Program Kickoff Meeting Notes

Download Word
DateJan 5, 2026
Time10:00–11:30 AM CT
LocationFalcon/Anchor War Room + Video Bridge
FacilitatorC. Tyrrell
SprintSprint 0, Day 1

Attendees

C. TyrrellProduct Owner & Agile Delivery Lead
M. DelacroixExecutive Sponsor, VP Digital Health
Dr. L. NguyenChief Medical Information Officer
T. BranniganDirector, Information Security & Compliance
J. MarshScrum Master, Team Falcon
R. OkaforScrum Master, Team Anchor
D. WhitfieldEngineering Lead, Team Falcon
A. SinghEngineering Lead, Team Anchor
Full Falcon & Anchor rosters10 engineers total (see Team Charter)

Purpose

Align both teams and all stakeholders on the program vision, success metrics, delivery model, and working agreement before Sprint 1 begins. This is a one-time program-level kickoff — each subsequent sprint gets its own Sprint Planning session, not a repeat of this meeting.

Agenda

TimeTopicLed By
10:00–10:10Welcome & program context (why CareLink Classic is being replaced)M. Delacroix
10:10–10:25Vision & Roadmap walkthrough, success metrics/OKRsC. Tyrrell
10:25–10:35Clinical & patient-safety considerations for this programDr. L. Nguyen
10:35–10:45HIPAA/compliance guardrails & the review-gate modelT. Brannigan
10:45–11:05Delivery model: two-team Scrum, Scrum-of-Scrums, ceremony cadence, Definition of Ready/DoneC. Tyrrell
11:05–11:20Team introductions & working agreement discussion/buy-inJ. Marsh / R. Okafor
11:20–11:30Open Q&A, next steps (environment setup, backlog seeding begins today)C. Tyrrell

Key Discussion Points

Decisions Made

Decision 1Definition of Done updated to require clinical workflow sign-off from Dr. Nguyen for any story touching scheduling, visit launch, or provider notes handoff.
Decision 2Compliance review checkpoint added before both Release 1 and Release 2 cutover (not a single end-of-program gate).
Decision 3Scrum-of-Scrums cadence set at 2x/week, 15 minutes, cross-team dependencies only — confirmed in the Team Charter.