Change Control Log · Portfolio Demo

CWP-700 Composite Wing Panel Production Program

Program ManagerC. Tyrrell
Quality Eng. LeadR. Kessler
As Of8 Changes, All Approved
Download Word
Purpose

About This Log

This log records every formal change against the program's engineering baseline or internal process since contract award — what changed, why, and who approved it. Changes affecting form, fit, or function require a Meridian-approved Engineering Change Notice (ECN) regardless of cost impact; process, tooling, and documentation changes that don't touch Meridian's engineering baseline are approved internally, per the decision-rights tiering in the Program Governance Model §3 and §6.

Summary

Changes at a Glance

8 Changes on record — all Approved.

Showing all 8 changes
Log

Change Detail

CN-001
Correct Part Marking Specification Reference
Approved
A drawing reference number in the part marking spec pointed to a superseded revision; corrected to the current revision with no change to the marking requirement itself.
Documentation / AdministrativeApproval: Acme Internal (Tier 1)
View Full Change Document (CN-001) →
CN-002
Clarify Edge-Trim Tolerance Callout
Approved
First Article Inspection found the edge-trim tolerance callout ambiguous between two adjacent drawing views; clarified wording, no change to the actual tolerance value.
Documentation / AdministrativeApproval: Acme Internal (Tier 1)
FAI
View Full Change Document (CN-002) →
CN-003
Revise FAI Checklist Acceptance Criteria Wording
Approved
Customer source-inspection auditor flagged 2 acceptance criteria as ambiguous (RAIDD I-04); checklist reworded with unambiguous pass/fail criteria for all subsequent article runs.
Documentation / AdministrativeApproval: Acme Internal (Tier 1)
RAIDD I-04
View Full Change Document (CN-003) →
CN-004
Update Program Baseline for Corrected Staffing Model
Approved
Formalized the 14→25-person staffing correction into the program's standing resource and schedule baseline, ahead of Phase 2 production ramp.
Schedule / ResourceApproval: Executive Sponsor (Tier 2 — RAIDD D-05)
Resource PlanRAIDD D-05
View Full Change Document (CN-004) →
CN-005
Approve Immersion Ultrasonic Testing as Alternate NDT Method
Approved
Added immersion ultrasonic testing as a Meridian-approved alternate inspection method to contact UT, supporting the corrected two-shift NDT staffing model without changing acceptance criteria.
Engineering Change (ECN)Approval: Meridian Program Office (Tier 3)
RAIDD I-02
View Full Change Document (CN-005) →
CN-006
Revise Layup Fixture Preventive Maintenance Schedule
Approved
Root cause corrective action following MRB-004 (ply misalignment traced to fixture wear) — added a standing preventive-maintenance schedule for the layup fixture. No change to the part or its acceptance criteria.
Process / ToolingApproval: Acme Internal (Tier 2)
MRB-004
View Full Change Document (CN-006) →
CN-007
Add Repair Limits Table for Oversized Fastener Holes
Approved
Formalized the rework disposition used in MRB-001 and MRB-003 into a standing repair-limits table, so future oversized-fastener-hole findings within the approved range don't each require a fresh MRB rework disposition.
Engineering Change (ECN)Approval: Meridian Program Office (Tier 3)
MRB-001, MRB-003
View Full Change Document (CN-007) →
CN-008
Add Second Approved Source for Composite Prepreg Material
Approved
Added a second qualified supplier to the drawing's approved-source list for the primary composite prepreg material, closing out RAIDD R-01's single-source schedule exposure (RAIDD Decision D-03).
Supplier / MaterialApproval: Meridian Program Office (Tier 3)
RAIDD R-01, D-03
View Full Change Document (CN-008) →
Reference

How to Use This Log