RAIDD Log — CWP-700

Download Excel

RAIDD = Risks, Assumptions, Issues, Dependencies, Decisions — the single log referenced throughout the Governance Model, Dashboard, and Steering Deck for the CWP-700 Composite Wing Panel Production Program, spanning Phase 1 (Qualification & First Article) and Phase 2 (Production Ramp & Steady-State). Realized risks and issues trace forward into the Lessons Learned register and, where quality-relevant, into the Material Review Board log.

7
Risks
5
Assumptions
5
Issues
5
Dependencies
6
Decisions
Risks

Risk Register

Score = Likelihood × Impact, each rated 1–3 (Low/Medium/High), for a 1–9 scale. 1–3 low · 4–6 medium · 7–9 high. The Low/Medium/High pair shown next to each score is (Likelihood/Impact).

IDRiskScoreOwnerStatusResponse
R-01Composite prepreg material lead time (single qualified material source) could delay Phase 1 tooling qualification9 (High/High)M. OseiWatchDual-source qualification initiated for the primary prepreg material; see D-03
R-02NDT (ultrasonic inspection) capacity may not scale with Phase 2 production rate, creating an inspection bottleneck6 (High/Medium)L. VanceMitigatedRealized — see I-02; a second NDT technician was qualified rather than outsourcing (D-01)
R-03Production tooling qualification could slip, delaying the First Article Inspection date6 (Medium/High)A. WhitfieldMitigatedRealized — see I-01; a 3-week schedule buffer was accepted rather than compressing the FAI schedule (D-02)
R-04Customer (Meridian) source inspection availability for FAI witness could bottleneck the FAI gate4 (Medium/Medium)C. TyrrellMonitoringFAI witness date pre-coordinated with Meridian's source inspection team 30 days out; see DEP-01
R-05Single-source fixture/tooling fabrication supplier could delay the handoff from Critical Design Review (CDR) sign-off into Phase 1 fabrication4 (Low/High)A. WhitfieldMonitoringFabrication lead time confirmed at CDR; no qualified backup supplier identified yet — flagged for the next Governance review
R-06AS9100 QMS ownership is concentrated in a single individual (R. Kessler); an unplanned absence would stall MRB dispositions and FAI sign-off3 (Low/Medium)C. TyrrellMitigatedQuality Inspector B. Solis cross-trained as backup MRB voting member per the Governance Model's succession section
R-07Original 14-person Phase 2 estimate, sized for a single production shift and one NDT resource, was insufficient to run real steady-state two-shift throughput — realized as an actual planning gap, not just a hypothetical risk6 (Medium/High)C. TyrrellMitigatedRealized — see D-05; drove the Resource Plan correction to 25 people across two shifts, reflected in the Program Budget's $5,200,000 baseline
Assumptions

Assumptions

IDAssumptionOwner
A-01Meridian's engineering source data (drawings, specs, tolerances) is final and baselined at contract start; no major spec changes during Phase 1C. Tyrrell
A-02Composite autoclave capacity at the Acme facility is sufficient for the planned Phase 2 production rate without additional capital investmentM. Osei
A-03Raw-material suppliers will deliver PPAP submissions on the agreed schedule without requiring a re-submission cycleS. Pham
A-04Meridian will route any post-CDR engineering change through a formal contract modification rather than an informal design changeC. Tyrrell
A-05The 3 manufacturing technician rotations qualified during Phase 1 will remain available at planned allocation through the full Phase 2 production rampM. Osei
Issues

Issue Log

IDIssueOwnerStatusResolutionTarget / Actual Closure
I-01First Article dimensional nonconformance found on the initial tooling run (edge trim out of tolerance on 2 of 8 panel positions)R. KesslerClosedDispositioned via MRB as rework; reworked panels re-inspected and accepted (see Material Review Board log)Closed, Phase 1
I-02NDT queue backlog formed during early Phase 2 ramp, adding roughly 4 days to the panel release cycle timeL. VanceResolvedA second NDT technician was qualified and added to the rotation, per D-01; cycle time returned to plan within 2 weeksClosed, Phase 2
I-03A brief MRB backlog held 2 nonconforming panel sets in disposition-pending status for 3 days during peak Phase 2 volumeJ. Ferraro (MRB Chair)ClosedMRB added a standing weekly session (in addition to as-needed sessions) once Phase 2 volume made the ad-hoc cadence insufficientClosed, Phase 2
I-04FAI checklist wording was found ambiguous by the customer source-inspection auditor on 2 acceptance criteria, risking inconsistent future FAI resultsR. KesslerResolvedFAI checklist (fai-checklist.xlsx) revised with unambiguous pass/fail criteria and re-issued for all subsequent article runsClosed, Phase 1
I-05A raw-material lot's PPAP submission arrived incomplete (missing one dimensional report), delaying that lot's qualification by 3 daysS. PhamClosedComplete submission received and re-reviewed; supplier notified of the completeness requirement ahead of future lotsClosed, Phase 2
Dependencies

Dependency Log

IDDependencyOwnerStatus
DEP-01Meridian source-inspection representative availability to witness the First Article InspectionC. TyrrellScheduled
DEP-02Raw-material supplier certifications (material certs, PPAP submissions) required before FAI can be scheduledS. PhamReceived
DEP-03Phase 2 production rate ramp depends on the second NDT technician (D-01) completing qualification trainingL. VanceComplete
DEP-04The new quarterly PPAP review cadence (D-04) depends on suppliers submitting quality data on the agreed scheduleS. PhamOn Track
DEP-05Phase 1 fabrication cannot begin until Meridian engineering signs off at the Critical Design Review (CDR) gateA. WhitfieldOn Track
Decisions

Decision Log

IDDecisionDecided ByDate
D-01Qualify a second NDT technician mid-Phase-2 rather than outsourcing ultrasonic inspection, to keep traceability in-houseR. KesslerFeb 11, 2027
D-02Accept a 3-week schedule buffer in Phase 1 for tooling qualification rather than compress the FAI scheduleC. TyrrellOct 2, 2026
D-03Approve dual-source qualification of the primary prepreg material rather than continuing single-source, given R-01's exposureC. Tyrrell / Meridian Program OfficeNov 19, 2026
D-04Establish a standing quarterly PPAP review cadence with key raw-material suppliers rather than an annual review, to catch quality drift earlierR. KesslerJan 7, 2027
D-05Correct the Resource Plan from a 14-person, single-shift estimate to a 25-person, two-shift team — adding a second layup shift, dedicated Autoclave/Cure and Trim & Drill Technicians, a second Level II NDT Technician, a Document Control Specialist, and an EHS & Facilities Coordinator (11 added positions, +$1,634,000 labor)C. Tyrrell / G. Talmadge (VP Operations)Sep 28, 2026
D-06Meridian Aircraft Co. issued Purchase Order Amendment PA-002, increasing the CWP-700 monthly production rate — this is genuine customer-driven demand growth, not a staffing correction for the existing rate. Program expands from 25 to 50 people: a third production shift (layup, autoclave/cure, trim & drill, NDT, quality inspection — mirroring the existing Shift 1/2 structure), a Deputy Program Manager and second Manufacturing/Supplier Quality Engineers for the larger program, and new support functions the higher throughput requires that didn't exist at the lower rate (Materials Handling/Logistics, Maintenance Technicians, Incoming Material Inspection, Packaging/Shipping, a Production Scheduler, Training Coordinator, and IT/Systems Support). Budget grows from $5,200,000 to $9,284,000.C. Tyrrell / G. Talmadge (VP Operations)Jul 3, 2027