← Aerospace Suite Execution & Change Governance

Change Control Detail

Download All 8 (Word)

Full detail document for each of the 8 changes logged on the Change Control Log — description, justification, impact, and approval authority for each.

CN-001

Correct Part Marking Specification Reference

CategoryDocumentation / AdministrativeRequested ByH. Lindgren (Doc Control)
Date Submitted08 Jun 2026Date Decided15 Jun 2026
Approval AuthorityAcme Internal (Tier 1) — C. Tyrrell

Description: A drawing reference number in the part marking specification pointed to a superseded engineering revision letter. No change to the physical marking requirement — the correction is purely to the document reference.

Justification: Caught during a routine document-control audit; left uncorrected, it risked confusion for future engineering changes referencing the wrong baseline revision.

Impact: None to cost, schedule, or the physical part.

Approved
CN-002

Clarify Edge-Trim Tolerance Callout

CategoryDocumentation / AdministrativeRequested ByR. Kessler (Quality Eng. Lead)
Date Submitted02 Aug 2026Date Decided09 Aug 2026
Approval AuthorityAcme Internal (Tier 1) — R. Kessler

Description: First Article Inspection found the edge-trim tolerance callout ambiguous between two adjacent drawing views (top view vs. section view showed the tolerance zone slightly differently). Wording clarified; the actual tolerance value did not change.

Justification: Ambiguous callouts risk inconsistent interpretation between inspectors on different shifts.

Impact: None to cost or schedule. Directly informed the standard used at First Article Inspection.

Approved
CN-003

Revise FAI Checklist Acceptance Criteria Wording

CategoryDocumentation / AdministrativeRequested ByR. Kessler (Quality Eng. Lead)
Date Submitted12 Aug 2026Date Decided19 Aug 2026
Approval AuthorityAcme Internal (Tier 1) — R. Kessler

Description: The customer source-inspection auditor flagged 2 acceptance criteria on the FAI checklist as ambiguous (see RAIDD Issue I-04). The checklist was revised with unambiguous pass/fail criteria and re-issued for all subsequent article runs.

Justification: Ambiguous acceptance criteria risk inconsistent FAI results across future units.

Impact: None to cost or schedule. See RAIDD Issue I-04 for the originating finding.

Approved
CN-004

Update Program Baseline for Corrected Staffing Model

CategorySchedule / ResourceRequested ByC. Tyrrell (Program Manager)
Date Submitted21 Sep 2026Date Decided28 Sep 2026
Approval AuthorityExecutive Sponsor (Tier 2) — G. Talmadge

Description: Formalized the correction of the delivery team from a 14-person, single-shift estimate to a 25-person, two-shift team into the program's standing resource and schedule baseline, ahead of Phase 2 production ramp.

Justification: The original staffing estimate was insufficient to run real steady-state two-shift production — see RAIDD Risk R-07 and Decision D-05 for the full record.

Impact: Program budget corrected from $3,500,000 to $5,200,000. See the Resource Plan and Program Budget for full detail.

Approved
CN-005

Approve Immersion Ultrasonic Testing as Alternate NDT Method

CategoryEngineering Change (ECN)Requested ByL. Vance (Materials/NDT Eng.)
Date Submitted25 Sep 2026Date Decided07 Oct 2026
Approval AuthorityMeridian Program Office (Tier 3)

Description: Added immersion ultrasonic testing as a Meridian-approved alternate inspection method to contact UT on the engineering drawing's NDT callout, with no change to acceptance criteria.

Justification: Supports the corrected two-shift NDT staffing model (2 Level II technicians) with a method better suited to sustained two-shift throughput; addresses the NDT queue backlog recorded in RAIDD Issue I-02.

Impact: No change to cost or acceptance criteria. Requires Meridian approval since NDT method is a drawing callout, not an internal Acme process choice.

Approved
CN-006

Revise Layup Fixture Preventive Maintenance Schedule

CategoryProcess / ToolingRequested ByM. Osei (Manufacturing Eng.)
Date Submitted02 Dec 2026Date Decided11 Dec 2026
Approval AuthorityAcme Internal (Tier 2) — Program Review Board

Description: Root cause corrective action following MRB-004 (ply misalignment traced to layup fixture wear) — added a standing preventive-maintenance schedule for the fixture. No change to the part or its acceptance criteria.

Justification: Prevents recurrence of the same root cause on future production runs. See the Material Review Board log for MRB-004.

Impact: Minor recurring maintenance cost, absorbed within existing tooling/maintenance budget lines — no baseline change.

Approved
CN-007

Add Repair Limits Table for Oversized Fastener Holes

CategoryEngineering Change (ECN)Requested ByR. Kessler (Quality Eng. Lead)
Date Submitted15 Dec 2026Date Decided05 Jan 2027
Approval AuthorityMeridian Program Office (Tier 3)

Description: Formalized the rework disposition already used in MRB-001 and MRB-003 into a standing repair-limits table on the engineering drawing, so future oversized-fastener-hole findings within the approved range don't each require a fresh MRB rework disposition.

Justification: Reduces repeat MRB cycle time for a known, bounded, already-precedented finding. See the Material Review Board log for MRB-001 and MRB-003.

Impact: No cost impact; reduces future MRB cycle time for this specific finding type. Requires Meridian approval since it changes the accepted repair envelope on the engineering drawing.

Approved
CN-008

Add Second Approved Source for Composite Prepreg Material

CategorySupplier / MaterialRequested ByS. Pham (Supplier Quality Eng.)
Date Submitted28 Oct 2026Date Decided19 Nov 2026
Approval AuthorityMeridian Program Office (Tier 3)

Description: Added a second qualified supplier to the engineering drawing's approved-source list for the primary composite prepreg material.

Justification: Closes out the single-source schedule exposure recorded as RAIDD Risk R-01 (score 9, High/High) — see RAIDD Decision D-03 for the full record.

Impact: No change to the current program budget; qualification cost was scoped separately. Requires Meridian approval since the approved-source list is part of the engineering drawing baseline.

Approved