Change Control Detail

Download All 8 (Word)

Full detail document for each of the 8 changes logged on the Change Control Log — description, justification, impact, and approval authority for each.

CN-001

Correct Part Marking Specification Reference

CategoryDocumentation / AdministrativeRequested ByH. Lindgren (Doc Control)
Date SubmittedJun 8, 2026Date DecidedJun 15, 2026
Approval AuthorityAcme Internal (Tier 1) — C. Tyrrell

Description: A drawing reference number in the part marking specification pointed to a superseded engineering revision letter. No change to the physical marking requirement — the correction is purely to the document reference.

Justification: Caught during a routine document-control audit; left uncorrected, it risked confusion for future engineering changes referencing the wrong baseline revision.

Impact: None to cost, schedule, or the physical part.

Approved
CN-002

Clarify Edge-Trim Tolerance Callout

CategoryDocumentation / AdministrativeRequested ByR. Kessler (Quality Eng. Lead)
Date SubmittedAug 2, 2026Date DecidedAug 9, 2026
Approval AuthorityAcme Internal (Tier 1) — R. Kessler

Description: First Article Inspection found the edge-trim tolerance callout ambiguous between two adjacent drawing views (top view vs. section view showed the tolerance zone slightly differently). Wording clarified; the actual tolerance value did not change.

Justification: Ambiguous callouts risk inconsistent interpretation between inspectors on different shifts.

Impact: None to cost or schedule. Directly informed the standard used at First Article Inspection.

Approved
CN-003

Revise FAI Checklist Acceptance Criteria Wording

CategoryDocumentation / AdministrativeRequested ByR. Kessler (Quality Eng. Lead)
Date SubmittedAug 12, 2026Date DecidedAug 19, 2026
Approval AuthorityAcme Internal (Tier 1) — R. Kessler

Description: The customer source-inspection auditor flagged 2 acceptance criteria on the FAI checklist as ambiguous (see RAIDD Issue I-04). The checklist was revised with unambiguous pass/fail criteria and re-issued for all subsequent article runs.

Justification: Ambiguous acceptance criteria risk inconsistent FAI results across future units.

Impact: None to cost or schedule. See RAIDD Issue I-04 for the originating finding.

Approved
CN-004

Update Program Baseline for Corrected Staffing Model

CategorySchedule / ResourceRequested ByC. Tyrrell (Program Manager)
Date SubmittedSep 21, 2026Date DecidedSep 28, 2026
Approval AuthorityExecutive Sponsor (Tier 2) — G. Talmadge

Description: Formalized the correction of the delivery team from a 14-person, single-shift estimate to a 25-person, two-shift team into the program's standing resource and schedule baseline, ahead of Phase 2 production ramp.

Justification: The original staffing estimate was insufficient to run real steady-state two-shift production — see RAIDD Risk R-07 and Decision D-05 for the full record.

Impact: Program budget corrected from $3,500,000 to $5,200,000. See the Resource Plan and Program Budget for full detail.

Approved
CN-005

Approve Immersion Ultrasonic Testing as Alternate NDT Method

CategoryEngineering Change (ECN)Requested ByL. Vance (Materials/NDT Eng.)
Date SubmittedSep 25, 2026Date DecidedOct 7, 2026
Approval AuthorityMeridian Program Office (Tier 3)

Description: Added immersion ultrasonic testing as a Meridian-approved alternate inspection method to contact UT on the engineering drawing's NDT callout, with no change to acceptance criteria.

Justification: Supports the corrected two-shift NDT staffing model (2 Level II technicians) with a method better suited to sustained two-shift throughput; addresses the NDT queue backlog recorded in RAIDD Issue I-02.

Impact: No change to cost or acceptance criteria. Requires Meridian approval since NDT method is a drawing callout, not an internal Acme process choice.

Approved
CN-006

Revise Layup Fixture Preventive Maintenance Schedule

CategoryProcess / ToolingRequested ByM. Osei (Manufacturing Eng.)
Date SubmittedDec 2, 2026Date DecidedDec 11, 2026
Approval AuthorityAcme Internal (Tier 2) — Program Review Board

Description: Root cause corrective action following MRB-004 (ply misalignment traced to layup fixture wear) — added a standing preventive-maintenance schedule for the fixture. No change to the part or its acceptance criteria.

Justification: Prevents recurrence of the same root cause on future production runs. See the Material Review Board log for MRB-004.

Impact: Minor recurring maintenance cost, absorbed within existing tooling/maintenance budget lines — no baseline change.

Approved
CN-007

Add Repair Limits Table for Oversized Fastener Holes

CategoryEngineering Change (ECN)Requested ByR. Kessler (Quality Eng. Lead)
Date SubmittedDec 15, 2026Date DecidedJan 5, 2027
Approval AuthorityMeridian Program Office (Tier 3)

Description: Formalized the rework disposition already used in MRB-001 and MRB-003 into a standing repair-limits table on the engineering drawing, so future oversized-fastener-hole findings within the approved range don't each require a fresh MRB rework disposition.

Justification: Reduces repeat MRB cycle time for a known, bounded, already-precedented finding. See the Material Review Board log for MRB-001 and MRB-003.

Impact: No cost impact; reduces future MRB cycle time for this specific finding type. Requires Meridian approval since it changes the accepted repair envelope on the engineering drawing.

Approved
CN-008

Add Second Approved Source for Composite Prepreg Material

CategorySupplier / MaterialRequested ByS. Pham (Supplier Quality Eng.)
Date SubmittedOct 28, 2026Date DecidedNov 19, 2026
Approval AuthorityMeridian Program Office (Tier 3)

Description: Added a second qualified supplier to the engineering drawing's approved-source list for the primary composite prepreg material.

Justification: Closes out the single-source schedule exposure recorded as RAIDD Risk R-01 (score 9, High/High) — see RAIDD Decision D-03 for the full record.

Impact: No change to the current program budget; qualification cost was scoped separately. Requires Meridian approval since the approved-source list is part of the engineering drawing baseline.

Approved
CN-009

Accept Deviation to Ship Panels With Porosity Above Drawing Limit

CategoryQuality / Material ReviewRequested ByC. Okwuosa (Production, Shift 2)
Date SubmittedDec 4, 2026Date DecidedDec 14, 2026
Approval AuthorityMeridian Program Office (Tier 1) — declined

Description: Requested a one-time deviation permitting delivery of eleven panels showing ultrasonic porosity indications marginally above the drawing's acceptance limit, to protect the December delivery slot.

Justification as submitted: Rework routes the panels through a four-week cure and inspection cycle and forfeits the slot. The indications are marginal and localized away from the primary load path.

Impact: Approving would have held the delivery slot and avoided roughly $310,000 of rework. It would also have delivered primary structure outside the substantiated allowable.

Basis of decision: The porosity limit on this drawing is not an inspection convention; it is a design allowable tied to the stress substantiation Meridian certified against. Accepting a deviation on primary structure without re-substantiation does not waive an inspection — it silently changes what the part is qualified to carry, and moves that question onto the customer's certification basis. A deviation is not a shortcut around an allowable; it is a request to change what the part is qualified to do. The MRB rework route was authorized instead and the slot was renegotiated.

Conditions for re-raise: Re-raisable only with stress re-substantiation for the as-built condition, endorsed by Meridian engineering. A commercial argument alone will be declined again.

Declined
CN-010

Reduce First Article Inspection to AQL Sampling on Dimensional Characteristics

CategoryQuality / ProcessRequested ByR. Kessler (Engineering)
Date SubmittedJan 9, 2027Date DecidedJan 20, 2027
Approval AuthorityQuality Assurance + Meridian Program Office — declined

Description: Requested that the FAI dimensional verification move from 100% of characteristics to an AQL sampling plan, to reduce first-article cycle time by an estimated nine days per configuration.

Justification as submitted: The dimensional inspection load on a 412-characteristic ballooned drawing is the largest single contributor to first-article cycle time, and the process has demonstrated capability.

Impact: Approving would have recovered roughly nine days per configuration across three remaining configurations. It would also have left an unknown subset of characteristics unverified at first article.

Basis of decision: AS9102 first article inspection exists precisely to verify every characteristic once, on the first part produced by the production process, before capability has been demonstrated on that process. Sampling assumes the stable process that the FAI is the instrument for establishing. An FAI you sample is not a first article inspection; it is a first article estimate. Cycle time was addressed instead by parallelizing CMM programming with tooling proveout, recovering four of the nine days.

Conditions for re-raise: Re-raise for delta FAI on configuration changes, where prior full verification exists and AS9102 already permits a reduced scope. Full-FAI sampling is not re-raisable.

Declined
CN-011

Install Automated Ultrasonic Scanning Cell for In-Process NDT

CategoryCapital / ProcessRequested ByS. Pham (Supplier Quality Eng.)
Date SubmittedFeb 2, 2027Date DecidedFeb 16, 2027
Approval AuthorityMeridian Program Office (Tier 3) — deferred

Description: Requested capital funding for an automated immersion ultrasonic scanning cell to replace manual hand-scan NDT on composite panels.

Justification as submitted: Manual scanning is the inspection bottleneck and carries operator-to-operator variability that shows up as re-scan volume.

Impact: The technical case is accepted. The cell requires capital approval outside program authority, and NADCAP qualification of the new process would complete after the current build concludes.

Basis of decision: Deferred on timing, not merit. The cell would not be qualified in time to inspect any panel on this contract, so its benefit accrues entirely to follow-on work while its disruption lands on this one. Deferring a good request is not the same as declining it — the business case was written up and handed to the capital planning cycle rather than closed out, and the re-scan variability data was retained as its evidence base.

Conditions for re-raise: Re-raise at the capital planning cycle for the follow-on contract, with the re-scan variability data as the benefit case. Re-raise immediately if the current build extends past the qualification window.

Deferred