Program Budget at a Glance
Cost by Category
| Category | Baseline | Actual | Variance |
|---|---|---|---|
| Internal Labor — Program Leadership & SMEs (6) | $432,000 | $432,000 | $0 |
| Internal Labor — Team Falcon (Mobile, 11 FTE) | $1,279,000 | $1,279,000 | $0 |
| Internal Labor — Team Anchor (Platform, 11 FTE) | $1,279,000 | $1,279,000 | $0 |
| Video SDK Vendor License & Support (PulseConnect) | $210,000 | $210,000 | $0 |
| Cloud Infrastructure (staging + production) | $110,000 | $128,000 | +$18,000 |
| Data Migration Contractor Support (Sprint 7 surge) | $0 | $42,000 | +$42,000 |
| Legacy Vendor (Vantix) Offboarding & Decommission Fees | $45,000 | $45,000 | $0 |
| App Store / Play Store Fees & Compliance Tooling | $20,000 | $18,000 | -$2,000 |
| Subtotal (Base Budget) | $3,375,000 | $3,433,000 | +$58,000 |
| Contingency Reserve (10% of base, drawn as needed) | $338,000 | $198,000 | -$140,000 |
| TOTAL PROGRAM BUDGET | $3,713,000 | $3,631,000 | -$82,000 |
Even with data migration now permanently owned by a dedicated specialist (P. Haddad), a short Sprint 7 contractor surge (CR-02) was still needed for the final push — the same event as before the staffing correction, now layered on top of a real team instead of substituting for one. The two categories with cost impact — Cloud Infrastructure (+$18,000) and Data Migration Contractor Support (+$42,000) — both trace to approved Change Requests (CR-01 and CR-02). See the Change Control Log for full detail. Both were absorbed within the Contingency Reserve, which is why the program closed 2.2% under its current baseline despite two approved cost increases.
Budget Baseline History
| Item | Amount |
|---|---|
| Original program budget (pre-CR, corrected per DEC-06) | $3,653,000 |
| CR-01 — Additional Staging/Load-Test Environment (Cloud Infrastructure) | +$18,000 |
| CR-02 — Contractor Support for Sprint 7 Migration Remediation | +$42,000 |
| Current Baseline (approved, used for closeout reporting) | $3,713,000 |
The "Baseline" column in the Cost by Category table above shows each category's original pre-CR allocation — which is exactly why Cloud Infrastructure ($110,000 baseline, $128,000 actual) and Data Migration Contractor Support ($0 baseline, $42,000 actual) show variance of precisely +$18,000 and +$42,000: those two variances are CR-01 and CR-02, fully accounted for with no unexplained overrun beyond what was approved. Full impact detail for both is in the Change Control Log. CR-03 (extending the pre-cutover compliance review window) was schedule-only and carried no budget impact, which is why it doesn't appear in this reconciliation. The $3,653,000/$3,713,000 figures already reflect the DEC-06 staffing correction (13→28 people) made before Sprint 1 Planning — that correction is not itself a Change Request, since it predates any approved baseline and is documented instead in the RAIDD Log.
Resource Rate Card (Named Roster)
The full 28-person named roster, per-person blended rate, FTE%, and program cost lives in the Team Resource Plan — reproducing it here as a second table risked drifting out of sync with the authoritative version, which is exactly what happened to this section before the DEC-06 correction. The category subtotals above ($432,000 / $1,279,000 / $1,279,000) trace directly to that roster's own subtotals with zero variance.
Baseline Approval & Sign-Off
| Name | Role | Status | Date |
|---|---|---|---|
| M. Delacroix | Executive Sponsor, VP Digital Health | Signed | Jan 5, 2026 |
| C. Tyrrell | Agile Delivery Lead (Author) | Signed | Jan 5, 2026 |