Inspection, Test & Verification Strategy

Download Word

How Acme Aerostructures proves that every CWP-700 composite wing panel delivered to Meridian Aircraft Co. conforms to specification — across Phase 1 qualification and First Article, and through Phase 2 rate production. This is the strategy that connects the AS9100 QMS (what the quality system requires), the First Article Inspection (proof the process can make a conforming part), and the Material Review Board (what happens when one doesn't). Those three documents own their subjects; this one owns how verification is designed, sequenced, and resourced across the whole program.

14
Quality & inspection staff
3
Shifts, Phase 2
4
NDT Level II technicians
100% → n
Sampling transition
Mo 14/18
Program status point
Why a composite structure is verified differently. A machined metal part can largely be inspected after the fact — the geometry is visible and measurable. A composite panel cannot. Its most critical properties, cure quality, void content, porosity, ply orientation, bond integrity, are created inside an autoclave and cannot be restored by rework once wrong. Verification therefore front-loads onto process control and non-destructive inspection, because by the time a panel exists, the strength you needed either got built into it or it did not.

01 Purpose, Scope & Document Boundaries

This strategy governs all verification performed on the CWP-700 program: incoming material, in-process, special process, non-destructive, destructive, dimensional, and final acceptance. It applies across both contract phases and all three production shifts.

Boundaries with adjacent quality documents

DocumentOwnsThis strategy adds
AS9100 QMSClause structure, QMS requirements, certification and audit cadence, product safety and counterfeit preventionHow verification activity satisfies Clause 8 in practice on this program
First Article InspectionThe AS9102 forms, the S/N 0001 checklist, the FAI gate itselfHow the program gets to a passing FAI, and what verification continues after it
Material Review BoardMRB composition, disposition types, escalation tiers, the MRB logHow nonconformances are detected and routed into MRB, and what happens after disposition

02 Verification Architecture

Verification follows the aerospace building-block principle: confidence is established at the lowest level first, so that a failure at panel level is a surprise rather than a routine outcome.

LEVEL 1
Material
Prepreg lot certification, PPAP, incoming inspection, out-time and freezer control
LEVEL 2
Process
Autoclave cure cycle validation, layup control, special process qualification
LEVEL 3
Coupon & witness
Mechanical test coupons and travelling witness panels cured with production hardware
LEVEL 4
Part
Dimensional, NDT, visual and workmanship verification of each panel
LEVEL 5
Acceptance
FAI, customer source inspection, Certificate of Conformance, delivery

How the phases differ

AspectPhase 1 — Qualification & First Article (6 months)Phase 2 — Production Ramp & Steady-State (12 months)
Purpose of verificationProve the process is capable of producing a conforming panelProve each panel conforms, and that the process stays capable at rate
Inspection intensity100% of characteristics, every panel100% of Key Characteristics; sampling on others once capability is demonstrated (Section 10)
Destructive testingExtensive — coupons, witness panels, cure validationReduced and periodic — witness panels per cure cycle, lot-based coupons
EmphasisEstablishing and validating the control planStatistical monitoring of the validated control plan

03 Standards & Specification Framework

StandardApplies toUse on CWP-700
AS9100DQuality management systemGoverning QMS; Clause 8 operational controls
AS9102First Article InspectionFAI forms 1–3 and the FAI gate into production
AS9145 / PPAPAdvanced product quality planning & part approvalSupplier PPAP submissions for raw material; control plan discipline
NADCAP special process accreditationComposites, NDT, bondingAccreditation maintained for in-house special processes; verified for external processors
NAS 410 / equivalentNDT personnel qualificationLevel II certification for all NDT technicians performing acceptance inspection
Meridian engineering source dataProduct definitionDrawings, specifications, tolerances and Key Characteristics — baselined per assumption A-01
ASTM / customer test methodsMechanical and physical testingCoupon test methods, void content, fiber volume fraction, glass transition temperature

04 Verification Organization

Fourteen quality and inspection staff, all onshore, phased in as the program scales from single-shift qualification to three-shift rate production.

NameRoleJoinsVerification responsibility
R. KesslerQuality Engineering Lead — AS9100 QMS OwnerPhase 1Owns this strategy, the control plan, FAI signature, QMS conformance
L. VanceMaterials / NDT EngineerPhase 1NDT method development, cure validation, coupon and witness-panel testing
S. PhamSupplier Quality Engineer (PPAP)Phase 1Supplier PPAP, incoming material verification, supplier audits
B. SolisQuality InspectorPhase 1Dimensional and visual inspection, in-process verification
J. FerraroMRB Chair / Sr. Quality EngineerPhase 2Chairs MRB; nonconformance disposition
N. VasquezQuality InspectorPhase 2Dimensional and visual inspection
R. AchebeNDT Technician, Level II — Shift 1Phase 2Ultrasonic inspection, acceptance disposition
K. SorensenNDT Technician, Level II — Shift 2Phase 2Ultrasonic inspection, acceptance disposition
B. WinfieldNDT Technician, Level II — Shift 3PA-002 (Jul 2027)Ultrasonic inspection, third-shift coverage
P. LarsenQuality Inspector — Shift 3PA-002 (Jul 2027)Third-shift dimensional and visual inspection
N. RedmondMRB Quality EngineerPA-002 (Jul 2027)MRB throughput support at increased rate
A. RestrepoSupplier Quality Engineer (PPAP)PA-002 (Jul 2027)Second supplier-quality resource for dual-source material
W. FairweatherIncoming Material InspectorPA-002 (Jul 2027)Incoming prepreg and detail-part verification
I. SondheimIncoming Material InspectorPA-002 (Jul 2027)Incoming prepreg and detail-part verification
Single-point-of-failure, named. Risk R-06 records that AS9100 QMS ownership sits with one individual (R. Kessler), and that an unplanned absence would stall both MRB dispositions and FAI signature — two gates that stop delivery outright. Mitigation is a designated deputy with signature authority for MRB disposition, plus J. Ferraro and N. Redmond carrying MRB capability independently from Phase 2 onward. A verification organization with one irreplaceable signature is a delivery risk, not just an HR one.

05 Key Characteristics & Control Plan Flow-Down

Not every dimension on a wing panel matters equally. Key Characteristics — those whose variation materially affects fit, structural performance, or safety — are identified from Meridian's engineering source data and flowed down into the control plan, the router, and the inspection method sheet.

Characteristic classExamples on CWP-700VerificationPhase 2 intensity
Key CharacteristicInterface hole positions, panel contour/profile, laminate thickness at load-bearing locations, bond-line integrityDimensional metrology, ultrasonic NDT, SPC-monitored100% — never sampled
Critical process parameterCure cycle temperature ramp, dwell, pressure, vacuum integrity, prepreg out-timeAutomated cure record, process monitoring, alarm on excursion100% of cycles, recorded
Standard characteristicEdge trim, non-structural dimensions, cosmetic finishDimensional and visual inspectionSampling once capability demonstrated
Lesson already learned on this program. Issue I-01 was a First Article dimensional nonconformance — edge trim out of tolerance on 2 of 8 panel positions on the initial tooling run. Edge trim is a standard characteristic, not a Key Characteristic, and it still stopped the FAI. The lesson embedded here: classification determines sampling intensity, not whether a characteristic is verified at all. Every characteristic on the drawing is verified; the classification only decides how often.

06 Incoming Material Verification

Composite material is perishable, single-sourced by default, and the origin of an entire panel's properties. It receives verification proportionate to that leverage.

ControlVerificationOwner
Supplier PPAPFull PPAP submission reviewed and approved before a lot is released to productionS. Pham / A. Restrepo
Certificate of AnalysisResin content, areal weight, tack, volatile content verified against specificationIncoming inspection
Lot traceabilityEvery panel traceable to prepreg lot, roll, and cure cycleQuality / router
Freezer & out-time controlCumulative out-time tracked per roll; material rejected at limit regardless of appearanceMaterials
Receiving inspectionPhysical condition, packaging integrity, documentation completenessW. Fairweather / I. Sondheim
Two decisions shaped this section. D-03 approved dual-source qualification of the primary prepreg rather than continuing single-source, in response to risk R-01 — which means incoming verification must now demonstrate equivalence between two qualified material sources, not merely conformance of one. D-04 established a standing quarterly PPAP review cadence with key raw-material suppliers rather than annual, to catch quality drift between formal submissions. Issue I-05 — a lot whose PPAP arrived missing a dimensional report, delaying qualification by three days — is exactly the drift that cadence exists to catch earlier.

07 Special Process Control

Composite layup, autoclave cure, bonding and NDT are special processes: their results cannot be fully verified by subsequent inspection of the product. Control is therefore exercised on the process and the operator, not only on the output.

Special processControl methodVerification evidence
Ply layupQualified operators; laser projection or template control of ply placement and orientationOperator certification records; in-process layup verification before bagging
Vacuum baggingLeak-down test to specification before cureRecorded vacuum integrity check — a failed bag is caught here, not after cure
Autoclave cureValidated cure cycle; thermocouple monitoring; automated cycle recordCure chart reviewed and accepted per cycle; excursions route to MRB
BondingSurface preparation control, environmental limits, qualified operatorsProcess records; witness coupons
NDTWritten technique, calibrated reference standards, NAS 410 Level II personnelTechnique sheets, calibration records, inspector certification

Operator qualification is verification too. Assumption A-05 — that the three manufacturing technician rotations qualified in Phase 1 remain available at planned allocation through Phase 2 — is a quality assumption as much as a staffing one, because an unqualified operator on a special process invalidates the control regardless of what the inspection finds afterward.

08 Non-Destructive Testing Strategy

Ultrasonic inspection is the primary means of detecting the defects that matter most in a cured composite panel — porosity, voids, delamination, and disbonds — none of which are visible externally. It is also the program's principal verification bottleneck.

AspectApproach
MethodUltrasonic (through-transmission and pulse-echo as applicable) against calibrated reference standards containing known defect sizes
Coverage100% of structural area on every panel — NDT is never sampled, in either phase
PersonnelNAS 410 Level II certified technicians; Level III oversight for technique approval and disposition of marginal indications
Acceptance criteriaPer Meridian specification; indications above threshold route to MRB rather than being dispositioned at the inspection station
CapacityFour Level II technicians across three shifts by PA-002 (Achebe, Sorensen, Winfield, plus qualification depth)
The bottleneck is real and was realized. Risk R-02 anticipated that NDT capacity might not scale with the Phase 2 rate. Issue I-02 records that it did: an NDT queue backlog formed during early Phase 2 ramp, adding roughly four days to panel release cycle time. Decision D-01 resolved it deliberately — qualify a second NDT technician in-house rather than outsource ultrasonic inspection, explicitly to keep traceability in-house. That trade is worth naming: outsourcing would have cleared the queue faster, but would have placed acceptance evidence for a flight-critical structure outside Acme's own traceability chain.

09 Destructive, Dimensional & Measurement Verification

Destructive and mechanical testing

TestPurposeCadence
Travelling witness panelsCured alongside production hardware; verify the cure actually achieved required propertiesPer cure cycle
Mechanical couponsStrength and stiffness verification against design allowablesPer material lot; more extensively in Phase 1
Void content / fiber volume fractionConfirm laminate quality achievedPer lot and on cause
Glass transition temperature (Tg)Confirm degree of curePer lot and after any cure excursion

Dimensional verification and measurement system analysis

Panel contour and interface features are verified by coordinate metrology against the digital product definition. Before any measurement system is relied upon for acceptance, it is itself verified: Gage R&R studies confirm that observed variation reflects the part rather than the measurement. A capability index computed from an unqualified gauge is a number without meaning, and on a program that transitions to sampling on the strength of capability data, that distinction is load-bearing.

10 Statistical Process Control & the Sampling Transition

This is the central strategic decision in any production ramp: when, and on what evidence, does 100% inspection give way to sampling?

The governing rule on CWP-700. Sampling is earned, never assumed. A characteristic moves from 100% inspection to sampling only when it has demonstrated sustained statistical capability, and it returns to 100% immediately if capability degrades. Key Characteristics and NDT never transition, regardless of how good the data looks — because the consequence of an escape on those is not scrap, it is a structural finding on a flying aircraft.
StageInspection basisEvidence required to advance
Qualification (Phase 1)100% of all characteristics, every panelFAI passed; control plan validated
Early ramp (Phase 2 start)100% continues while capability data accumulatesSufficient consecutive conforming panels to establish control limits
Demonstrated capabilityStandard characteristics move to defined sampling; SPC charts monitor continuouslyProcess capability sustained above agreed threshold, with a stable, in-control chart
Steady stateSampling on standard characteristics; 100% on Key Characteristics and NDTOngoing SPC monitoring; periodic audit of sampled characteristics
Capability lossImmediate reversion to 100%Root cause found and corrected; capability re-demonstrated before sampling resumes

Control charts are reviewed by shift, not only in aggregate. A process that is capable overall but drifting on third shift is a real and common failure mode on a three-shift operation — and one that a monthly aggregate capability number would conceal entirely.

11 Nonconformance Detection & MRB Interface

The MRB owns disposition. This strategy owns what reaches it, and how quickly.

StageRequirement
DetectionAny characteristic outside specification is documented at the point of detection — inspectors do not disposition at the station
ContainmentNonconforming hardware physically segregated and identified before the shift ends; suspect population bounded by lot and cure cycle traceability
RoutingNonconformance record raised with objective evidence — measurement data, NDT indication, cure chart — not a narrative description
DispositionMRB per its own escalation tiers; use-as-is and repair dispositions on Key Characteristics require customer concurrence
ClosureCorrective action verified effective before the record closes — not when the action is implemented, but when it is shown to have worked
Throughput is a quality control. Issue I-03 records an MRB backlog that held two nonconforming panel sets in disposition-pending status for three days at peak Phase 2 volume. A disposition queue is not a neutral delay: it creates pressure to disposition quickly rather than correctly, and it consumes floor space that encourages hardware to be moved before it is cleared. Adding N. Redmond as a dedicated MRB Quality Engineer under PA-002 was a verification-integrity decision, not merely a capacity one.

12 Customer Verification & Source Inspection

ActivityApproachRisk managed
FAI witnessMeridian source inspector witnesses First Article; scheduling confirmed well ahead of the FAI windowR-04 — customer source-inspection availability bottlenecking the FAI gate
Acceptance criteria clarityEvery FAI checklist criterion written to be unambiguous to an external auditor before submissionI-04 — two criteria found ambiguous by the customer's auditor, risking inconsistent future interpretation
Certificate of ConformanceIssued per shipment with full traceability to lot, cure cycle, NDT record and inspection resultsDelivery acceptance
Ongoing source inspectionPer Meridian's surveillance arrangement; Acme maintains inspection records available for audit at any timeCustomer confidence; audit readiness
Engineering changeAny post-CDR change routed through formal contract modification per assumption A-04; re-FAI triggered where AS9102 requiresConfiguration integrity
Why I-04 mattered more than its size suggests. Two ambiguously worded acceptance criteria were caught by Meridian's source-inspection auditor. Nothing nonconforming shipped, and the immediate fix was small. But ambiguous acceptance criteria are how two organizations come to hold different beliefs about what "conforming" means — and that disagreement surfaces at the worst possible moment, on a panel already built. Clarity in acceptance criteria is a verification control in its own right.

13 Rate Readiness Verification

Purchase Order Amendment PA-002 increased the monthly production rate, adding a third shift and expanding quality staffing (decision D-06). A rate increase is a change to the process, and is verified as one.

14 Quality Metrics

MetricWhat it revealsTarget
First Pass YieldWhether the process makes a conforming panel without reworkImproving trend through ramp; stable at steady state
Escape rate to customerEffectiveness of the entire verification chainZero
Process capability by characteristic and shiftWhether sampling remains justifiedSustained above threshold; reviewed per shift
NDT cycle time and queue depthLeading indicator of the R-02 bottleneck recurringWithin takt; queue not growing
MRB disposition turnaroundWhether disposition pressure is building (I-03)Within agreed turnaround; no aging backlog
Scrap and rework costFinancial consequence of quality performance on a fixed-price contractDownward trend
Supplier PPAP on-time and completeIncoming material risk (I-05, A-03)100% complete on first submission

15 Risks to the Verification Approach

RiskEffect on verificationMitigation
R-02 — NDT capacity does not scale with rateInspection becomes the constraint; pressure to reduce coverageIn-house technician qualification (D-01); queue depth monitored as a metric; coverage never reduced
R-06 — QMS ownership concentrated in one individualMRB disposition and FAI signature stallDeputy signature authority; MRB capability held by Ferraro and Redmond independently
R-01 — single-source prepreg lead timeMaterial shortage forces schedule pressure onto verification windowsDual-source qualification (D-03); incoming verification proves source equivalence
R-04 — customer source-inspection availabilityFAI gate waits on customer schedulingWitness scheduling confirmed early; internal readiness complete before the window opens
Rate pressure eroding sampling disciplineSampling extended to characteristics that have not earned itSampling tied explicitly to demonstrated capability; reversion rule is automatic, not discretionary
Governing relationship. This strategy operates under the AS9100 QMS and the Program Management Plan. It is the parent of the control plan, inspection method sheets, and NDT technique documents. Changes affecting Key Characteristics, acceptance criteria, or inspection frequency require Quality Engineering approval and, where they touch customer-defined requirements, Meridian concurrence through the formal change process.