← Stage-Gate NPD Suite Gate Package · Draft, 167 Days Before the Gate

Gate 2 Review Deck

⚠ This is a draft package, and the gaps are the point

Gate 2 convenes 01 April 2027. This package was assembled at the status date, 167 days out, and most of its evidence does not exist yet. Nothing here is padded to look finished.

Assembling a gate package early is a diagnostic, not just preparation. A package built the week before a gate can only report what happened. A package built five months early reports what will be missing if nothing changes — which is the only version anyone can still act on. Every “awaiting evidence” marker below is a live instruction to somebody.

Program timeline · status 16 Oct 2026Read the full story →
Harborline
Aug 2025
Cancelled
Gate 0
Feb 2026
Go
Stage 1
Business case
Gate 1
Apr 2026
Recycled
Gate 1
Jun 2026
Go w/ conditions
Stage 2
Development
You are here
Gate 2
Apr 2027
Gate 3
Oct 2027
Gate 4
Feb 2028
Launch
Mar 2028
Gate 5
Sep 2028

Lighthouse Financial Services Company — The package the Gate Review Board will receive at Gate 2. Program is in week 18 of 41 in Stage 2. The decision before the Board is whether to release the Stage 3 tranche of $7,450,000.

Gate 2 package — 14 slides

Draft as at 16 October 2026. Full content reproduced below.

Download PowerPoint ↓
167
Days to the gate
0 of 5
Must-meets fully evidenced
1
Must-meet at risk
$7,450,000
Tranche requested
Contents
  1. What This Gate Decides
  2. Must-Meet Criteria — Evidence State
  3. Gate 1 Conditions
  4. Scoring Worksheet — Deliberately Blank
  5. Economics
  6. The Case for CANCEL
  7. Dissent
  8. What the Chair Is Asking For

1. What This Gate Decides

Gate 2 decides whether to release $7,450,000 for Stage 3 — testing and validation, regulatory submission, and operations process build. It is the second-largest tranche in the program and the first one whose release the Board has not already effectively pre-committed by approving a business case.

Outcome availableWhat it means here
GORelease the Stage 3 tranche in full. Requires all five must-meets certified and a weighted score at or above 3.50.
GO WITH CONDITIONSRelease with named, dated, owned conditions. Requires all five must-meets certified and a score of 3.00–3.49.
RECYCLEReturn the package. Can be carried by any two members, and is mandatory if any criterion is rated U.
HOLDPause for a cause outside the program's control. Not available for causes inside it.
CANCELEnd the program and return the unspent tranche. Simple majority only — a deliberately lower bar than GO.
A must-meet failure removes GO and GO WITH CONDITIONS from the table regardless of the weighted score. The two-tier test evaluates the knockout criteria first. That is why §2 comes before §4 in this deck, and why a strong score cannot rescue MM-4.

2. Must-Meet Criteria — Evidence State

IDCriterionCertifiesStateEvidence position
MM-1Contract forms complete and cleared by outside counselB. LindqvistPartialThird GLWB redraft with counsel (I-05). Base contract cleared; rider language open.
MM-2Pricing signed, supported by the GC-03 external reviewN. AdeyemiAwaiting evidenceArdmore engaged and reporting ahead of the due date. Opinion not yet received.
MM-3Illustration output validated against the filed methodologyE. KowalczykPartialConfiguration complete for the three-strategy set; validation cycle not started.
MM-4Hedging readiness plan accepted under GC-05J. WhitmoreAt riskSecond ISDA counterparty not started (DEP-06). No float left in Stage 2 to absorb it.
MM-5All Gate 1 conditions closed or formally re-issuedC. TyrrellPartial3 of 5 closed. GC-03 on track; GC-05 at risk.
Not one of the five is fully evidenced today, and that is the expected position 167 days out. The one that matters is MM-4: hedging readiness depends on two derivatives counterparties and the second has not begun negotiation (DEP-06). Stage 2 was compressed from 46 weeks to 41 to absorb the Gate 1 recycle, so there is no float left to absorb this. On current trajectory MM-4 fails, and a must-meet failure removes GO from the table.

3. Gate 1 Conditions

IDConditionStatus
GC-01Reduce launch crediting strategies from five to threeClosed
GC-02Remove New York from launch scope and issue a deferral memorandumClosed
GC-03Independent external actuarial peer review of GLWB rider pricing before Gate 2Open
GC-04Re-validate distribution volume assumptions with the three largest IMO partnersClosed
GC-05Present a hedging readiness plan with ISDA execution milestones at Gate 2At Risk

Full verification methods, evidence and the post-closure efficacy findings are in the Gate Conditions Register. Worth carrying into the room: GC-04 was correctly specified, verified and closed — and left $17,000,000 of Year 1 volume uncommitted. Closed is not the same as resolved, and the Board should not read “3 of 5 closed” as 60% of a problem solved.

4. Scoring Worksheet — Deliberately Blank

Criteria and weights were locked at Gate 1. They are reproduced here so the Board sees them before the evidence, not after.

CriterionWeightScore
Strategic fit and portfolio coherence15%
Product and technical readiness25%
Regulatory and compliance readiness25%
Distribution readiness15%
Economics still supporting the case20%
Weighted total100%
The score column is blank because the gate has not convened. A draft package arriving with scores already filled in would be the Chair scoring the gate, and the Chair does not vote (D-11). The scale is 1–5 plus U — unscoreable. Any criterion for which defensible evidence does not exist is rated U rather than given a middling number, and a single U obliges the Chair to table a recycle. Gate 1 was not scored low; it was never scored.

5. Economics

MeasureValueNote
Base case return13.4%Against an 11.0% hurdle — clears by 240 bp
Downside scenario10.1%Does not clear. Disclosed at Gate 1, not closed
Volume tolerance to breakeven23%Roughly two fifths already consumed pre-launch
Program cost released to date$14,232,000Of $27,904,000 authorized

Nothing in the economics has changed since Gate 1. The business case is not being re-opened at this gate; it is being checked for whether anything has moved against it.

6. The Case for CANCEL

This section is mandatory and appears even when the Chair expects the gate to carry. The Chair does not vote. The obligation that comes with facilitating rather than deciding is to put the strongest available argument against proceeding in front of the people who do — not the weakest one, and not a strawman that makes the recommendation look inevitable.
  1. Written channel commitments stand at $168,000,000 against a $185,000,000 Year 1 target. GC-04 closed having surfaced the gap and without closing it. The program has consumed roughly two fifths of its volume tolerance before a policy has been sold.
  2. The downside scenario returns 10.1% against an 11.0% hurdle — it does not clear. No other program in the portfolio carries an approved case with a failing scenario in it.
  3. Two assumptions cannot be tested before the gate that depends on them (A-02, A-08). Releasing $7,450,000 at Gate 2 commits money against both.
  4. Stage 2 was compressed from 46 weeks to 41 to absorb the Gate 1 recycle. There is no remaining float to absorb a second problem, and MM-4 is currently a second problem.

The Chair's assessment of that case: it is serious and it is not yet sufficient. The base case clears the hurdle by 240 basis points on an independently checked capital charge, and every argument above describes a risk that is disclosed and monitored rather than one that has materialized. But the case would become sufficient if MM-4 fails and the response is to re-issue it as a condition rather than to fix it — because that would be the second consecutive gate at which hedging readiness was carried forward instead of closed.

7. Dissent

A dissent section is required in every gate package. It records positions held before the gate, so a member who intends to vote against is not discovering their own argument in the room.

MemberPosition recorded ahead of the gate
R. Castellanos, Head of DistributionHas indicated he will not support GO while the Year 1 commitment gap remains open, on the grounds that GC-04 demonstrated the condition mechanism cannot close it. Abstained at Gate 1 for the same reason.
D. Pemberton, CRO (observer, non-voting)Has asked that the hedging readiness position be presented by the CFO directly rather than summarized by the Chair.
All other membersNo position recorded at the time of drafting.

8. What the Chair Is Asking For

Not a decision — the decision belongs to the Board on 01 April 2027. What this draft asks for, 167 days out, is action on what it shows is missing.

AskOf whomBy when
Begin negotiation with the second derivatives counterparty, or bring a written alternativeCFO / InvestmentsImmediately — this is the only item that can remove GO from the table
Confirm the rider contract language timetable with outside counselGeneral CounselWithin 30 days
Table the launch-footprint threshold for decision at Gate 3Chair, with DistributionBefore the Gate 2 package is finalized
Record any intended dissent in writingAny voting memberTen business days before the gate
If MM-4 cannot be certified by the gate, the Chair will table RECYCLE rather than seek a sixth condition. That is stated here, in the draft, rather than reserved for the room — because a Board that learns the Chair's position at the gate has less time to change the outcome than a Board that learns it five months early.

Assembled by C. Tyrrell, NPD Program Manager and Chair of the Gate Review Board, with K. Iyer, PMO Lead. Related: Gate 2 Readiness Assessment · Gate Decision Framework · Gate Conditions Register · Program Dashboard.