RAIDD Log

Download Excel

Risks, Assumptions, Issues, Decisions, and Dependencies (RAIDD) log for the CWP-700 Composite Wing Panel Production Program, spanning Phase 1 (Qualification & First Article) and Phase 2 (Production Ramp & Steady-State). Realized risks and issues trace forward to the Lessons Learned register.

4
Risks
2
Assumptions
2
Issues
2
Dependencies
2
Decisions
IDTypeDescriptionImpactOwnerStatusLesson
R-01RiskComposite prepreg material lead time (single qualified material source) could delay Phase 1 tooling qualification.HighM. OseiMonitored — dual-source qualification initiatedLL-01
R-02RiskNDT (ultrasonic inspection) capacity may not scale with Phase 2 production rate, creating an inspection bottleneck.HighL. VanceRealized — see I-02LL-02
R-03RiskProduction tooling qualification could slip, delaying the First Article Inspection date.MediumA. WhitfieldRealized — see I-01LL-03
R-04RiskCustomer (Meridian) source inspection availability for FAI witness could bottleneck the FAI gate.MediumC. TyrrellOpen — monitoring
A-01AssumptionMeridian's engineering source data (drawings, specs, tolerances) is final and baselined at contract start; no major spec changes during Phase 1.C. TyrrellHeld — no material changes to date
A-02AssumptionComposite autoclave capacity at the Acme facility is sufficient for planned Phase 2 production rate without additional capital investment.M. OseiHeld
I-01IssueFirst Article dimensional nonconformance found on the initial tooling run (edge trim out of tolerance on 2 of 8 panel positions).HighR. KesslerDispositioned via MRB — rework, closedLL-03
I-02IssueNDT queue backlog formed during early Phase 2 ramp, adding ~4 days to panel release cycle time.MediumL. VanceMitigated — second NDT technician addedLL-02
D-01DecisionQualify a second NDT technician mid-Phase-2 rather than outsourcing ultrasonic inspection, to keep traceability in-house.R. KesslerDecidedLL-02
D-02DecisionAccept a 3-week schedule buffer in Phase 1 for tooling qualification rather than compress the FAI schedule.C. TyrrellDecidedLL-03
DEP-01DependencyMeridian source-inspection representative availability to witness the First Article Inspection.MediumC. TyrrellScheduled
DEP-02DependencyRaw-material supplier certifications (material certs, PPAP submissions) required before FAI can be scheduled.MediumS. PhamReceived

R-01 through R-04 are risks; A-01/A-02 are planning assumptions; I-01/I-02 are realized issues (both trace back to a risk above); D-01/D-02 are program decisions; DEP-01/DEP-02 are external dependencies outside Acme Aerostructures's direct control.