Resource-Loaded WBS

Download Word

This is the resource-loaded view of the CWP-700 Work Breakdown Structure. Every work package carries its named effort and cost, every hour traces to a named person on the Resource Plan, and effort is split by program phase — because Phase 1 and Phase 2 are not merely earlier and later, they are staffed by different people doing different work.

79
WBS line items
68
Loaded work packages
50
Named resources
312
Assignments
100,568
Total effort (h)

01 How this WBS is loaded

Each work package names one accountable owner plus the named contributors who perform the work. On a production program that distinction is unusually literal: the engineer who owns a work package is rarely the person whose hands are on the part. A layup work package is owned by a manufacturing engineer and performed by composite layup technicians across shifts, and a resource-loaded WBS that recorded only the owner would account for a fraction of the labour actually consumed.

The loading is allocation-aware: each person's hours come from their Resource Plan line, which carries their FTE percentage — and these vary (100%, 80%, 60%, 50%, 40%). Hours are then distributed across the packages they work on in proportion to package duration.

Cost is distributed, not recomputed. Blended rates are rounded for presentation, so rate × hours drifts from the stated cost by a few dollars per person. Each person's stated cost is allocated instead, so the roll-up ties to the Program Budget exactly rather than approximately.

02 Effort & cost by phase

PhaseScopeResourcesPackagesEffort (h)Labor cost
Phase 1Qualification & First Article (6 months)9318,216$755,000
Phase 2Production Ramp & Steady-State (12 months)493792,352$7,216,000
Total18 months5068100,568$7,971,000
Phase 2 is not simply "more of Phase 1". Phase 1 runs with 9 people proving the process can make a conforming part; Phase 2 runs with 49 proving it can make them repeatedly and at rate. That is a 9.6× cost step and an almost entirely different team — which is exactly why the original 14-person estimate was wrong in kind rather than merely low, and why decision D-06 corrected NDT capacity that had been sized against the wrong phase. A. Whitfield (Tooling Engineer) appears in Phase 1 only, and any reading of the roster that takes the Phase 2 table alone silently loses them — the merge of both phase tables is what gives the true 50-person program team.

03 Reconciliation

CheckValueResult
Phase 1 distributed effort / cost8,216 h / $755,000= Resource Plan Phase 1 total ✓
Phase 2 distributed effort / cost92,352 h / $7,216,000= Resource Plan Phase 2 total ✓
Combined100,568 h / $7,971,000= Program Budget labor, $0 variance ✓
Per-resource, per-phase50 of 50each equals that person's roster line exactly ✓

These are assertions the generator evaluates, not totals typed into a table — it refuses to emit this page if any fails. The $7,971,000 reconciled here is the same labor line that appears in the Program Charter's authorized budget.

04 Effort & cost by work stream

WBSWork streamPackagesEffort (h)Labor cost
1.1Tooling design & fabrication81,484$132,617
1.2Material qualification (PPAP)6923$82,859
1.3Initial production run & inspection113,311$290,000
1.4MRB-001 disposition & re-inspection51,434$127,620
1.5Milestone Gate: FAI Accepted11,064$121,904
2.1Production release authorization18$1,002
2.2Composite layup production939,134$2,853,263
2.3In-process inspection & NDT615,528$1,351,672
2.4MRB case management81,658$179,502
2.5Supplier quality & procurement916,141$1,131,787
2.6Preventive maintenance program (layup fixture, post MRB-004)12,802$271,349
2.7Program status reporting217,019$1,420,400
2.8Milestone: Program Closeout162$7,025

05 Resource loading by person

ResourceRoleFTE %PhasesHoursCostPkgs
C. TyrrellProgram Manager100% / 100%Both phases3,120$360,0004
R. KesslerQuality Engineering Lead (AS9100 QMS Owner)100% / 100%Both phases3,120$330,00024
M. OseiManufacturing Engineer100% / 100%Both phases3,120$300,0004
B. SolisQuality Inspector100% / 100%Both phases3,120$235,0004
D. MarchettiDeputy Program Manager100%Phase 2 only2,080$220,0004
K. RutherfordManufacturing Technician (Composite Layup)100% / 100%Both phases3,120$220,0007
L. VanceMaterials / NDT Engineer80% / 50%Both phases1,872$210,0005
S. PhamSupplier Quality Engineer (PPAP)60% / 100%Both phases2,704$210,0008
T. WinslowManufacturing Engineer100%Phase 2 only2,080$200,00015
B. WinfieldNDT Technician, Level II, Shift 3100%Phase 2 only2,080$180,0001
K. SorensenNDT Technician, Level II, Shift 2100%Phase 2 only2,080$180,0001
R. AchebeNDT Technician, Level II, Shift 1100%Phase 2 only2,080$180,0001
G. OchoaMaintenance Technician100%Phase 2 only2,080$164,0006
H. WinthropMaintenance Technician100%Phase 2 only2,080$164,0006
E. SolbergAutoclave / Cure Technician, Shift 3100%Phase 2 only2,080$160,0009
L. SheffieldProduction Scheduler / Planner100%Phase 2 only2,080$160,00010
M. VartanAutoclave / Cure Technician, Shift 1100%Phase 2 only2,080$160,0009
N. VasquezQuality Inspector100%Phase 2 only2,080$160,0001
P. LarsenQuality Inspector, Shift 3100%Phase 2 only2,080$160,0001
S. OkoroAutoclave / Cure Technician, Shift 2100%Phase 2 only2,080$160,0009
A. DelacroixManufacturing Technician (Composite Layup), Shift 2100%Phase 2 only2,080$150,0009
A. RestrepoSupplier Quality Engineer (PPAP)100%Phase 2 only2,080$150,0002
C. NakashimaTrim & Drill Technician, Shift 3100%Phase 2 only2,080$150,0009
C. OkwuosaManufacturing Technician (Composite Layup)100%Phase 2 only2,080$150,0002
D. HalvorsenTrim & Drill Technician, Shift 1100%Phase 2 only2,080$150,0009
J. BeaumontManufacturing Technician (Layup), Shift 3 Lead100%Phase 2 only2,080$150,0001
J. WhitbyManufacturing Technician (Composite Layup), Shift 2100%Phase 2 only2,080$150,0009
K. DelvecchioManufacturing Technician (Layup), Shift 3100%Phase 2 only2,080$150,0001
L. FontaineTrim & Drill Technician, Shift 2100%Phase 2 only2,080$150,0009
P. MensahManufacturing Technician (Composite Layup), Shift 2100%Phase 2 only2,080$150,0009
R. KowalczykManufacturing Technician (Layup), Shift 3100%Phase 2 only2,080$150,0001
T. AlvaradoManufacturing Technician (Composite Layup)100%Phase 2 only2,080$150,0002
I. SondheimIncoming Material Inspector100%Phase 2 only2,080$146,0001
W. FairweatherIncoming Material Inspector100%Phase 2 only2,080$146,0001
H. LindgrenDocument Control / Configuration Management Specialist100%Phase 2 only2,080$140,0003
Q. WhitcombDocument Control / Configuration Mgmt Specialist100%Phase 2 only2,080$140,0003
J. PackardPackaging / Shipping Technician100%Phase 2 only2,080$136,0009
K. MerchantPackaging / Shipping Technician100%Phase 2 only2,080$136,0009
M. TalbotMaterials Handling / Logistics Coordinator100%Phase 2 only2,080$136,0001
S. KandelMaterials Handling / Logistics Coordinator100%Phase 2 only2,080$136,00014
N. RedmondMRB Quality Engineer60%Phase 2 only1,248$135,0009
N. CastilloIT / Systems Support Technician80%Phase 2 only1,664$125,0002
D. OkaforProgram Coordinator50% / 50%Both phases1,560$120,0007
A. WhitfieldTooling Engineer100%Phase 1 only1,040$90,0006
J. FerraroMRB Chair / Sr. Quality Engineer40%Phase 2 only832$90,0008
L. PrescottBuyer / Procurement Specialist60%Phase 2 only1,248$85,0001
R. BianchiBuyer / Procurement Specialist60%Phase 2 only1,248$85,0001
M. AinsleyTraining Coordinator60%Phase 2 only1,248$84,00015
V. CastellanosEHS & Facilities Coordinator40%Phase 2 only832$64,00015
V. HalsteadEHS & Facilities Coordinator40%Phase 2 only832$64,00015
Total — 50 resources100,568$7,971,000312

06 Loaded work packages

All 68 loaded work packages with owner, contributors, phase, effort and cost. Effort is carried at work-package level only, so nothing is double-counted in the roll-ups above.

WBSWork packageOwnerContributorsPhaseEffort (h)Cost
1.1.1Tooling concept design — layup mandrelA. WhitfieldPhase 1133$11,571
1.1.2Tooling concept design — trim/drill fixtureA. WhitfieldPhase 1133$11,571
1.1.3Tooling detailed design & drawings — mandrelA. WhitfieldPhase 1163$14,142
1.1.4Tooling detailed design & drawings — trim fixtureA. WhitfieldPhase 1163$14,142
1.1.4BCritical Design Review (CDR) — internal walkthroughM. OseiD. OkaforPhase 1222$20,475
1.1.4CCritical Design Review (CDR) — Meridian engineering sign-offR. KesslerD. OkaforPhase 1222$22,142
1.1.5Tooling fabrication — machine shop, mandrelA. WhitfieldPhase 1226$19,289
1.1.6Tooling fabrication — machine shop, trim fixtureA. WhitfieldPhase 1222$19,285
1.2.1Supplier material cert review — prepreg batch dataS. PhamD. OkaforPhase 1249$20,904
1.2.2Supplier material cert review — fastener hardwareS. PhamD. OkaforPhase 1246$20,901
1.2.3PPAP sample submission — prepregS. PhamPhase 1151$14,214
1.2.4PPAP sample submission — fastenersS. PhamPhase 1147$14,210
1.2.5PPAP test & approval — prepregS. PhamPhase 165$6,315
1.2.6PPAP test & approval — fastenersS. PhamPhase 165$6,315
1.3.1Composite layup — ply cutting, S/N 0001K. RutherfordPhase 1260$17,500
1.3.2Composite layup — hand layup, S/N 0001K. RutherfordPhase 1260$17,500
1.3.3Composite layup — autoclave cure, S/N 0001K. RutherfordPhase 1130$8,750
1.3.4Composite layup — trim & drill, S/N 0001K. RutherfordPhase 1130$8,750
1.3.5NDT ultrasonic scan — S/N 0001L. VancePhase 1624$67,500
1.3.6Quality inspection — dimensional layoutB. SolisPhase 1348$25,000
1.3.7Quality inspection — visual/cosmeticB. SolisPhase 1346$25,000
1.3.8FAI full dimensional layout — CMM measurementM. OseiPhase 1521$50,001
1.3.9FAI full dimensional layout — hand-tool measurementM. OseiPhase 1346$33,333
1.3.10FAI documentation — AS9102 Form 1R. KesslerPhase 1173$18,333
1.3.11FAI documentation — AS9102 Form 2/3R. KesslerPhase 1173$18,333
1.4.1MRB-001 disposition review (edge-trim nonconformance)R. KesslerD. OkaforPhase 1447$44,287
1.4.2MRB-001 disposition decision (rework authorized)R. KesslerPhase 1173$18,333
1.4.3Rework composite panel — edge trim re-machiningK. RutherfordPhase 1260$17,500
1.4.4FAI re-inspection — dimensionalB. SolisPhase 1346$25,000
1.4.5FAI re-inspection — NDT re-scanL. VancePhase 1208$22,500
1.5Milestone Gate: FAI AcceptedC. TyrrellD. OkaforPhase 11,064$121,904
2.1Production release authorizationC. TyrrellD. MarchettiPhase 28$1,002
2.2.1Panel production — rotation A, batch 1 (S/N 0002-0017)K. RutherfordA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 24,051$294,901
2.2.2Panel production — rotation A, batch 2 (S/N 0018-0033)J. BeaumontA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 25,066$368,897
2.2.3Panel production — rotation A, batch 3 (S/N 0034-0050)K. RutherfordA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 23,935$287,309
2.2.4Panel production — rotation B, batch 1 (S/N 0051-0067)T. AlvaradoA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 24,040$294,872
2.2.5Panel production — rotation B, batch 2 (S/N 0068-0083)R. KowalczykA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 25,066$368,897
2.2.6Panel production — rotation B, batch 3 (S/N 0084-0100)T. AlvaradoA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 23,935$287,309
2.2.7Panel production — rotation C, batch 1 (S/N 0101-0117)C. OkwuosaA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 24,040$294,872
2.2.8Panel production — rotation C, batch 2 (S/N 0118-0133)K. DelvecchioA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 25,066$368,897
2.2.9Panel production — rotation C, batch 3 (S/N 0134-0150)C. OkwuosaA. Delacroix, C. Nakashima, D. Halvorsen, E. Solberg, J. Packard, J. Whitby +11 morePhase 23,935$287,309
2.3.1NDT ultrasonic scan — rotation A panelsR. AchebeL. Vance, R. KesslerPhase 22,836$262,319
2.3.2NDT ultrasonic scan — rotation B panelsK. SorensenL. Vance, R. KesslerPhase 22,826$262,307
2.3.3NDT ultrasonic scan — rotation C panelsB. WinfieldL. Vance, R. KesslerPhase 22,826$262,307
2.3.4Dimensional/visual inspection — rotation A & BB. SolisR. KesslerPhase 22,280$181,216
2.3.5Dimensional/visual inspection — rotation CN. VasquezR. KesslerPhase 22,280$181,216
2.3.6Monthly inspection metrics rollupP. LarsenR. KesslerPhase 22,480$202,307
2.4.1MRB-002 review — surface porosity findingJ. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.4.2MRB-002 disposition (use-as-is)J. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.4.3MRB-003 review — oversized fastener hole findingJ. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.4.4MRB-003 disposition (rework, oversized fastener)J. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.4.5MRB-004 review — ply misalignment findingJ. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.4.6MRB-004 disposition (scrap) & root-cause investigationJ. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.4.7MRB-005 review — material traceability gapJ. FerraroH. Lindgren, N. Redmond, Q. Whitcomb, R. KesslerPhase 2223$23,507
2.4.8MRB-005 disposition (return-to-supplier)J. FerraroN. Redmond, R. KesslerPhase 2205$22,285
2.5.1Supplier PPAP maintenance — quarterly review Q1S. PhamG. Ochoa, H. Winthrop, M. Ainsley, R. Kessler, T. Winslow, V. Castellanos +1 morePhase 21,166$85,801
2.5.2Supplier PPAP maintenance — quarterly review Q2A. RestrepoG. Ochoa, H. Winthrop, M. Ainsley, R. Kessler, T. Winslow, V. Castellanos +1 morePhase 21,166$85,801
2.5.3Supplier PPAP maintenance — quarterly review Q3S. PhamG. Ochoa, H. Winthrop, M. Ainsley, R. Kessler, T. Winslow, V. Castellanos +1 morePhase 21,166$85,801
2.5.4Supplier PPAP maintenance — quarterly review Q4A. RestrepoG. Ochoa, H. Winthrop, M. Ainsley, R. Kessler, T. Winslow, V. Castellanos +1 morePhase 21,166$85,801
2.5.5Incoming lot verification — prepreg (ongoing)W. FairweatherS. KandelPhase 22,457$170,306
2.5.6Incoming lot verification — fasteners (ongoing)I. SondheimS. KandelPhase 22,451$170,300
2.5.7Purchase order execution — prepreg replenishmentR. BianchiS. KandelPhase 21,541$104,184
2.5.8Purchase order execution — fastener replenishmentL. PrescottS. KandelPhase 21,541$104,184
2.5.9Supplier scheduling & delivery coordinationM. TalbotL. Sheffield, S. KandelPhase 23,487$239,609
2.6Preventive maintenance program (layup fixture, post MRB-004)M. OseiG. Ochoa, H. Winthrop, M. Ainsley, N. Redmond, R. Kessler, T. Winslow +2 morePhase 22,802$271,349
2.7.1RAIDD log maintenance & weekly reviewD. OkaforD. Marchetti, G. Ochoa, H. Lindgren, H. Winthrop, M. Ainsley, N. Castillo +4 morePhase 211,056$875,269
2.7.2Program status report — monthly cadenceC. TyrrellD. Marchetti, H. Lindgren, N. Castillo, Q. WhitcombPhase 25,963$545,131
2.8Milestone: Program CloseoutC. TyrrellD. MarchettiPhase 262$7,025