Task Order Dashboard · Portfolio Demo

BenefitConnect Portal Modernization

Task Order PMC. Tyrrell
Status As OfOct 16, 2026 · Month 5 of 18
PhaseBuild & Compliance Testing
Overall HealthAmber
Download PowerPoint
Exec Summary

Task Order Health at a Glance

BenefitConnect Portal Modernization is at Month 5 of 18, in Build & Compliance Testing. Five CDRL data items have been accepted (A001 Project Management Plan, A002 IMS Baseline, A003 Risk Management Plan, A004 Section 508 Test Plan, A005 System Security Plan); A009 Data Migration Plan & Validation Report was submitted on its 15 Oct due date and is under COR review; A008 Monthly Status Report is current on cadence. The Task Order is currently Amber overall due to R-01 — the ATO Security Assessment carries a 9 (High/High) risk score, since any finding there cascades directly into Milestone Gate 1 (Dec 14, 2026), now eight weeks out. The get-to-Green strategy is a pre-assessment scan run 60 days ahead of formal ATO submission specifically to surface findings early, with a POA&M template pre-staged so any finding has a same-day remediation path — plus the D-03 decision to pursue a phased ATO for lower-risk components rather than holding all functionality for one gate. The scan window opens Oct 15, 2026; results are the single biggest determinant of whether this Task Order returns to Green. No change to the Milestone Gate 1 target is being proposed at this time. The delivery team reached its full 35-person strength in Month 4 following Mod P00011, which added $4,040,000 of scope in Month 2 and is the reason spend (25.7%) sits below time elapsed (27.6%) rather than above it.

Overall Status
Amber
ATO schedule risk (R-01), 9 (High/High)
Watch
Schedule
Month 5 of 18
5 of 10 CDRLs accepted, all on time; A009 under review
On track
Budget (FFP)
~25.7%
$1,980,000 of $7,704,000 incurred vs 27.6% elapsed
On track
Security / ATO
1
R-01 open, unmitigated pending pre-assessment scan
Monitor
Accessibility (508)
On Plan
A004 accepted; VPAT test cycle prep for A006 (14 Nov)
On plan

Milestone Timeline Kickoff → Closeout

Task Order Kickoff
May 18, 2026
PMP + IMS Baseline (A001/A002)
Jun 17, 2026
Section 508 Test Plan (A004)
Jul 17, 2026
System Security Plan (A005)
Aug 16, 2026
Data Migration Plan (A009)
Oct 15, 2026 · in review

Top Risks from RAIDD Log

R-01
ATO assessment surfaces a security finding that delays Milestone Gate 1 beyond Dec 14, 2026
Owner: T. Abernathy (ISSO) · Score 9 (High/High) · Mitigation: pre-assessment scan 60 days ahead of submission
R-05
All-onshore staffing constraint limits surge capacity if a developer or QA resource attrites mid-Option
Owner: D. Ferris (Deputy PM) · Score 6 (Medium/High) · Pre-cleared onshore bench candidates identified
R-02
Legacy applicant data has inconsistent formatting that complicates migration validation
Owner: K. Lindqvist · Score 6 (Medium/High) · Automated field-level profiling underway

Budget Snapshot vs. $7,704,000 current FFP value

Cost incurred to date$1,980,000
Labor baseline (full team)$6,960,000
Non-labor (508/SCA/Cloud/Data)$744,000
Value growth to date: +$4,154,000 (11 mods) FFP — no cost variance reported to FOPBA

Contract Modifications 11 processed, all Approved

11
Approved
Detail

Drill-Down: Schedule, Compliance & Resources

WBS Phase Progress 225 line items · 5 phases

1 · Task Order Authorization & Planning
100%Closed
2 · Requirements & Design
100%Closed
3 · Build & Compliance Testing
42%In progress
4 · ATO & Cutover
8%Prep only
5 · Operations & Closeout
0%Not started

RAIDD Summary Live register

CategoryCountNote
Risks61 high (R-01), 4 medium — R-04 raised to Medium/High after P00011
Assumptions54 holding; A-02 did not hold (Option exercised early — P00010)
Issues51 open (I-05, past original target — escalated to COR), 4 resolved/closed
Decisions4All approved
Dependencies51 at risk (DEP-01), 4 on track

Compliance Readiness

TrackOwnerStatus
Section 508 / VPATP. DuvallA004 accepted 17 Jul; VPAT test cycle prep for A006
ATO Security AssessmentT. AbernathyA005 SSP accepted 16 Aug; pre-assessment scan window opens 15 Oct
Third-Party Security Assessment (SCA)T. AbernathyQueued

Resource Utilization Base Period FTE% — original 13-person core

Shows the 13 roles awarded at Task Order kickoff. The 22 roles added by Mod P00011 reached full allocation in Month 4 and are listed in the Resource Plan (35 named resources).

C. TyrrellTask Order PM
100%
D. FerrisDeputy PM
100%
K. LindqvistSolutions Architect
100%
T. AbernathyISSO
100%
P. DuvallSection 508 Lead
60%
N. CastellanoQA Lead
80%
J. OkonkwoBusiness Analyst
75%
E. MarstonFront-End Developer
100%
R. ColvilleFront-End Developer
100%
H. IbrahimBack-End Developer
100%
G. PetrovBack-End Developer
100%
S. VanceDevOps / Cloud Engineer
80%
A. ByrneQA Tester
100%