Weekly Status Report · Portfolio Demo

BenefitConnect Portal Modernization

Task Order PMC. Tyrrell
Reporting PeriodMo. 5, Wk. 4 · w/e Oct 16, 2026
Report No.WK-22
DistributionInternal + COR (info)
Download Word
Summary

Weekly Status — At a Glance

BenefitConnect Portal Modernization is in Build & Compliance Testing at Month 5 of 18. The Task Order is currently Amber due to R-01 — the ATO Security Assessment carries a 9 (High/High) risk score, since any finding cascades directly into Milestone Gate 1 (Dec 14, 2026), now eight weeks out. This week CDRL A009 (Data Migration Plan & Validation Report) was submitted on its 15 Oct due date and the ATO pre-assessment scan window opened. No change to Milestone Gate 1 is being proposed this period. This internal weekly cadence rolls up into the formal Monthly Status Report (CDRL A008) submitted to the COR.

Overall Status
Amber
Schedule
On Track (Mo. 5)
Budget (FFP)
~25.7% Spent
Open Risks (High)
1

Accomplished This Week

  • ATO pre-assessment scan window opened — 60 days ahead of the formal A007 submission, per the R-01 mitigation plan. First automated sweep completed; findings triage begins Monday.Owner: T. Abernathy
  • CDRL A009 (Data Migration Plan & Validation Report) submitted to the COR on its 15 Oct due date, one day inside the QASP window.Owner: P. Duvall
  • Second conversion dry run completed on the full legacy applicant extract — cleansing rules held; residual exception rate down to 0.6% from 4.1% on the first run (R-02 mitigation).Owner: K. Lindqvist
  • All 22 P00011 roles confirmed at full allocation — the final two FOPBA suitability determinations cleared, closing the Month 4 ramp (R-05 bench retained).Owner: D. Ferris

Planned Next Week

  • Triage the first pre-assessment scan results and open POA&M entries for anything that will not close before A007 submission.Owner: P. Duvall
  • Open the VPAT test cycle for CDRL A006 ahead of the Nov 14, 2026 due date, with the independent auditor scheduled in.Owner: T. Abernathy
  • Escalate GFE VPN latency (I-05) at the monthly COR meeting — the original 15 Aug target was missed and it is now carried as a Government-side dependency.Owner: S. Vance
  • Respond to COR comments on A009 if returned, and schedule the third conversion dry run (R-02).Owner: K. Lindqvist
Detail

Risks & Issues Requiring Attention

IDDescriptionOwnerStatus / ActionTarget Date
R-01 ATO assessment surfaces a security finding that delays Milestone Gate 1 (Score 9, High/High) T. Abernathy Scan window opened 15 Oct; POA&M template pre-staged; findings triage begins next week Milestone Gate 1: Dec 14, 2026
R-05 All-onshore staffing constraint limits surge capacity (Score 6, Medium/High) D. Ferris Full 35-person team at allocation; pre-cleared onshore bench retained Ongoing — Option Period
R-02 Legacy applicant data formatting complicates migration validation (Score 6, Medium/High) K. Lindqvist Second dry run clean at a 0.6% exception rate; third dry run being scheduled Nov 20, 2026 (third dry run)
I-05 Intermittent VPN latency to FOPBA's GFE affecting DevOps deployment windows S. Vance Status: Open, past original target — escalated to COR 27 Aug; off-peak deployment scheduling is holding the schedule Revised: Oct 30, 2026
DEP-01 ATO package (A007) cannot submit until Section 508 report (A006) is accepted T. Abernathy Status: At Risk — sequencing tracked, no slip yet A006 target: Nov 14, 2026

Government Touchpoints This Week

InteractionGovernment ContactOutcome
CDRL A009 submission walkthrough with the COR M. Whitcombe (COR) Submitted 15 Oct; the COR review clock runs to 22 Oct per the QASP
ATO pre-assessment scan kickoff with FOPBA Security T. Abernathy (Acme ISSO) / FOPBA Security POC Scan window confirmed open 15 Oct; no change to Milestone Gate 1 timeline

Budget Health & Variance Firm-Fixed-Price

On Track
Current Period Variance
$0
FFP — FOPBA sees CDRL schedule status, not internal cost variance
Value Growth to Date
+$4,154,000 (11 mods)
$3,550,000 baseline → $7,704,000 current adjusted value

Internal Acme cost tracking (not billed line-item to FOPBA): est. $1,980,000 of $7,704,000 current value consumed — 25.7% against 27.6% of the period of performance elapsed. The slight underrun is the P00011 ramp: $4,040,000 of scope was authorized in Month 2, but the 22 added roles only reached full allocation in Month 4. Burn steps up from Month 6. No re-baselining is recommended at this time.

Roadmap

Upcoming Milestones

Task Order KickoffMay 18, 2026 ✓
PMP + IMS Baseline (A001/A002)Jun 17, 2026 ✓
Section 508 Test Plan (A004)Jul 17, 2026 ✓
System Security Plan (A005)Aug 16, 2026 ✓
Data Migration Plan (A009)Oct 15, 2026 · in review
Section 508 / VPAT Testing (A006)Nov 14, 2026
ATO Milestone Gate (A007)Dec 14, 2026
Production Go-LiveJan 13, 2027
Option Period Start (exercised early — P00010)May 18, 2027