Overall
AmberSchedule
AmberBudget (FFP)
GreenSecurity / ATO
AmberAccessibility
GreenCDRL Progress (3 of 10 Accepted)
Milestone Gates
- G1 — Authority to Operate Granted: target Month 7 (tracking Amber — R-01)
- G2 — Production Go-Live: target Month 8
- Option Period decision point: Month 12
Top Risks
- R-01: ATO assessment may delay Milestone Gate 1
- R-02: Legacy data formatting complicates migration validation
Financial Snapshot
- Total FFP Value: $2,140,000
- Contract Mods Processed: 1 (P00001, +$28,000)
- 5-Yr TCO Advantage vs. Legacy: ~$35,000