Steering Committee Deck · Portfolio Demo

Enrollment & Claims Platform Modernization

Download PowerPoint
ACME COMPANY

Enrollment & Claims
Platform Modernization

Monthly Program Update — Steering Committee
15 January 2027 Presented by C. Tyrrell, Program Manager
1
Agenda

What We'll Cover Today

Executive Summary
Overall program health and key message
Decision Requested
One item for Steering Committee approval
Schedule & Milestones
Phase progress and the road ahead
Budget & Financials
Spend, forecast, and variance
Risks, Issues & Quality
What's on watch and how we're tracking
Resources & Change Control
Team status and governance activity
Enrollment & Claims Platform Modernization · ACME Company
2
🎯
Executive Summary

Program Health at a Glance

YELLOW
Data Conversion & Integration Build phases now underway. Program has completed Initiation, Requirements & Vendor Selection, and System Upgrade Validation. A high-severity data quality risk in the historical claims data (R-001) could extend the Data Conversion timeline if root-cause cleansing proves insufficient. Get-to-Green plan: complete data profiling ahead of schedule and hold a third Dry Run cycle in reserve. No milestone changes are being proposed this period.
37%
Schedule Complete
43%
Budget Spent
+2.1%
Forecast Variance
1
High-Severity Risk
Next Milestone: Data Conversion Sign-off — 16 March 2027
3
🤝
Decision Requested
Pre-approve contingency utilization of up to $150,000 for a third Data Conversion Dry Run cycle, should root-cause cleansing of historical claims data (R-001) prove insufficient ahead of the scheduled Dry Run 2.
WHY THIS MATTERS
Protects the Data Conversion Sign-off milestone (16 Mar 2027)
Contingency Reserve currently has $0.58M of $0.642M available — sufficient capacity
No schedule impact if approved and invoked promptly; avoided cost if not needed
RECOMMENDATION: Approve
4
📅
Schedule

Program Timeline & Milestones

Project Kickoff
04 Aug 26
Requirements & Vendor Selection
03 Nov 26
System Upgrade Validated
05 Jan 27
Data Conversion Sign-off
16 Mar 27
Integration Build Complete
11 May 27
Testing / UAT Sign-off
10 Aug 27
Go-Live
24 Aug 27

Where We Are

The program has passed three consecutive gate milestones on schedule. Data Conversion and Integration Build are now running in parallel — the program's most execution-intensive stretch — with Testing entrance criteria being prepared alongside. The next gate, Data Conversion Sign-off, is 60 calendar days out.
5
📈
Schedule

Progress by Phase

1. Initiation & Requirements
100
2. System Upgrade
100
3. Data Conversion
16
4. Integration Build (Agile)
9
5. Testing (Functional-UAT)
5
6. Cutover & Hypercare
0
7. Change Mgmt & Training
37
8. Program Governance & Risk
42
KEY TAKEAWAY
Phases 1 & 2 are fully closed. Phases 3 & 4 have just opened and will ramp quickly over the coming weeks. Change Management and Governance run continuously in parallel across the whole program.
37%
OVERALL SCHEDULE COMPLETE
6
Progress

Key Accomplishments This Period

Staging security finding remediated
External penetration test flagged an outdated TLS configuration; patched and re-scanned clean.
M. Alvarez
System Upgrade Validated milestone achieved
Phase 2 formally closed on schedule (05 Jan 2027), clearing the path for Conversion and Build.
M. Alvarez
Data Conversion & Integration Build phases opened
Both workstreams entered execution in parallel this period.
T. McCormick / C. Tyrrell
Architecture continuity established
Decision log created to cross-train the Business Analyst on architecture rationale.
J. Albert
7
🏁
Look Ahead

Planned for Next Period

🕑
Begin Data Conversion mapping
Member/policy data mapping kickoff
T. McCormick
🕑
Begin Integration Build Sprint 1
Across all six integration tracks
6 Track Developers
🕑
Finalize offshore/onshore QA handoff
Awaiting onshore Test Lead sign-off
P. Sundaram / R. Whitfield
🕑
Monitor vendor SOW negotiation
Status: At Risk — contract in progress
W. Donnelly
Next Steering Committee gate: Data Conversion Sign-off review — 16 March 2027
8
💰
Financials

Budget & Financial Status

$7.062M
TOTAL BUDGET
Platform Upgrade
Integration Mid.
Internal Labor
QA Labor
Dev. Labor
Infrastructure
Training/Change
Contingency
$3.05M
Spent to Date (43%)
$7.21M
Forecast at Completion
+2.1%
Variance to Baseline
$0.58M
Contingency Remaining
Full variance is attributed to Internal Labor, reflecting Data Conversion Lead time held in reserve against R-001.
9
Risks & Issues

Top Risks Requiring Attention

R-001
Historical claims data quality issues
Early profiling & automated cleansing rules underway ahead of Dry Run 2
Score 9 · High/High
Owner: T. McCormick
R-003
Vendor SOW negotiation delay
Backup vendor pre-qualified as contingency
Score 6 · Medium/High
Owner: W. Donnelly
R-002
Offshore/onshore QA coordination gaps
Daily overlap-hour standup in place
Score 4 · Medium/Medium
Owner: R. Whitfield
DEP-003
Platform vendor SOW must finalize before Environment Provisioning
Contract negotiation in progress
At Risk
Owner: W. Donnelly
10
🛡
Quality

Quality & KPI Dashboard

MetricTargetCurrent Status
Schedule Performance Index (SPI)≥ 0.95On Track
Cost Performance Index (CPI)≥ 0.95On Track
Data Conversion Accuracy≥ 99.5% record matchNot Yet Measurable — Dry Run 1 Pending
Critical/High Defect Escape Rate to UAT≤ 5%Not Yet Measurable — Build In Progress
Security Findings (Critical/High) at Go-Live0On Track — Staging Finding Remediated
Training Completion Rate≥ 95% prior to Go-LiveNot Started — Scheduled Later Phases
Hypercare Severity-1 Incidents≤ 2Not Yet Applicable
11
👥
Team

Resource & Team Status

C. Tyrrell (PM)
100
J. Albert (Architect)
90
T. McCormick (Data Conv.)
100
M. Alvarez (Sys. Upgrade)
70
R. Whitfield (QA-Onshore)
65
P. Sundaram (QA-Offshore)
50
6 Integration Developers
80
Program team stands at 20 named resources across Program Management, Architecture, Data Conversion, System Upgrade, QA (onshore/offshore), six Integration Development tracks, Compliance/Audit, Procurement, Governance, Change Management, Training, and Customer Experience.
12
🔄
Governance

Change Control Summary

10/10
CHANGE REQUESTS
IMPLEMENTED
Security, Performance & DR Testing added
Steering Committee approved — Testing phase scope
SOX Control Impact Assessment & Compliance Testing
Steering Committee approved — updated WBS, PM Plan, RAIDD Log, Resource Register
Offshore QA Coordination role & dual-shore model
PM-approved — added capacity ahead of Build ramp-up
All change requests to date have followed the program's tiered governance model (PM / PMO / Steering Committee) and are fully reflected in the WBS, PM Plan, RAIDD Log, and Resource Register.
13
📋
Appendix

Steering Committee Roster

NameRoleVoting
G. WhitfieldExecutive Sponsor (VP of Operations)Yes
A. MarchettiCIO / VP of Information TechnologyYes
R. CastellanoVP, UnderwritingYes
J. BoudreauxVP, Claims AdministrationYes
S. WhitcombeVP, FinanceYes
N. SharmaChief Compliance Officer / General CounselYes
S. RyanDirector, PMOYes
C. TyrrellProgram Manager (briefs the committee)No
14

Questions & Discussion

C. Tyrrell, Program Manager
Enrollment & Claims Platform Modernization · ACME Company