← Federal Suite 02 · Planning & Compliance

Federal RACI

Download Word

Responsibility matrix spanning the contractor delivery team and the government-side roles (COR, CO, Sponsor). The key difference from a commercial RACI: government roles hold formal, contractual authority over acceptance and approval — not just stakeholder input.

The delivery team grew substantially under Contract Modification P00011 (see the Resource Plan and Org Chart for the full 35-person roster). Front-end, back-end, and infrastructure/data roles roll up under K. Lindqvist (Solutions Architect) for RACI purposes below rather than each carrying a separate column; QA carries its own column under N. Castellano (QA Lead) given the size and distinct surveillance role of that team.

RResponsible AAccountable CConsulted IInformed
Activity C. Tyrrell
TO PM
D. Ferris
Deputy PM
K. Lindqvist
Solutions Arch.
T. Abernathy
ISSO
P. Duvall
508 Lead
N. Castellano
QA Lead
M. Whitcombe
COR (Gov)
A. Reyes
CO (Gov)
R. Osei
Sponsor (Gov)
PWS interpretation / scope questionsARC---RA-
CDRL deliverable submissionARCCCCR--
CDRL deliverable acceptanceI-----ARC
Section 508 test plan & executionICC-ACR--
ATO / security authorization packageI-CA--R-I
Technical architecture decisionsCCAC--I--
Schedule / IMS maintenanceAR----I--
Contract modification requestR-----CAI
Program status reportingAR----R-I
Front-end / back-end build executionICA--C---
QA test execution (functional + regression)I-C-CAI--
Go-live / cutover decisionC-CCCCA-R
Data migration validation & sign-offA-R--CR--
Deliverable Acceptance Log sign-offI-----A--
QASP surveillance executionI-----AI-
Weekly / Monthly status report submissionAR----R-I
RAIDD Log risk/issue escalationARCCCCI--
Staffing changes / onboarding (post-Mod P00011)AR----I--
Option Period exercise decisionI-----CAR
Task Order closeout & CDRL closeout certificationAR----RR-