← Aerospace Suite 05 · Reporting & Closeout

Lessons Learned Register

Download Word

Lessons Learned register for the CWP-700 Composite Wing Panel Production Program — 10 entries (8 improvement, 2 positive), each traced back to a specific risk, issue, or MRB case rather than written generically after the fact.

IDTypeLessonTraces ToRecommended Action
LL-01ImprovementSingle-source composite prepreg created schedule risk with no fallback if the material lead time slipped.Traces to R-01Qualify a second material source before FAI, not after, on future composite production programs.
LL-02ImprovementNDT capacity was sized for FAI-level throughput, not full production rate, creating a queue backlog at ramp.Traces to R-02 / I-02Size NDT staffing to the Phase 2 production rate from day one of the resource plan, not the Phase 1 rate.
LL-03ImprovementTooling qualification schedule had no buffer; the FAI nonconformance consumed the entire 3-week contingency.Traces to R-03 / I-01Build an explicit tooling-qualification buffer into the Phase 1 schedule on future programs, sized to at least one rework cycle.
LL-04ImprovementThe layup fixture had no preventive-maintenance schedule, contributing to the ply-misalignment scrap (MRB-004).Traces to MRB-004Establish a preventive-maintenance schedule for production tooling/fixtures before Phase 2 ramp, not after a scrap event.
LL-05ImprovementRaw material lot traceability gaps surfaced late, at incoming inspection, rather than at supplier qualification.Traces to DEP-02Verify supplier material-certification traceability format during PPAP qualification, before the first production lot ships.
LL-06PositiveDual NDT technician qualification, once triggered, resolved the inspection queue backlog within two weeks with no further schedule impact.Traces to D-01Keep in-house NDT qualification (vs. outsourcing) as the default mitigation for inspection capacity risk — traceability stayed fully in-house.
LL-07PositiveThe FAI rework-and-reinspect path (MRB-001) kept the program on schedule instead of a full FAI failure and restart.Traces to I-01Build the MRB disposition path into the FAI schedule contingency by design, not as an exception path.
LL-08ImprovementCustomer source-inspection scheduling for the FAI gate review was arranged reactively, close to the actual FAI date.Traces to R-04 / DEP-01Request the customer source-inspection date at the same time the FAI schedule is baselined, not once FAI is imminent.
LL-09ImprovementMandatory customer notification timing for major/structural nonconformances was not written down until mid-program.Traces to Comms PlanDocument contractual nonconformance-notification timing (e.g., 24-hour window) in the Communications Plan from day one, not after the first case.
LL-10PositiveUndrawn program management reserve ($150,000) reflects that risk mitigations (dual NDT source, tooling buffer) were sized appropriately, not that risks didn't materialize — both R-02 and R-03 did.Traces to Closeout ReportReserve sizing methodology (fund the mitigation, not just the reserve) is worth carrying forward to the next production program.

This register feeds directly into the Closeout Report and is the input Acme's next composite production program would start from — most directly LL-01, LL-02, and LL-03, which all point to the same underlying pattern: Phase 1 planning sized for FAI, not for the Phase 2 production rate.