Program Closeout Report

Download Word

Program closeout report for the CWP-700 Composite Wing Panel Production Program — final schedule, budget, and quality performance against the original charter, and the formal handoff to Meridian Aircraft Co.'s steady-state production support.

Final Performance vs. Charter

Success CriterionResult
FAI accepted by Meridian source inspection within Phase 1 scheduleMet — accepted after one rework cycle (MRB-001), within the 3-week schedule buffer
Phase 2 production ramps to full contracted rate on timeMet
Zero repeat nonconformances of the same root causeMet — MRB-004's root cause (fixture wear) resolved via preventive maintenance, no repeat
Program closes within $3,500,000 total budget, $0 varianceMet — see final reconciliation below

Final Budget Reconciliation

LineBudgetActualVariance
Total Labor$2,710,000$2,710,000$0
Total Non-Labor$640,000$640,000$0
Program Management Reserve$150,000$0 (undrawn)$150,000 returned
Total Program Cost$3,500,000$3,350,000$150,000 under budget

Quality Summary

5 Material Review Board cases across the program (1 rework at FAI, 2 rework, 1 scrap, 1 return-to-supplier) — see the full MRB log. All findings and their corrective actions are captured in the Lessons Learned register for the next production program.

Handoff

Steady-state production support transitions from the program team to Acme Aerostructures's standing production quality organization. R. Kessler remains available for any customer escalation during the transition window; J. Ferraro's MRB chair responsibilities transfer to the standing production Quality Review Board.