Program closeout report for the CWP-700 Composite Wing Panel Production Program — final schedule, budget, and quality performance against the original charter, and the formal handoff to Meridian Aircraft Co.'s steady-state production support.

Final Performance vs. Charter

Success CriterionResult
FAI accepted by Meridian source inspection within Phase 1 scheduleMet — accepted after one rework cycle (MRB-001), within the 3-week schedule buffer
Phase 2 production ramps to full contracted rate on timeMet
Zero repeat nonconformances of the same root causeMet — MRB-004's root cause (fixture wear) resolved via preventive maintenance, no repeat
Program closes within $9,284,000 total budget (corrected from an original $3,500,000 / 14-person estimate, then grown via RAIDD D-06 to 50 people), $0 variance on baselineMet — see final reconciliation below

Final Budget Reconciliation

LineBudgetActualVariance
Total Labor (50-person team, corrected from 14 via D-05 then D-06)$7,971,000$7,971,000$0
Total Non-Labor$930,000$930,000$0
Program Management Reserve$383,000$0 (undrawn)$383,000 returned
Total Program Cost$9,284,000$8,901,000$383,000 under budget

The $3,500,000 / 14-person original estimate priced enough leadership and engineering oversight to run governance and a single layup cell, but not enough to run real steady-state two-shift production. The Resource Plan was corrected to a 25-person team (second layup shift, dedicated Autoclave/Cure and Trim & Drill Technicians, redundant NDT capacity, Document Control, and EHS) before Phase 2 began — see Resource Plan and RAIDD Decision D-05. The team grew again, to 50, once Meridian's Purchase Order Amendment PA-002 added a third production shift later in the program (RAIDD Decision D-06) — genuine customer-driven demand growth, not a repeat correction.

Quality Summary

5 Material Review Board cases across the program (1 rework at FAI, 2 rework, 1 scrap, 1 return-to-supplier) — see the full MRB log. All findings and their corrective actions are captured in the Lessons Learned register for the next production program.

Handoff

Steady-state production support transitions from the program team to Acme Aerostructures's standing production quality organization. R. Kessler remains available for any customer escalation during the transition window; J. Ferraro's MRB chair responsibilities transfer to the standing production Quality Review Board.