← Federal Suite 04 · Execution & Reporting

Monthly Status Report — CDRL A008

Download Word

Reporting Period: Month 4 of 18 (18 Aug – Sep 17, 2026), submitted Oct 5, 2026 per the CDRL A008 cadence. The current program position is Month 5 — a monthly CDRL necessarily reports the last completed month, so this report sits one period behind the Dashboard and the Weekly Status Report by design. Submitted to M. Whitcombe (COR). This is a contractual deliverable, not just an internal update — late or incomplete submission is itself a QASP finding. This monthly CDRL rolls up from the internal Weekly Status Report cadence used to track progress between formal submissions.

Overall Status
Amber
Schedule
Amber
Budget (FFP)
Green
CDRLs Accepted
5 of 10

Accomplishments This Period

Staffing Status

All 35 Base Period roles are onboarded and at planned FTE% per the Resource Plan. The 22 roles added by Mod P00011 completed onboarding during this period; the pacing constraint was FOPBA suitability determination throughput rather than recruiting, since the all-onshore/US-persons requirement (PWS 6.1) removes any offshore surge option. No open reqs, no attrition this period.

Concerns / Risks

Upcoming Milestones (Next 60 Days)

CDRL Deliverable Status

CDRL #DeliverableStatus
A001Project Management PlanAccepted
A002Integrated Master Schedule (IMS)Accepted
A003Risk Management Plan (RAIDD baseline)Accepted
A004Section 508 Test PlanAccepted
A005System Security Plan (SSP)Accepted
A009Data Migration Plan & Validation ReportDue Oct 15, 2026 — on track
A008Monthly Status Report (this deliverable)Recurring — on cadence

Full list of all 10 CDRL items and their acceptance status is in the CDRL.

Funding & Burn Rate

Current FFP Value$7,704,000 (Base $6,376,000 + Option $1,328,000)
Cumulative Invoiced to Date$1,470,000 — 19.1% of current FFP value at Month 4, against 22.3% of the period of performance elapsed
Burn Rate vs. ScheduleTracking modestly below the straight-line mark. Mod P00011 added $4,040,000 of value in Month 2, but the 22 associated roles only reached full allocation inside this reporting period, so four months of elapsed time carry roughly two months of full-team burn. Burn rate steps up from Month 6 and is expected to converge with elapsed time by Milestone Gate 1. No re-baselining recommended
Value Remaining (all periods)$6,234,000

Action Items / Government Decisions Needed

ItemOwnerNeeded By
FOPBA IT root-cause resolution for GFE VPN latency (I-05) — escalated 27 Aug, original 15 Aug target missedM. Whitcombe (COR)Next reporting period
Confirm FOPBA business data owner availability for legacy DB2 schema review ahead of full data migrationR. Osei (Sponsor)Prior to Nov 14, 2026 migration dry run