Program Resource Plan

Download Excel Download Word

Named delivery-team roster for the CWP-700 Composite Wing Panel Production Program, showing FTE allocation, location, blended hourly rate, and period labor cost — reconciled line-for-line to the Program Budget's Labor line for both the Qualification/First Article phase and the Production Ramp & Steady-State phase.

Staffing note: Acme Aerostructures is the Tier 1 supplier of record; all roles are Acme Aerostructures employees onshore at the production facility, plus periodic on-site source inspection by Meridian Aircraft Co. quality representatives (not billed to this program).

Phase 1 — Qualification & First Article (6 months)

NameRoleLocationFTE %Phase HoursBlended RatePhase Cost
C. TyrrellProgram ManagerOnshore (US)100%1,040$115.38$120,000
R. KesslerQuality Engineering Lead (AS9100 QMS Owner)Onshore (US)100%1,040$105.77$110,000
M. OseiManufacturing EngineerOnshore (US)100%1,040$96.15$100,000
L. VanceMaterials / NDT EngineerOnshore (US)80%832$108.17$90,000
A. Whitfield Phase 1 onlyTooling EngineerOnshore (US)100%1,040$86.54$90,000
S. PhamSupplier Quality Engineer (PPAP)Onshore (US)60%624$96.15$60,000
D. OkaforProgram CoordinatorOnshore (US)50%520$76.92$40,000
K. RutherfordManufacturing Technician (Composite Layup)Onshore (US)100%1,040$67.31$70,000
B. SolisQuality InspectorOnshore (US)100%1,040$72.12$75,000
Total Phase 1 Labor$755,000

Phase 2 — Production Ramp & Steady-State (12 months)

NameRoleLocationFTE %Phase HoursBlended RatePhase Cost
C. TyrrellProgram ManagerOnshore (US)100%2,080$115.38$240,000
R. KesslerQuality Engineering Lead (AS9100 QMS Owner)Onshore (US)100%2,080$105.77$220,000
M. OseiManufacturing EngineerOnshore (US)100%2,080$96.15$200,000
L. VanceMaterials / NDT EngineerOnshore (US)50%1,040$115.38$120,000
J. Ferraro Phase 2 onlyMRB Chair / Sr. Quality EngineerOnshore (US)40%832$108.17$90,000
S. PhamSupplier Quality Engineer (PPAP)Onshore (US)100%2,080$72.12$150,000
D. OkaforProgram CoordinatorOnshore (US)50%1,040$76.92$80,000
K. RutherfordManufacturing Technician (Composite Layup)Onshore (US)100%2,080$72.12$150,000
B. SolisQuality InspectorOnshore (US)100%2,080$76.92$160,000
T. Alvarado Phase 2 onlyManufacturing Technician (Composite Layup)Onshore (US)100%2,080$72.12$150,000
C. Okwuosa Phase 2 onlyManufacturing Technician (Composite Layup)Onshore (US)100%2,080$72.12$150,000
N. Vasquez Phase 2 onlyQuality InspectorOnshore (US)100%2,080$76.92$160,000
R. Bianchi Phase 2 onlyBuyer / Procurement SpecialistOnshore (US)60%1,248$68.11$85,000
Total Phase 2 Labor$1,955,000

Reconciliation to Program Budget

PhaseResource Plan TotalProgram Budget (Labor)Variance
Phase 1 — Qualification & First Article$755,000$755,000$0
Phase 2 — Production Ramp & Steady-State$1,955,000$1,955,000$0
Total Labor$2,710,000$2,710,000$0

Blended Hourly Rate is a fully loaded internal cost-recovery rate — salary, fringe, overhead, and G&A — not a billing rate to Meridian Aircraft Co.. J. Ferraro (MRB Chair) is added at the start of Phase 2 as production volume creates a steady stream of nonconformances requiring formal disposition; A. Whitfield (Tooling Engineer) rolls off at the end of Phase 1 once production tooling is qualified and released.

See the Work Breakdown Structure for how each of these 14 people's time maps to specific, dated tasks — not just FTE% and cost.