← Drug Development Suite Decision Criteria · Vitalis Therapeutics Inc.

Gate Decision Framework

Download Word
Program timeline · status 15 Oct 2026Read the full story →
Gate 0
Mar 2022
Go
Stage 1
Nonclinical
Gate 1
Dec 2022
Go
Stage 2
IND & Phase 1
Gate 2
Jun 2023
Go
Gate 3
May 2024
Go
Gate 4
Jun 2026
Go w/ conditions
Stage 4
Phase 3
You are here
Gate 5
Sep 2028
Gate 6
Oct 2029
Launch
Nov 2029

Vitalis Therapeutics Inc. — The criteria against which every gate in the VitaFlow (VTX-401) program is decided: the two-tier must-meet and should-meet model, the scoring scale, the evidence standard, and the full criteria set for all seven gates. Operates alongside the Development Committee Charter, which defines who decides.

7
Gates
2
Criteria tiers
3
Threshold score
5
Possible outcomes
Contents
  1. The Two-Tier Model
  2. Scoring Scale
  3. Evidence Standard
  4. Gate Criteria
  5. How an Outcome Is Derived
  6. Worked Example — the Gate 4 Score Sheet
  7. What a RECYCLE Would Have Looked Like
  8. Evidence Packs
  9. Criteria Change Control

1. The Two-Tier Model

Every gate assesses two kinds of criteria, and they behave differently on purpose.

TierNatureEffect of a shortfall
Must-meetBinary. Satisfied or not.An unsatisfied must-meet cannot produce a GO. The outcome is RECYCLE if remediable, KILL if not. It is not outvotable — a majority cannot vote a criterion into satisfaction.
Should-meetScored 1–5 against a defined scale.Scores at threshold (3) produce conditions. Scores below threshold drive RECYCLE. Scores at 4 or 5 carry no consequence.
Why the tiers are separated. A single blended score lets a strong commercial case compensate for a weak safety package. Separating them prevents that arithmetic: no amount of commercial upside converts an unsatisfied must-meet into a pass, because the two tiers do not share a scale.

2. Scoring Scale

ScoreMeaning
5Fully satisfied. Evidence complete and independently verifiable.
4Satisfied. Minor gaps that do not affect the decision.
3Threshold. Satisfiable inside the next stage — the score that produces a condition rather than a failure.
2Materially short. Drives RECYCLE unless a must-meet is also unsatisfied.
1Absent. No credible evidence tabled.

The threshold score is 3. It is deliberately defined as “satisfiable inside the next stage” rather than “adequate”, because the question a gate asks about a should-meet criterion is not whether the position is good — it is whether the gap can be closed with work the program is about to do anyway.

3. Evidence Standard

A criterion is assessed on evidence tabled at the gate, not on assurance given at the gate. The Chair certifies that what has been tabled meets the standard; the Committee decides what it means.

AcceptableNot acceptable
Signed reports, agency minutes, validated datasetsVerbal summary of a report not yet issued
Executed contracts and dated commitmentsDraft agreements and expressions of intent
Data from the running studyExtrapolation from an earlier phase
Independent verification where the criterion is contestedSelf-assessment by the owning function alone
Assertion is not evidence. “The team is confident enrolment will recover” is an assertion. A site activation schedule with dated commitments and a screen-failure rate from the running study is evidence. Where only assertion is available, the criterion scores 1 — not 3 with a caveat.

4. Gate Criteria

Criteria are set when a gate is defined and are not revised inside the stage that leads to it. A criterion the program discovers it cannot meet is a matter to escalate, not a matter to rewrite.

Gate 0 — Candidate Selection — 01 Mar 2022 · GO (6-0)

Must-meet

RefCriterion
M1Target validated in at least two independent models
M2Freedom-to-operate opinion obtained
M3Candidate meets the minimum target product profile

Should-meet

RefCriterionScore
S1Differentiation against approved products in the class4
S2Projected development cost within portfolio tolerance4
S3Commercial case supports the therapeutic area5

Gate 1 — IND-Enabling Readiness — 31 Dec 2022 · GO (5-1)

Must-meet

RefCriterion
M1GLP toxicology package complete and supportive of first-in-human
M2Drug substance route defined and reproducible at scale
M3Regulatory strategy agreed and pathway confirmed

Should-meet

RefCriterionScore
S1Analytical methods qualified3
S2Drug product formulation stable to the required shelf life4
S3Clinical development plan costed and resourced4

Gate 2 — IND Submission — 30 Jun 2023 · GO (6-0)

Must-meet

RefCriterion
M1IND submitted and accepted — thirty-day review clear
M2Phase 1 protocol final and IRB-approved
M3Clinical supply released to specification

Should-meet

RefCriterionScore
S1Investigator sites contracted4
S2Pharmacovigilance system operational5

Gate 3 — Phase 2 Readiness — 31 May 2024 · GO (6-0)

Must-meet

RefCriterion
M1Phase 1 safety and tolerability support continued development
M2Pharmacokinetic profile supports the intended dosing interval
M3Phase 2 protocol final, dose span justified

Should-meet

RefCriterionScore
S1Phase 2 sites identified and activation sequenced4
S2CMC capacity adequate for Phase 2 supply4
S3Competitive landscape unchanged in a material way3

Gate 4 — Phase 3 Initiation — 30 Jun 2026 · GO WITH CONDITIONS (5-0-1)

Must-meet

RefCriterion
M1Phase 2 efficacy demonstrated at a dose with acceptable tolerability
M2End-of-Phase-2 meeting held; pivotal design and endpoints agreed with the agency
M3Phase 3 protocol final and statistically powered to the agreed endpoints
M4Manufacturing plan supports registration-batch timing

Should-meet

RefCriterionScore
S1CMC readiness — analytical method transfer complete3
S2Market access evidence plan in place3
S3Phase 3 site and enrolment plan credible against the curve4
S4Business case clears the hurdle on refreshed assumptions4

Three should-meet criteria scored 3 at Gate 4 — CMC method transfer, market access evidence, and (at 4) the enrolment plan. The two scored at threshold produced GC-01 and GC-03. This is the framework working as designed: the gate carried, and the two weakest areas were converted into dated, owned, verifiable obligations rather than absorbed as optimism.

Gate 5 — NDA Submission — 30 Sep 2028 · pending

Must-meet

RefCriterion
M1Both pivotal trials met the co-primary endpoints
M2Safety database complete and integrated summaries drafted
M3Registration batches manufactured, on stability, process validation complete
M4Pre-NDA meeting held and content agreed

Should-meet

RefCriterionScore
S1Labeling strategy aligned to the datanot yet assessed
S2Launch supply plan credible against the action datenot yet assessed
S3Payer evidence package completenot yet assessed

Gate 5 is the next gate. Should-meet criteria are recorded but not yet scored; scoring happens at the gate on evidence tabled, not in advance. Open items carried against them are tracked in the Gate Conditions Register, and live position against every criterion is maintained in the Gate 5 Readiness Assessment.

Gate 6 — Approval & Launch — 11 Oct 2029 · pending

Must-meet

RefCriterion
M1Approval granted
M2Pre-approval inspection closed with no unresolved deficiency
M3Launch supply released and in distribution

Should-meet

RefCriterionScore
S1Field force trained and deployednot yet assessed
S2Payer coverage secured in the launch accountsnot yet assessed

5. How an Outcome Is Derived

  1. Assess must-meets first. If any is unsatisfied, the outcome is RECYCLE or KILL and the should-meet scoring is not reached. This ordering matters: scoring first invites the committee to weigh a strong overall picture against a specific unmet obligation.
  2. Score should-meets against §2, on evidence per §3.
  3. Derive the outcome. All must-meets satisfied and no should-meet below 4 → GO. All must-meets satisfied with one or more should-meets at 3 → GO WITH CONDITIONS, one condition per criterion at threshold. Any should-meet at 2 or below → RECYCLE.
  4. Record. The score sheet is part of the minutes and is not amended after approval.
The outcome is derived, not negotiated. The Committee's judgment is exercised in the scoring — which is where judgment belongs — not in the step from scores to outcome. Once the scores are recorded the outcome follows mechanically, which is what stops a gate from becoming a negotiation about how much the program would like to proceed.

6. Worked Example — the Gate 4 Score Sheet

The framework above describes machinery. This section runs it, using the actual Gate 4 decision of 30 June 2026.

Step 1 — Must-meet assessment

RefCriterionEvidence tabledAssessment
M1Phase 2 efficacy demonstrated at a dose with acceptable tolerabilityLocked Phase 2 dataset; primary and secondary endpoint analyzes; discontinuation rates by dose armsatisfied
M2End-of-Phase-2 meeting held; pivotal design and endpoints agreed with the agencyOfficial minutes, 19 May 2026; agreed co-primary endpoints; CV safety expectation recordedsatisfied
M3Phase 3 protocol final and statistically powered to the agreed endpointsFinal protocol v1.0; statistical analysis plan; power calculation at 90% for both co-primariessatisfied
M4Manufacturing plan supports registration-batch timingCMC plan with registration-batch schedule; Aldergate capacity confirmationsatisfied

All four satisfied. The gate proceeds to scoring. Had any been unsatisfied, scoring would not have occurred — the ordering at §5 exists precisely so that a strong overall picture cannot be weighed against a specific unmet obligation.

Step 2 — Should-meet scoring

RefCriterionScoreBasis
S1CMC readiness — analytical method transfer complete3Two of three methods re-qualified at Aldergate; the third in progress with a dated plan. Closeable inside Stage 4, so threshold rather than below.
S2Market access evidence plan in place3Evidence plan drafted; payer advisory board program scoped but not scheduled. Work identified, not started.
S3Phase 3 site and enrolment plan credible against the curve4Site list with activation sequence and a reserve list; recruitment rates carried forward from Phase 2 with a stated haircut.
S4Business case clears the hurdle on refreshed assumptions4Refreshed model returns 43.6% against a 15.0% hurdle. Minor gap: gross-to-net assumptions not re-tested against the latest payer landscape.

Step 3 — Outcome derivation

All must-meets satisfied; two should-meets at threshold. Per §5 the outcome is GO WITH CONDITIONS, with one condition per criterion at threshold. Nothing here is a judgment call at this step — the judgment was exercised in the scoring.

Threshold criterionCondition issuedOwnerDue
S1 — CMC method transferGC-01 — complete re-qualification for all three methodsDr. K. Oyelaran18 Dec 2026
S2 — Market access evidenceGC-03 — stand up the payer evidence plan and hold first advisory boardsJ. Barrington31 Mar 2027

GC-02 was also issued at this gate, but not from a threshold score — it arose from the CR-02 scope addition approved shortly before, and attaches the DMC protocol confirmation to the sub-study. Conditions may be issued for reasons other than a threshold score; a threshold score must always produce one.

Step 4 — The vote

Recorded outcome: GO WITH CONDITIONS (5-0-1). Five voting seats, four in favour, one abstention. The abstention was recorded by the Chief Financial Officer against S4 — specifically the un-refreshed gross-to-net assumptions — on the basis that a $125,800,000 release warranted a fully re-tested commercial model rather than one with a stated minor gap.

The abstention was not overruled and did not block the gate. It is part of the permanent record, and it is the reason the business case refresh carries a standing item at Gate 5. An abstention is a statement that a member cannot support the decision on the evidence tabled — recording the reason is what makes it useful eighteen months later, when the question of whether the commercial case was tested becomes live again.

7. What a RECYCLE Would Have Looked Like

Gate 4 carried. It is worth setting out what the same gate would have produced had the evidence been weaker, because a framework is only meaningful if the failure paths are as well defined as the success path.

Scenario — M1 unsatisfied

Suppose the Phase 2 dataset had shown efficacy at the top dose but with a discontinuation rate materially above the modelled figure, such that no dose demonstrated efficacy with acceptable tolerability. M1 is then unsatisfied.

StepWhat happens
ScoringDoes not occur. The must-meet assessment terminates the gate.
OutcomeRECYCLE — the criterion is unsatisfied but remediable: an extended dose-escalation schedule is work the program can actually perform.
TrancheThe $125,800,000 Stage 4 tranche does not release. Phase 3 does not start, and no CRO Phase 3 work package is authorized.
Remediation scopeChair produces it within ten working days: a tolerability sub-study on a revised escalation schedule, its cost, its owner, and the date Gate 4 re-convenes.
FundingFrom contingency, against a named draw. The cost of the recycle is therefore visible in the Program Budget rather than absorbed.
RosterRetained. Releasing and rebuilding a 109-person program team costs more than carrying it through a remediation window.
AgencyThe End-of-Phase-2 position may require revisiting, since dose selection was agreed on the superseded data. This is usually the longest pole in a recycle, not the clinical work itself.
Why this scenario matters more than the one that happened. A committee with no RECYCLE option facing an unsatisfied M1 has two usable choices: pass anyway on an understanding that tolerability will be managed in Phase 3, or kill an asset that has cleared every other criterion. It will choose to pass, and the program will discover in Phase 3 — at $125,800,000 rather than at the cost of a sub-study — what it could have learned first.

8. Evidence Packs

Each criterion is assessed on a defined evidence pack, submitted at day −20 per the gate preparation timetable in the Development Committee Charter. Pack contents are fixed when the gate is defined.

GateEvidence pack contents
Gate 0Target validation data from two independent models; freedom-to-operate opinion; target product profile; indicative development cost and timeline.
Gate 1GLP toxicology study reports; drug substance route and reproducibility data; formulation stability data; regulatory strategy document; costed clinical development plan.
Gate 2IND submission receipt and thirty-day clearance; final Phase 1 protocol with IRB approvals; certificate of analysis and release documentation for clinical supply; executed site contracts; pharmacovigilance system master file.
Gate 3Phase 1 clinical study report; PK/PD analysis; final Phase 2 protocol with dose justification; site activation plan; CMC supply plan for Phase 2.
Gate 4Locked Phase 2 dataset and analyzes; End-of-Phase-2 official minutes; final Phase 3 protocol and statistical analysis plan; power calculation; CMC plan with registration-batch schedule; refreshed business case model; site and enrolment plan.
Gate 5Clinical study reports for both pivotals; integrated summaries of safety and efficacy; registration-batch release and stability data; process validation report; Pre-NDA meeting minutes; draft labeling; launch supply plan.
Gate 6Approval letter; pre-approval inspection close-out; batch release documentation; distribution readiness confirmation; field deployment and training records; payer coverage position in launch accounts.

A pack is a list of documents, not a presentation. Slides may be used to walk the Committee through the pack; they are not themselves evidence, and a criterion supported only by a slide is supported only by assertion (§3).

9. Criteria Change Control

Criteria are set when a gate is defined and are not revised inside the stage leading to it.

The one-stage rule is the whole provision. Without it, a program approaching a gate it will not pass has an obvious and entirely rational move: propose a criteria revision. The revision will be well-argued, the reasoning will be sound, and the gate will be rendered meaningless. Requiring a full stage of separation removes the option at exactly the moment it becomes tempting.