← Agile/Scrum Suite 24 · Governance & Stakeholder

Program Budget

Delivery LeadC. Tyrrell
As OfMay 15, 2026 (Closeout)
StatusClosed — Within Budget
Download Excel
Overview

Program Budget at a Glance

Original Budget
$1,790,000
Current Baseline
$1,850,000
Final Actual
$1,810,000
Variance to Baseline
-2.2%
Breakdown

Cost by Category

Final actuals as of program closeout (May 15, 2026).
CategoryBaselineActualVariance
Internal Labor — Team Falcon (Mobile, 5 FTE)$520,000$512,000-$8,000
Internal Labor — Team Anchor (Platform, 5 FTE)$540,000$556,000+$16,000
Product Owner / Agile Delivery Lead$126,000$126,000$0
Scrum Masters (2)$168,000$168,000$0
Video SDK Vendor License & Support (PulseConnect)$210,000$210,000$0
Cloud Infrastructure (staging + production)$96,000$114,000+$18,000
Data Migration Contractor Support$0$42,000+$42,000
Legacy Vendor (Vantix) Offboarding & Decommission Fees$45,000$45,000$0
App Store / Play Store Fees & Compliance Tooling$18,000$16,000-$2,000
Subtotal (Base Budget)$1,723,000$1,789,000+$66,000
Contingency Reserve (10% of base, drawn as needed)$127,000$21,000-$106,000
TOTAL PROGRAM BUDGET$1,850,000$1,810,000-$40,000

The two categories with cost impact — Cloud Infrastructure (+$18,000) and Data Migration Contractor Support (+$42,000) — both trace to approved Change Requests (CR-01 and CR-02). See the Change Control Log for full detail. Both were absorbed within the Contingency Reserve, which is why the program closed 2.2% under its current baseline despite two approved cost increases.

Reconciliation

Budget Baseline History

How the $1,790,000 original budget grew to the $1,850,000 current baseline, and why two specific categories above show variance.
ItemAmount
Original program budget (pre-CR)$1,790,000
CR-01 — Additional Staging/Load-Test Environment (Cloud Infrastructure)+$18,000
CR-02 — Contractor Support for Sprint 7 Migration Remediation+$42,000
Current Baseline (approved, used for closeout reporting)$1,850,000

The "Baseline" column in the Cost by Category table above shows each category's original pre-CR allocation — which is exactly why Cloud Infrastructure ($96,000 baseline, $114,000 actual) and Data Migration Contractor Support ($0 baseline, $42,000 actual) show variance of precisely +$18,000 and +$42,000: those two variances are CR-01 and CR-02, fully accounted for with no unexplained overrun beyond what was approved. Full impact detail for both is in the Change Control Log. CR-03 (extending the pre-cutover compliance review window) was schedule-only and carried no budget impact, which is why it doesn't appear in this reconciliation.

Labor

Resource Rate Card (Named Roster)

Blended bill rates, benchmarked against 2026 U.S. software/telehealth market data. 18-week program duration used for full-program estimates.
ResourceRoleBlended RateEst. Labor Cost
C. TyrrellProduct Owner & Agile Delivery Lead$175/hr$126,000
J. MarshScrum Master, Team Falcon$140/hr$100,800
R. OkaforScrum Master, Team Anchor$140/hr$100,800
D. WhitfieldEngineering Lead, Team Falcon$165/hr$118,800
A. SinghEngineering Lead, Team Anchor$165/hr$118,800
K. AlvareziOS Developer$135/hr$97,200
S. ParkAndroid Developer$135/hr$97,200
R. KimBackend/Mobile API Developer$135/hr$97,200
N. OseiQA Engineer, Team Falcon$110/hr$79,200
4 additional Anchor engineersBackend/Platform Developers$130/hr$374,400
Dr. L. NguyenCMIO (advisory allocation, ~10%)$210/hr$15,120
T. BranniganCompliance/Security Director (advisory allocation, ~10%)$180/hr$12,960
TOTAL (Named Roster)$1,338,480
Remaining budget covers vendor licensing, infrastructure, and contingency shown in the category breakdown above.
Governance

Baseline Approval & Sign-Off

The $1.85M current baseline (original $1.79M + 2 approved cost-impact CRs) required Sponsor approval per this program's decision-rights tiering — lighter-weight than the Enrollment & Claims program's Steering Committee approval chain, appropriate to a program of this size.
NameRoleStatusDate
M. DelacroixExecutive Sponsor, VP Digital HealthSignedJan 5, 2026
C. TyrrellProduct Owner & Agile Delivery Lead (Author)SignedJan 5, 2026
Both approved cost-impact CRs (CR-01, CR-02) were approved directly by M. Delacroix without requiring a full re-baseline vote, per this program's lighter governance model — see Change Control Log.