knowledge transfer to ACME or its nominee. This obligation survives termination, including termination by Supplier for ACME's breach. |
| TM-05 | No suspension for disputed sums. Supplier shall not suspend service or withhold transition assistance on account of a disputed invoice; disputes run through §12 escalation. |
Transition assistance is negotiated now because it cannot be negotiated later. It is the term a client has least leverage to obtain at the moment it needs it — by then the relationship has usually failed and the supplier has no commercial reason to help. ⭐ Leverage is set by how long you still need someone, not by how long the relationship has left to run, and TM-05 exists because withholding help over a disputed invoice is the most common way this clause is defeated in practice.
15. Order of Precedence
Where documents conflict, the following order applies:
| # | Document |
|---|---|
| 1 | The Master Services Agreement |
| 2 | The Business Associate Agreement, in respect of PHI |
| 3 | Executed Change Orders, most recent first |
| 4 | This Statement of Work |
| 5 | Vendor Management Plan §4 and §5, as reproduced here |
| 6 | Supplier proposals and correspondence |
⚠ Supplier proposals rank last deliberately. A proposal is written to win the work: it routinely contains commitments the supplier would not accept as contractual alongside assumptions ACME never agreed. Ranking it above this instrument would import both.
16. General Conditions
| Ref | Clause | Provision |
|---|---|---|
| GC-01 | Governing agreement | This statement of work is issued under the Master Services Agreement between ACME Health and Murfreesboro Secure Logistics. Where the two conflict, the Master Services Agreement governs except on scope, price and schedule, which this instrument governs. |
| GC-02 | Contracting party across the close | ⚠ Executed before closing by ACME Health. Cumberland Valley Health Plan becomes a beneficiary at closing without further action; no novation is required because ACME is the contracting party throughout. |
| GC-03 | Key personnel | Named individuals in §2 may not be substituted without written agreement. A substitution without agreement is a material failure, not an administrative change. |
| GC-04 | Subcontracting | No subcontracting without prior written consent. All obligations of this instrument flow down to any approved subcontractor, including data-handling and audit rights. |
| GC-05 | Data handling and location | ⚠ No member-level data is processed, stored or accessed outside the United States. This is a contractual obligation, not a policy preference, and derives from a condition of the state insurance approval. |
| GC-06 | Business associate agreement | A business associate agreement is executed before any access to protected health information, and remains in force through the retention period after termination. |
| GC-07 | Security incident notification | Supplier notifies ACME within 24 hours of discovering a suspected security or privacy incident. ⚠ The clock runs from discovery, not from confirmation. |
| GC-08 | Audit rights | ACME may audit compliance on 10 business days' notice, and without notice following a reported incident. |
| GC-09 | Insurance | Professional liability, cyber liability and workers compensation maintained at the limits in the Master Services Agreement; certificates provided before work begins and on renewal. |
| GC-10 | Change control | Scope changes are priced and approved before work begins, against the program's thresholds ($250,000 Program Manager, $1,000,000 Executive Sponsor, above that the Steering Committee). ⚠ Work performed before approval is performed at Supplier's risk. |
| GC-11 | Intellectual property | Not applicable. ⚠ Supplier acquires no rights of any kind in the transported data and is prohibited from retaining, copying or indexing it. |
| GC-12 | Knowledge transfer | Knowledge transfer is a deliverable with named receivers and an acceptance test, not a by-product of the work. Acceptance is by reverse shadowing: ACME performs unaided while Supplier observes. |
| GC-13 | Termination for convenience | ACME may terminate on 30 days' written notice. Supplier is paid for work accepted and work in progress to the termination date. |
| GC-14 | Transition assistance | ⚠ On termination for any reason, Supplier provides transition assistance for up to 90 days at the rates in §4, and returns all data and artifacts in a documented, usable format. "Available on request" is not a format. |
| GC-15 | Surviving obligations | Confidentiality, business associate terms, data return and record retention survive termination. |
| GC-16 | Independence | Supplier confirms no engagement with Cumberland Valley Health Plan, Cheatham Mutual Holdings, or any party adverse to the transaction, and will disclose any such engagement arising during the term. |
17. Execution
This statement of work is not effective until executed by an authorized signatory of both parties and endorsed by ACME Legal. ⚠ Work performed before execution is performed at Supplier's risk and is not payable.
Related: 21A — Vendor Management Plan · 8 — Consulting SOW & Engagement Model · 21 — Vendor & Contract Disposition Matrix · 26 — Quality Plan