Change Control Log · Portfolio Demo

CWP-700 Composite Wing Panel Production Program

Program ManagerC. Tyrrell
Quality Eng. LeadR. Kessler
As Of11 Changes, 8 approved · 2 declined · 1 deferred
Download Word
Purpose

About This Log

This log records every formal change against the program's engineering baseline or internal process since contract award — what changed, why, and who approved it. Changes affecting form, fit, or function require a Meridian-approved Engineering Change Notice (ECN) regardless of cost impact; process, tooling, and documentation changes that don't touch Meridian's engineering baseline are approved internally, per the decision-rights tiering in the Program Governance Model §3 and §6.

Summary

Changes at a Glance

11 Changes on record — all Approved.

Showing all 11 changes
Log

Change Detail

CN-001
Correct Part Marking Specification Reference
Approved
A drawing reference number in the part marking spec pointed to a superseded revision; corrected to the current revision with no change to the marking requirement itself.
Documentation / AdministrativeApproval: Acme Internal (Tier 1)Owner: H. Lindgren (Doc Control)Target/Decided: Jun 15, 2026
View Full Change Document (CN-001) →
CN-002
Clarify Edge-Trim Tolerance Callout
Approved
First Article Inspection found the edge-trim tolerance callout ambiguous between two adjacent drawing views; clarified wording, no change to the actual tolerance value.
Documentation / AdministrativeApproval: Acme Internal (Tier 1)Owner: R. Kessler (Quality Eng. Lead)Target/Decided: Aug 9, 2026
FAI
View Full Change Document (CN-002) →
CN-003
Revise FAI Checklist Acceptance Criteria Wording
Approved
Customer source-inspection auditor flagged 2 acceptance criteria as ambiguous (RAIDD I-04); checklist reworded with unambiguous pass/fail criteria for all subsequent article runs.
Documentation / AdministrativeApproval: Acme Internal (Tier 1)Owner: R. Kessler (Quality Eng. Lead)Target/Decided: Aug 19, 2026
RAIDD I-04
View Full Change Document (CN-003) →
CN-004
Update Program Baseline for Corrected Staffing Model
Approved
Formalized the 14→25-person staffing correction into the program's standing resource and schedule baseline, ahead of Phase 2 production ramp.
Schedule / ResourceApproval: Executive Sponsor (Tier 2 — RAIDD D-05)Owner: C. Tyrrell (Program Manager)Target/Decided: Sep 28, 2026
Resource PlanRAIDD D-05
View Full Change Document (CN-004) →
CN-005
Approve Immersion Ultrasonic Testing as Alternate NDT Method
Approved
Added immersion ultrasonic testing as a Meridian-approved alternate inspection method to contact UT, supporting the corrected two-shift NDT staffing model without changing acceptance criteria.
Engineering Change (ECN)Approval: Meridian Program Office (Tier 3)Owner: L. Vance (Materials/NDT Eng.)Target/Decided: Oct 7, 2026
RAIDD I-02
View Full Change Document (CN-005) →
CN-006
Revise Layup Fixture Preventive Maintenance Schedule
Approved
Root cause corrective action following MRB-004 (ply misalignment traced to fixture wear) — added a standing preventive-maintenance schedule for the layup fixture. No change to the part or its acceptance criteria.
Process / ToolingApproval: Acme Internal (Tier 2)Owner: M. Osei (Manufacturing Eng.)Target/Decided: Dec 11, 2026
MRB-004
View Full Change Document (CN-006) →
CN-007
Add Repair Limits Table for Oversized Fastener Holes
Approved
Formalized the rework disposition used in MRB-001 and MRB-003 into a standing repair-limits table, so future oversized-fastener-hole findings within the approved range don't each require a fresh MRB rework disposition.
Engineering Change (ECN)Approval: Meridian Program Office (Tier 3)Owner: R. Kessler (Quality Eng. Lead)Target/Decided: Jan 5, 2027
MRB-001, MRB-003
View Full Change Document (CN-007) →
CN-008
Add Second Approved Source for Composite Prepreg Material
Approved
Added a second qualified supplier to the drawing's approved-source list for the primary composite prepreg material, closing out RAIDD R-01's single-source schedule exposure (RAIDD Decision D-03).
Supplier / MaterialApproval: Meridian Program Office (Tier 3)Owner: S. Pham (Supplier Quality Eng.)Target/Decided: Nov 19, 2026
RAIDD R-01, D-03
View Full Change Document (CN-008) →
CN-009
Accept deviation to ship panels with porosity above drawing limit
Declined
Declined. The porosity limit is a design allowable tied to the stress substantiation, not an inspection convention — a deviation would change what the part is qualified to carry. MRB rework authorized instead and the delivery slot renegotiated.
Quality / Material ReviewApproval: Meridian Program Office (Tier 1)Owner: C. Okwuosa (Production, Shift 2)Target/Decided: Dec 14, 2026
MRB LogFAI Checklist
View Full Change Document (CN-009) →
CN-010
Reduce first article inspection to AQL sampling on dimensional characteristics
Declined
Declined. AS9102 FAI verifies every characteristic once, before process capability is established — sampling assumes the stability the FAI exists to prove. Four of the nine days recovered by parallelizing CMM programming with tooling proveout.
Quality / ProcessApproval: QA + Meridian Program OfficeOwner: R. Kessler (Engineering)Target/Decided: Jan 20, 2027
FAI ChecklistControl Plan
View Full Change Document (CN-010) →
CN-011
Install automated ultrasonic scanning cell for in-process NDT
Deferred
Deferred, not declined. Technical case accepted; the cell could not be NADCAP-qualified before this build concludes, so its benefit accrues to follow-on work while its disruption lands here. Business case handed to capital planning rather than closed.
Capital / ProcessApproval: Meridian Program Office (Tier 3)Owner: S. Pham (Supplier Quality Eng.)Target/Decided: Feb 16, 2027
RAIDD R-01Control Plan
View Full Change Document (CN-011) →
Reference

How to Use This Log