← Aerospace Suite 00 · Program Foundations

Program Org Chart

Download PowerPoint

Program organization chart for the CWP-700 Composite Wing Panel Production Program — reporting structure across program, quality, and phase-specific roles, plus the customer source-inspection relationship. Download the PowerPoint for the full 2-slide deck (chart + role responsibility table).

Reporting Structure

RoleReports ToType
Program Manager (C. Tyrrell)Program lead
Quality Engineering Lead (R. Kessler)Program ManagerDirect report, full duration
Manufacturing Engineer (M. Osei)Program ManagerDirect report, full duration
Materials / NDT Engineer (L. Vance)Program ManagerDirect report, full duration
Supplier Quality Engineer (S. Pham)Program ManagerDirect report, full duration
Program Coordinator (D. Okafor)Program ManagerDirect report, full duration
Tooling Engineer (A. Whitfield)Quality Engineering Lead (matrixed)Phase 1 only
MRB Chair (J. Ferraro)Quality Engineering Lead (matrixed)Phase 2 only
Manufacturing Technicians — 3 total (K. Rutherford, T. Alvarado, C. Okwuosa)Manufacturing EngineerK. Rutherford full duration; Alvarado/Okwuosa Phase 2 only
Quality Inspectors — 2 total (B. Solis, N. Vasquez)Quality Engineering LeadB. Solis full duration; Vasquez Phase 2 only
Buyer / Procurement Specialist (R. Bianchi)Supplier Quality Engineer (matrixed)Phase 2 only
Meridian Aircraft Co. — Source InspectionExternal, dashed relationshipCustomer party, not billed to program

See the Resource Plan for FTE% and cost detail on each role, and Program Governance for the RACI behind these reporting lines.